Loading...
HomeMy WebLinkAbout2560400 - CEMP Construction & Environmental Management Plan Development: Clones Single Turbine, Co. Monaghan Applicant: Art Generation Limited Report Date: 30/09/2025 Document Ref. No.: 22790-CEMP-P1 RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 1 Table of Contents 1.0 Introduction ......................................................................................... 5 1.1 Development Description.................................................................................................. 5 1.2 Scope .................................................................................................................................. 5 1.3 Report Layout .................................................................................................................... 5 1.4 Statement of Authority ...................................................................................................... 5 1.5 CEMP Objectives ............................................................................................................... 6 1.6 Live Document ................................................................................................................... 6 2.0 Overview of Existing Site ................................................................... 7 2.1 Site Location ...................................................................................................................... 7 3.0 Proposed Development ...................................................................... 8 3.1 Description ......................................................................................................................... 8 3.2 Wind Farm Site Layout ...................................................................................................... 8 3.3 Grid Connection Route ..................................................................................................... 9 4.0 Ulster Canal Greenway ..................................................................... 10 5.0 Construction Management .............................................................. 11 5.1 Duration and Phasing of the Proposed Development .................................................. 11 5.2 Construction Hours ......................................................................................................... 12 5.3 Employment ..................................................................................................................... 12 5.4 Roles and Responsibilities ............................................................................................. 12 5.4.1 Developer .............................................................................................................................. 12 5.4.2 Construction Manager ......................................................................................................... 13 5.4.3 Ecological Clerk of Works ................................................................................................... 13 5.4.4 Project Supervisor Design Process (PSDP) ...................................................................... 14 5.4.5 Project Supervisor Construction Stage (PSCS) ................................................................ 14 5.4.6 Designers .............................................................................................................................. 15 5.4.7 Project Archaeologist .......................................................................................................... 15 5.4.8 Project Ecologist .................................................................................................................. 15 5.4.9 Project Hydrologist .............................................................................................................. 16 5.4.10 Project Geotechnical Engineer ........................................................................................... 16 5.4.11 Community Liaison Manager .............................................................................................. 16 5.4.12 Contractor ............................................................................................................................. 16 5.4.13 Site Manager ......................................................................................................................... 17 5.4.14 Health, Safety, Environmental and Quality (HSEQ) Officer .............................................. 17 5.4.15 Traffic Management Coordinator ........................................................................................ 17 5.5 Vehicles, Plant and Equipment ....................................................................................... 17 5.6 Pre-Construction Surveys & Detailed Design ............................................................... 18 5.6.1 Pre-Construction Surveys ................................................................................................... 18 5.6.2 Construction Stage Detailed Design .................................................................................. 18 5.7 Development Construction Works ................................................................................. 19 5.7.1 Enabling Works .................................................................................................................... 19 5.7.2 Site Drainage ........................................................................................................................ 19 5.7.3 Topsoil Stripping .................................................................................................................. 19 RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 2 5.7.4 Site Entrances ...................................................................................................................... 19 5.7.5 Internal Access Track .......................................................................................................... 20 5.7.6 Excavated Track ................................................................................................................... 20 5.7.7 Stone Aggregate and Fill Requirements ............................................................................ 21 5.7.8 Stone Aggregate Specification ........................................................................................... 21 5.7.9 Spoil Management Plan ....................................................................................................... 22 5.7.10 Excavated Material Use ....................................................................................................... 22 5.7.11 Management of Excavated Material.................................................................................... 22 5.7.12 Substation............................................................................................................................. 23 5.7.13 Internal Underground Cabling ............................................................................................ 23 5.7.14 Wind Turbine ........................................................................................................................ 24 5.7.15 Wind Turbine Hardstands ................................................................................................... 24 5.7.16 Turbine Foundation ............................................................................................................. 25 5.7.16.1 Wind Turbine Erection ......................................................................................................... 27 5.7.17 Reinstatement ...................................................................................................................... 28 5.7.18 Commissioning .................................................................................................................... 28 5.7.19 Decommissioning ................................................................................................................ 29 5.8 Construction in a Flood Zone ......................................................................................... 29 5.9 Turbine Delivery Route ................................................................................................... 29 5.10 Grid Connection Works ................................................................................................... 30 5.10.1 Cable Trenching Methodology ............................................................................................ 30 5.10.2 Managing Excess Material from Trench ............................................................................. 32 5.10.3 Cable Ducting Methodology ................................................................................................ 32 5.10.4 Joint Bays ............................................................................................................................. 33 5.10.5 Surface Cable Markers & Marker Posts ............................................................................. 33 5.10.6 Crossings ............................................................................................................................. 34 5.10.7 Existing Underground Services .......................................................................................... 34 5.10.8 Watercourses ....................................................................................................................... 34 5.10.9 Bridges .................................................................................................................................. 34 5.10.10 Culverts ................................................................................................................................. 34 5.10.11 Horizontal Directional Drilling Methodology ..................................................................... 35 5.11 Consents .......................................................................................................................... 36 6.0 Safety, Health and Welfare at Work ................................................ 37 6.1 Construction Compound and Facilities ......................................................................... 37 6.2 Safety and Security ......................................................................................................... 38 6.3 Site Access....................................................................................................................... 38 6.4 Signage ............................................................................................................................. 38 6.4.1 Site Signage.......................................................................................................................... 39 6.4.2 Signage on the Public Road ................................................................................................ 39 7.0 Environmental Management ............................................................ 40 7.1 Ecology Impact Mitigation .............................................................................................. 40 7.2 Mitigation to prevent the spread of non-native invasive plant species ...................... 40 7.3 Mitigation measures for spoil disposal .......................................................................... 41 7.4 Mitigation by Remediation .............................................................................................. 42 7.5 Bird Impact Mitigation ..................................................................................................... 42 7.6 Protection of Bats ............................................................................................................ 42 RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 3 7.7 Noise and Vibration Mitigation ....................................................................................... 42 7.8 Dust Mitigation Measures ............................................................................................... 43 7.9 Fuels and Oils Management ........................................................................................... 43 7.10 Climate .............................................................................................................................. 44 7.11 Surface Water Management Plan ................................................................................... 44 7.11.1 Design Principles ................................................................................................................. 44 7.11.2 Design Methods ................................................................................................................... 44 7.11.3 General Drainage Provisions .............................................................................................. 45 7.11.4 Buffer Zones ......................................................................................................................... 45 7.11.5 Office of Public Works Section 50 Approval ..................................................................... 46 7.11.6 Watercourse Crossings ....................................................................................................... 46 7.11.7 Culvert Crossings ................................................................................................................ 46 7.11.8 Stream Crossing – Bridge Installation ............................................................................... 46 7.11.9 Maintenance and Inspection Protocols.............................................................................. 46 7.11.10 Control Measures ................................................................................................................. 47 7.11.11 Surface Water Drainage Measures ..................................................................................... 48 7.11.11.1 Construction Stage ........................................................................................................ 48 7.11.11.2 Operation Stage Measures – the Permanent Works ................................................... 48 7.11.11.3 Decommissioning Phase ............................................................................................... 49 7.11.11.4 Clean Water Cut-off Drains ............................................................................................ 49 7.11.11.5 Dirty Water Cut-off Drains ............................................................................................. 49 7.11.11.6 Silt Fencing ..................................................................................................................... 50 7.11.11.7 Check Dams .................................................................................................................... 51 7.11.11.8 Swales ............................................................................................................................. 52 7.11.11.9 Buffered Outfalls ............................................................................................................ 52 7.11.11.10 Settlement Ponds ......................................................................................................... 53 7.11.11.11 Silt Buster ..................................................................................................................... 54 7.11.11.12 Vegetation Filters ......................................................................................................... 55 7.11.11.13 Level Spreaders ............................................................................................................ 55 7.12 Land, Soils, and Geology ................................................................................................ 56 7.13 Site Meetings.................................................................................................................... 56 7.14 Toolbox Talks ................................................................................................................... 56 7.15 Site Monitoring ................................................................................................................. 57 7.16 Complaints ....................................................................................................................... 57 8.0 Waste Management Plan .................................................................. 58 8.1 Objectives ........................................................................................................................ 58 8.2 Anticipated Waste Streams............................................................................................. 58 8.3 Separation & Handling .................................................................................................... 59 8.4 Waste Description and Management Principles ........................................................... 60 8.5 Concrete ........................................................................................................................... 61 8.6 Metal ................................................................................................................................. 61 8.7 Wood /Timber ................................................................................................................... 61 8.8 Packaging ......................................................................................................................... 61 8.9 General Wastes ................................................................................................................ 62 8.10 Hazardous Materials ........................................................................................................ 62 RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 4 8.11 Other materials ................................................................................................................ 63 8.12 Responsibilities ............................................................................................................... 63 8.13 Signage ............................................................................................................................. 63 8.14 Permitted or Licensed Waste Collectors ....................................................................... 64 9.0 Summary ............................................................................................ 65 Document Control Author(s) Date Reviewed by Review Date Revision Status Comment Name Signature Name Signature E. Roche Project Engineer 30/09/2025 B. McGinn Chartered Engineer 30/09/2025 P1 Finalised For Planning RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 5 1.0 Introduction This Construction and Environmental Management Plan (CEMP) has been developed by Mable Consulting Engineers on behalf of ART Generation Limited (the applicant), who intend to apply to Monaghan County Council for planning permission to construct a single Wind Turbine Development and associated infrastructure to be located in the townlands of Carney's Island, Altartate Glebe, Legarhill, and ClonavillaCo. Monaghan. This CEMP has been prepared in conjunction with the Planning and Environmental Report (PER) which will accompany the planning application for the proposed Development. This CEMP is to be read in conjunction with the following documents:-  Traffic Management Plan (TMP);  The Planning Drawings. 1.1 Development Description A detailed description of the proposed Development is contained within the Planning and Environmental Report that accompanies the planning application. 1.2 Scope This CEMP details the construction and environmental management measures which will be implemented during the construction and decommissioning of the Development. The CEMP compiles the various mitigation measures identified in the various reports carried out in relation to the environment and details work methodologies and systems to be put in place as part of the proposed mitigation measures. 1.3 Report Layout The CEMP is structured as follows:-  Section 1 – Introduction;  Section 2 – Overview of Existing Site;  Section 3 – Proposed Development  Section 4 – Ulster Canal Greenway;  Section 5 – Overview of the Construction Works;  Section 6 – Safety, Health and Welfare at Work;  Section 7 – Environmental Management;  Section 8 – Waste Management Plan (WMP);  Section 9 – Summary. 1.4 Statement of Authority This CEMP has been prepared by Mr. Barry McGinn and Mr. Eoin Roche of Mable Consulting Engineers Limited. Mr. Barry McGinn is a Chartered Engineer with over 28 years’ experience in the design, construction and project management of civil and structural engineering projects including; Wind Farms, Solar Farms, Battery Storage, Electrical Substations, Flood Alleviation, and multiple other Project types. Barry is a member of Engineers Ireland and holds a BSc(Eng) in Structural Engineering, BEng (Ord) in Civil Engineering and Post Graduate Diplomas in Planning and Environmental Law, Construction Law & Contract Administration and Project Management. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 6 Mr. Eoin Roche is a Project Engineer with over 5 years of experience in the design and construction of civil and structural engineering works, as well as renewable energy infrastructure projects. His portfolio includes Wind Farms, Solar Farms, Battery Energy Storage Systems (BESS), Synchronous Compensators and Electrical Substations. Eoin holds a Bachelor of Engineering (Hons) in Structural Engineering and a Postgraduate Diploma (Distinction) in Sustainable Energy and the Environment. 1.5 CEMP Objectives Key aims for the Development are:-  To ensure the Development is constructed and commissioned in a safe and timely manner and within the Development budget;  To ensure the Development is undertaken in accordance with best construction and environmental practices;  To ensure construction activities adhere to all relevant environmental regulations and standards  To ensure that construction activities are carried out in accordance with all planning conditions for the proposed Development;  To ensure that construction activities have minimal impact/ disturbance to local landowners and the local community;  To ensure that construction activities have minimal impact on the natural environment;  To adopt a sustainable approach to construction; and  To provide adequate training and awareness to all construction site personnel. The key objectives of this CEMP are:-  Appointment of a suitability qualified and experienced design and construction team to oversee the construction of the Development;  Delegation of clear lines of responsibility within the design and construction team for monitoring construction and environmental compliance and adherence to this CEMP;  Provide appropriate levels of training to ensure the design and construction team are up to date with construction and environmental best practice and legislative changes;  Establishment of documented schedules and records for monitoring and inspections;  Establishment of reporting procedures for incidents on site;  Provide opportunities for community feedback and submission of complaints; and  Adoption of a sustainable and socially responsible approach to construction. 1.6 Live Document This CEMP is considered a ‘live’ document and as such will be reviewed and updated as required during the construction stage design and as required during the construction works. Updates to the CEMP may be required due to changes in legislation or due to changes in construction and environmental best-practices. Updates may also be required to incorporate measures for compliance with any conditions of planning by the Local Authority. Prior to commencement of construction works, this CEMP will be further developed by the construction contractor to the requirements of the Local Authority and other appropriate Stakeholders and incorporated into its construction management systems. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 7 2.0 Overview of Existing Site 2.1 Site Location The proposed Development is located in the townlands of Carney’s Island, Altartate Glebe, Clonavilla, and Legarhill Co. Monaghan. The site is within an agricultural landscape and is approximately 2km from Clones Town, County Monaghan. The site has an area of approximately 7.64 hectares (ha) and comprises a number of private land parcels. The closest town / village is Clones Town, 2km north-west of the Development. The proposed Development is serviced by the regional public road the R183. The R183 runs to the south of the site between Clones and Newbliss. The R183 connects to the N54 in Clones. Bishop’s Lough lies to the south-west of the site, while the Finn River flows further to the east. The Ulster Canal also travels through the site. The location of the site is outlined in red in Figure 2-1 below. Figure 2-1 – Site Location – Site outlined in red RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 8 3.0 Proposed Development 3.1 Description The development will consist of the construction of a Single Turbine Wind Farm development on a 7.64-hectare site consisting of:- a) A single 4.8-megawatt (MW) Wind Turbine with an overall tip height of 143.8 metres, comprising a rotor diameter of 133.2m and a hub height 78m; b) Wind turbine foundation, crane hardstanding and assembly area; c) Temporary Construction Compound; d) Upgrade of an existing field entrance to new wind farm site entrance; e) Upgrading and widening of existing access tracks; f) New access tracks; g) A new 10.5m clear span bridge crossing an existing stream; h) Demolition of the ruinous remains of two old stone buildings; i) An on-site 20kV electrical substation; j) Electrical and communication cabling within private lands; k) Underground 20kV grid connection within private lands and within the R183 public road connecting to the existing ESB Clones 38kV Substation; l) Tree felling, landscaping and reinstatement works; and m) All associated ancillary works. 3.2 Wind Farm Site Layout A layout of the proposed Wind Farm is shown on in Figure 3-1 below, further detail is contained in the Planning Drawings 22790-100 to 103. Figure 3-1 – Proposed Wind Farm Layout RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 9 A schedule of the proposed Wind Turbine and its corresponding grid co-ordinates (ITM) is set out in Table 3-1. Turbine ID ITM Coordinates Easting: Northing: Turbine 1 (T1) 652228 826431 Table 3-1 – Proposed Wind Turbine Coordinates 3.3 Grid Connection Route The proposed grid connection from the Development will be by means of 1.9km of 20kV underground cable connecting to the existing ESB Networks Clones 38kV Substation via private lands and the public road network. The grid route is shown in Figure 3-2 below, further detail on the Grid Connection construction and crossings is contained in Section 5.10 and in the Planning Drawings 22790-102 to 105. Figure 3-2 - Layout of Grid Route RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 10 4.0 Ulster Canal Greenway Waterways Ireland, in partnership with Monaghan County Council and in association with the Department of Transport, is progressing the Development of the Ulster Canal Greenway, a proposed network of Greenway routes. The Greenway will follow the alignment of the former Ulster Canal and sections of disused railway corridors, providing connections between key towns, villages, and tourist attractions across the mid-Ulster region. The Greenway is a work in progress. Phases 1 and 2 of the proposed Greenway are already open, and planning is underway for Phase 3 of the Development. Phase 3 of the Greenway scheme is presently at the options appraisal stage, and a preferred route has not yet been determined. Three route options are currently under consideration, each of which passes through the Development site. The site layout has been designed to accommodate the Greenway for each of the three potential alignments, with indicative designs provided on planning drawings 22790-101 to 22790-103. The designs ensure that the Development will not affect the delivery or future implementation of Phase 3 of the Greenway. Figure 4-1 gives detail on the interaction between the greenway and the proposed Development, further detail is contained in the Planning Drawing 22790-103. Prior to commencement of the works, this CEMP will be further developed by the appointed contractor. As part of the preparation of the construction stage CEMP, the Developer & Contractor will liaise with Monaghan County Council in relation to the new Greenway scheme and incorporate it requirements into the detailed plan. Figure 4-1 – Ulster Canal Greenway Phase Options with Development Overlay RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 11 5.0 Construction Management 5.1 Duration and Phasing of the Proposed Development It is anticipated that the overall construction of the Development will take approximately 12 months from starting on-site to final commissioning of the Wind Turbine. All vegetation clearance that is required for the construction works will be carried outside the bird breeding season, which runs from the 1st of March to the 31st of August. To comply with this requirement a section of the initial Civil Engineering Works may be carried out as advance enabling works in the months from September to February. Table 5-1 below details the works in a number of key phases, some of these phases will run in parallel. Table 5-1 – Proposed Development Construction Stage Duration and Phasing Phase Activity Estimated Duration 1 Detailed Design Stage – For Construction - Detailed Civil, Structural and Electrical Design Works - Planning Compliance Works - Environmental Compliance Works - Pre-Construction Surveys 3 months 2 Civil Engineering Enabling Works - Setting out site boundaries - Tree and hedge cutting - Site entrance works to create access - Temporary Construction Compound - Advance drainage works and silt control measures 2 months 3 Civil Engineering Main Site Works - Upgrade and Widening of Public Road in Vicinity of Site - Access Track Construction - Crane Hardstand Construction - Drainage Works - Initial Reinstatement Works (Pre-Turbine Delivery) - Final Reinstatement Works (Post-Turbine Delivery) 8 months (Pre-Turbine Delivery) 2 months (Post-Turbine Delivery) 4 Structural Engineering Works - Wind Turbine Foundation Construction - Substation Construction 5 months 5 Turbine Circuit Connector Ducting and Cabling 2 months 6 Turbine Delivery Route Works 2 months 7 Turbine Delivery, Erection and Commissioning 6 months 8 Site Electrical Works - Developer (IPP) Electrical Installations & Commissioning - ESB Networks Electrical Installations & Commissioning 2 months 9 Grid Connection Works - Ducting Works - Cable Installation Works - Final Connection Works in ESB Substation 3 months 10 Final Commissioning of the Development 1 month Total Duration on Site (Some Phases will be carried out in parallel) 12 months RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 12 5.2 Construction Hours The hours of construction activity will be limited to avoid unsociable hours, where possible. Construction operations shall generally be restricted to between 07:00hrs and 19:00hrs on weekdays and between 07:00hrs and 14:00hrs on Saturdays. However, to ensure that optimal use is made of good weather periods or at critical periods within the programme (i.e., concrete pours or to accommodate delivery of large turbine components along public routes), it may be necessary on occasion to work outside of these hours. Any such out of hours working will be agreed in advance with Monaghan County Council. 5.3 Employment For the wind farm construction, a peak workforce of approximately 10 persons is anticipated on the wind farm Site and approximately 5 persons on the GCR. There will be peaks and troughs in the numbers, with a larger workforce during the general site works. 5.4 Roles and Responsibilities The Organisational Structure for the construction stage of the Development is set out below. This structure will be developed further at pre-construction stage and agreed with Monaghan County Council and other stakeholders prior to construction commencement. Figure 5-1 – Development Organisational Structure The roles and responsibilities of each of the key members of the Organisational Structure is set out below. 5.4.1 Developer The Developer (or client) is the developer of the proposed Development. The Developer is responsible for ensuring that competent parties are appointed to undertake the design and construction of the Development and to ensure Developer External Stakeholders Such as: Statutory Agencies Public Bodies General Public Landowners Construction Manager Designers PSDP PSCS Civil Engineering Works Contractor Project Archaeologist Ecologist Hydrologist Geologist Turbine Supply Contractor Grid Works Contractor Sub-Contractors Ecological Clerk of Works (ECOW) RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 13 sufficient resources are made available to facilitate the appropriate management of risks to the environment, safety and health and compliance with the Planning Permission, Building Regulations and other legislative requirements. 5.4.2 Construction Manager A suitability qualified Construction Manager (CM) will be appointed by the Developer and will have overall responsibility for overseeing the construction of the Development in accordance with regulatory and Development environmental requirements. The duties and responsibilities of the Construction Manager will include:-  Assist the Developer with the appointment of suitably qualified Ecological Clerk of Works (ECoW), PSDP, PSCS, Designers, Project Archaeologist, Ecologist, Geotechnical Engineer, Turbine Supply Contractor, Civil Engineering Contractors and other contractors.  Hold design team meetings, site meetings and other stakeholder meetings as required;  Coordinate with the above roles and liaise with other Development stakeholders;  Ensure that all works are designed, planned and constructed safely and with minimal environmental risk;  Update this CEMP to create a “Construction Stage” CEMP for agreement with Stakeholders;  Implement the CEMP on site, monitor the compliance through audits and site visits and take corrective action where necessary;  Take advice from the ECoW on legislation, codes of practice, guidance notes and good environmental practice;  Ensure timely notification of environmental incidents;  Put communication protocols in place to ensure that all personnel on site are made aware that they are responsible for ensuring good construction and environmental practice and that they are encouraged to provide feedback and suggestions for improvements. 5.4.3 Ecological Clerk of Works A suitably qualified Ecological Clerk of Works (ECoW) will be appointed by the Developer and will have overall responsibility for overseeing Environmental compliance on the Development and will report to Construction Manager. The ECoW will monitor the site works and ensure that methodologies and mitigation are followed throughout construction to avoid negatively impacting on the receiving environment. The duties and responsibilities of the ECoW will include:-  Preparation of the CEMP and supporting environmental documentation.  Review and approval of contractor method statements and risk assessments;  Monitor the implementation of the CEMP, carry out site inspections and audits to ensure the works are carried out in compliance with the CEMP;  Keep site records to demonstrate compliance with the CEMP, the Planning Permission and other statutory requirements;  Hold design team meetings, site meetings and other stakeholder meetings as required;  Advise site management and contractors on items such as:- o Prevention of environmental pollution; o Planning conditions and other statutory requirements; o Suitability and use of plant, equipment and materials to prevent pollution; o Environmentally sound methods of working and systems to identify environmental hazards.  Ensure agreed mitigation measures are initiated and adhered to during the construction phase;  Liaise with Project Archaeologist, Ecologist, Hydrologist and Geotechnical Engineer and ensure their regular site visits and audits / inspections are completed;  Ensure adequate emergency response procedures are put in place; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 14  Ensure that details of environmental incidents are communicated in a timely manner to the relevant regulatory authorities;  Investigate incidents of significance and ensure corrective actions are carried out;  Identify environmental training requirements and arrange relevant training for all levels of site-based personnel.  Put communication protocols in place to ensure that all personnel on site are made aware that they are responsible for ensuring good construction and environmental practice and that they are encouraged to provide feedback and suggestions for improvements. 5.4.4 Project Supervisor Design Process (PSDP) The design and construction of wind energy Developments is governed by the Safety, Health and Welfare at Work Act 2005 and also by S.I. No. 291 of 2013 the Safety, Health and Welfare at Work (Construction) Regulations 2013 (H&S Construction Regulations). The scale and scope of this Development requires that a Project Supervisor Design Process (PSDP) and Project Supervisor Construction Stage (PSCS) are appointed by the Developer (referred to as the client in the Construction Regulations). The role of the PSDP is to ensure co-ordination of the work of designers throughout the Development. This role has been performed by Mable Consulting Engineers up to the end of the planning stage of the Development. The Developer will appoint a PSDP for the construction stage of the Development, the PSDP will report directly to the Developer. The duties of the PSDP will include:-  Identify hazards arising from the design or from the technical, organisational, planning or time related aspects of the Development;  Work with and coordinate designers to design out safety, health and environmental risks at source where possible so as to eliminate / reduce these risks during the construction stage and during the operation, maintenance and decommissioning;  Prepare a written Safety and Health Plan for the Development taking into account any particular risks;  Communicate necessary control measures, design assumptions and residual risks to the PSCS so they can be dealt with in the Construction Stage Safety and Health Plan;  Ensure that the work of designers is coordinated in terms of Health, Safety and the Environment; o Coordinate the designers involved in the Development, including any temporary works designs during the construction stage;  Organise co-operation between designers;  Prepare a safety file for the completed Development and give it to the client; o The safety file is to include relevant detail on the Development’s design, operation, maintenance and decommissioning;  Notify the HSA and the client of non-compliance with any written directions issued. 5.4.5 Project Supervisor Construction Stage (PSCS) The role of the PSCS is to manage and co-ordinate health and safety matters during the construction stage. The Developer will appoint a PSCS for the construction stage of the Development, the PSCS will report directly to the Developer. The duties of the PSCS will include:-  Development of the Safety and Health Plan for the construction stage and update as required as work progresses;  Notify the Health and Safety Authority (HSA) before work commences;  Provide required safety file information to the PSDP;  Report accidents / incidents to the HSA and the client; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 15  Coordinate the implementation of the H&S Construction Regulations, monitor compliance and take corrective action where necessary;  Organise cooperation between contractors;  Coordinate the checking of safe work procedures and monitor compliance with the H&S Construction Regulations;  Review and approval of contractor method statements and risk assessments;  Coordinate arrangements to ensure workers have Safe Pass and relevant Construction Skills Certification Scheme (CSCS) cards;  Coordinate measures to restrict entry to site;  Provide a site induction to all site personnel and carry out Toolbox Talks as necessary;  Maintenance of the site Safety Files which are to include detail on personnel on site, their training details and induction date;  Coordinate the appointment of a Safety Representative (when there are 20+ people on site);  Notify the HSA and the client of non-compliance with any written directions issued. 5.4.6 Designers Designers will be appointed to carry out the construction stage detailed design of the Development and to monitor the on-site construction works. They will be appointed either directly by the Developer or by the contractors. The duties and responsibilities of Designers will include:-  Carry out designs that allows the Development to be constructed, operated, maintained and decommissioned safely and in compliance with the Planning Permission, and relevant legislation;  Carry out Design Risk assessments. o Identify possible hazards that may present during construction and subsequent operation, maintenance and decommissioning. Where possible, eliminate the hazards or reduce the risk;  Communicate necessary control measures, design assumptions and residual risks to the Construction Manager, Environmental Manager, PSDP and PSCS;  Co-operate and coordinate designs with other designers, the PSDP and the PSCS;  Carry out periodic site inspections during construction. Key designers will be required to hold appropriated professional indemnity insurance and, upon successful completion of their design, will issue opinions on compliance with Planning Permissions and Building Regulations. 5.4.7 Project Archaeologist The Project Archaeologist will report to the Construction Manager and the National Monuments Service and will be responsible for archaeological monitoring of the site during the construction phase. This will include monitoring of site investigations, excavation works, metal detection of excavated spoil and other tasks which may be required for compliance with the planning conditions. 5.4.8 Project Ecologist The Project Ecologist will report to the Construction Manager and is responsible for the protection of sensitive habitats and species encountered during the construction phase of the Development. The Project Ecologist will carry out periodic site inspections during construction. The responsibilities and duties of the Project Ecologist will include the following:-  Review and input into the preparation of the Construction Stage CEMP in respect of ecological matters;  Carry out site visits to carry out environmental audits and reviews and report any issues noted;  In liaison with ECoW, oversee and provide advice on all relevant ecology mitigation measures set out in the planning application reports and as may be required for compliance with the planning conditions;  Carry out ecological monitoring and survey work as may be required by Monaghan County Council and for compliance with the planning conditions. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 16 5.4.9 Project Hydrologist The Project Hydrologist will report to the Construction Manager and is responsible for inspection and review of drainage and water quality aspects associated with construction of the Development. The Project Hydrologist will carry out periodic site inspections during construction. The responsibilities and duties of the Project Hydrologist will include the following:-  Review and input into the preparation of the Construction Stage CEMP in respect of hydrological matters;  Assist in compiling a detailed drainage design before construction commences and attend the site to set out and assist with micro siting of proposed drainage controls;  Review and input to the preparation of the Construction Stage CEMP in respect of drainage and water quality management;  Carry out site visits and hydrological and water quality audits and report any issues noted. 5.4.10 Project Geotechnical Engineer The Geotechnical Engineer or Project Geologist will report to the Construction Manager and is responsible for inspection and review of geotechnical aspects associated with construction of the Development. The Geotechnical Engineer will carry out periodic site inspections during construction. The responsibilities and duties of the Geotechnical Engineer or Geologist will include the following:-  Review and input into the preparation of the Construction Stage CEMP in respect of geotechnical matters;  Liaise with designers and specify any construction stage site geotechnical investigation works;  Inspect turbine foundation formation and confirm formation make-up;  Carry out site visits to carry out geotechnical assessment work and monitoring;  Ensuring that identified hazards are listed in the Geotechnical Risk Register and that these are subject to ongoing monitoring. 5.4.11 Community Liaison Manager The Community Liaison Manager will report to the Construction Manager and the Environmental Manager. The responsibilities and duties of the Community Liaison Manager will include:-  Establish communication channels between Developer, Contractor, Monaghan County Council, local residents / neighbours;  Briefing residents/ neighbours on progress and issues as necessary;  Liaison with Monaghan County Council, emergency services and other stakeholders;  Liaison with local Gardaí, particularly in relation to traffic movements and permits where necessary. Contact details for the Community Liaison Manager will be posted on all construction site notice boards and on any other information or correspondence, which may be distributed from time to time. 5.4.12 Contractor Suitably qualified and experienced contractors will be appointed to carry out the Development construction works in accordance with the Planning Permission, Environmental and other regulatory requirements. The construction contractors appointed will be responsible for the organisation, direction, and execution of construction related activities during the detailed design and construction of the Development. Contractors will report to the Construction Manager and the ECoW. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 17 5.4.13 Site Manager A Site Manager will be appointed by the contractor to oversee the day-to-day management of working areas within the site and ensure that effective, safe, planned construction activities are delivered on an ongoing basis to the highest standards. The Site Manager will be a suitably qualified, competent, and experienced professional that will oversee site logistics, communicate regularly with construction staff, accommodate Development-specific inductions for staff on site and ensure that all work is compliant with the relevant design standards and health and safety legislation. The Site Manager will report to the Construction Manager and the ECoW. The Site Manager will be responsible for:-  Implementing the CEMP on the site;  Establishing, implementing, and maintaining the environmental management systems in line with ISO 14001;  Conducting regular on-site inspections and audits and ensure that adequate site records on compliance are documented;  Monitor the works to ensure they are carried out in accordance with the CEMP and relevant H&S and environmental requirements and when necessary, recommend corrective action;  Hold site meetings and other stakeholder meetings as required;  Ensuring appropriate Method Statements and Risk Assessments have been prepared for the works;  Ensuring all personnel have undertaken adequate inductions, awareness briefings and training;  Liaise with Stakeholders and dealing with enquires and complaints;  Managing and responding to environmental incidents and ensuring that all incidents are recorded and reported in an appropriate manner.  Put communication protocols in place to ensure that all personnel on site are made aware that they are responsible for ensuring good construction and environmental practice and that they are encouraged to provide feedback and suggestions for improvements. 5.4.14 Health, Safety, Environmental and Quality (HSEQ) Officer A HSEQ Officer will be appointed by the contractor to ensure that the CEMP is effectively implemented, developed and managed. The HSEQ Officer will be a suitably qualified, competent and experienced professional that will review health, safety, environmental and quality on a day-to-day basis and consult with the members of the construction team and stakeholders as requited. The HSEQ Officer will work closely with, and report to, the Site Manager. The HSEQ will assist the Site manager in meeting the above responsibilities and will also be required to keep up to date with relevant environmental best practice and legislative changes. 5.4.15 Traffic Management Coordinator A competent Traffic Management Co-ordinator (TMC) will be appointed for the duration of the Development and this person will be the main point of contact for all matters relating to traffic management. The TMC will monitor works which have an impact on the public road and ensure that methodologies and mitigation are followed throughout construction to avoid negatively impacting road use and safety. The TMC will report to Construction Manager. 5.5 Vehicles, Plant and Equipment Vehicles, Plant and Equipment will be required to meet the following:-  Only mechanically sound vehicles, plant and equipment will be permitted on site; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 18  To minimise emissions, noise and the risks of oil or fuel leaks; vehicles, plant and equipment use on site are to be properly serviced and maintained;  Noise emitting vehicles, plant and equipment are to be fitted with effective exhaust silencers;  Vehicles, plant and equipment are to travel to work areas using the access tracks, the is to be no tracking of vehicle through watercourses and open land not part of the works;  Refuelling of plant and vehicles will be carried out only in designated areas using the prescribed procedure.  Refuelling and maintenance is not to be carried out within watercourse or drain buffer zones;  Maintenance; in the event of a vehicle, plant or equipment requiring repairs, maintenance will be promptly carried out to minimise emissions arising from inefficient operation. This work will be carried out in the refuelling area or off site; and  Engine Idling; stationary onsite vehicles, plant and equipment will have engines turned off to reduce unnecessary idling emissions and noise. 5.6 Pre-Construction Surveys & Detailed Design 5.6.1 Pre-Construction Surveys Prior to commencement of the construction works pre-construction surveys will be carried out to be used as part of the construction stage design and to meet the requirements of the design and if required, planning conditions. These surveys will typically include: -  Detailed Geotechnical Site Investigations;  Road Condition Surveys;  Environmental Surveys;  Archaeological Surveys;  Ecological Surveys. 5.6.2 Construction Stage Detailed Design Prior to the commencement of construction works, construction stage detailed design will be carried out for agreement with relevant stakeholders. At construction stage these designers will be appointed to monitor the on- site construction works and to issue certificates of compliance with relevant codes on completion. Key designers will be required to hold appropriated professional indemnity insurance and upon successful construction of their design will issue opinions on compliance with Planning Permissions and Building Regulations. Key designers will include:-  Civil Engineering Design Engineer;  Structural Design Engineer;  Electrical Design Engineer;  Geotechnical Engineer;  Hydrology Engineer;  Turbine Designer;  ESB Networks (ESBN) Grid Connection Design Engineer. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 19 5.7 Development Construction Works 5.7.1 Enabling Works Prior to the main construction works commencing, advanced site enabling works may be carried out outside the bird breeding season, which runs from the 1st of March to the 31st of August. These works will include topographical setting out to demarcate the site boundaries, tree and hedge cutting, site entrance works, Construction Compound and advance drainage works and silt control measures. Figure 5-2 below shows a typical advance settlement pond under construction and later this pond in operation during the main construction works. Figure 5-2 - Settlement Pond Construction in advance of the Works, and later its operation 5.7.2 Site Drainage Site drainage is to be designed and constructed in accordance with the requirements of the following documents:-  Monaghan County Development Plan 2019-2025  Fisheries considerations shall incorporate guidance stated in ‘Guidelines on Protection of Fisheries During Construction Works in and Adjacent to Waters’ as published by Inland Fisheries Ireland (2016);  Protection and Conservation of Fishery Habitat with particular reference to Road Construction (2009);  The Greater Dublin Regional Code of Practice for Drainage Works (Version Draft 6.0);  The SuDS Manual (C753) 2015, CIRIA;  CIRIA Culvert design and operation guide (C689);  TII Publications - Vegetated Drainage System for Road Runoff (DN-DNG03063)  Part H, Building Drainage of The Building Regulation;  BS EN-725:2008, Drains & Sewer Systems Outside Buildings; 5.7.3 Topsoil Stripping To avoid exposing subsoils to poor weather conditions, topsoil stripping is to be carried out “just in time” prior to commencement of main excavation works and only after the installation of the proposed surface water drainage control measures for the area being stripped. Topsoil reinstatement and re-seeding is to be carried out as soon as practical after completion of the main earthworks in a work area. 5.7.4 Site Entrances Primary access to the proposed Development site will be provided via a new entrance off the regional road, R183 on the south boundary of the proposed Development site. This entrance will accommodate the Development during both the construction and operational phases of the wind farm Development site RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 20 Site Entrance Design The proposed site entrances have been designed in accordance with TII Publication ‘Rural Road Link Design 2017’ (DN-GEO-03031), ‘Geometric Design of Junctions (Priority Junctions, Direct Accesses, Roundabouts, Grade Separated and Compact Grade Separated Junctions)’ (DN-GEO-03060) & The Monaghan County Development Plan 2019-2025. Prior to construction detailed site entrance layouts will be prepared and agreed with Monaghan County Council These will be designed to ensure surface water from the Development does not flow onto the public road. This will be achieved by creating a localised ramp at the entrance directing surface water flow into the site. 5.7.5 Internal Access Track It is proposed to construct a new Access Track off the R183 local road for a distance of 1.1km as far as the Wind Turbine. This track in the main will take the form of an “Excavated Track” made up of stone fill track with a clause 804 crushed aggregate capping. Typical access track cross sections are detailed on Planning Drawing 22790-210 and 22790-211. 5.7.6 Excavated Track Figure 5-3 shows typical excavated track construction at formation level with geotextile, geogrid and an edge drain. Figure 5-3 - Excavated Track Formation, Geotextile, Geogrid and Edge Drain The Access Track will be constructed as follows:- 1. The appointed contractor(s) will liaise with the Wind Turbine supplier prior to the commencement of the works to ensure that the design of the new excavated Access Track conforms with the Wind Turbine supplier's specifications. 2. The proposed Access Track will have an overall width of 4.5m. 3. The alignment of the new site Access Track will be set out based on the construction drawings and the centreline marked out using ranging rods or timber posts. 4. Topsoil will be excavated in the presence of the Archaeologist and removed to the temporary topsoil repository area for use in the permanent reinstatement works. 5. The subsoil will be excavated to appropriate bearing strata in accordance with the requirements of the Design Engineer. 6. Well graded granular fill will be spread and compacted in layers and capped with blinding aggregate in accordance with the requirements of the Design Engineer. 7. All new Access Tracks will be constructed with a fall to aid drainage of surface water. Access Tracks will be graded to ensure that all runoff is channelled towards the dirty water drains. A small embankment will RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 21 be built between the road and clean water drains to prevent runoff from the road from entering the clean water system. Figure 5-4 below shows a competed and landscaped site Access Track. Figure 5-4 - Completed Access Track 5.7.7 Stone Aggregate and Fill Requirements As part of construction of the proposed Development, a significant amount of stone aggregate fill material will be required. This will be used to construct Wind Turbine Foundation Formation, Substation Compound, Access Track, Hardstands and Construction Compounds. Stone and aggregate fill will be delivered to site via ridged and articulated tipper lorries. The peak period for stone and aggregate fill deliveries will be during internal Access Track Construction. During this period there will be up to 5 deliveries to site per hour for a period of approximately 1 week. Outside this period there will be up to 10 deliveries of stone and aggregates to site per day. 5.7.8 Stone Aggregate Specification To mitigate against siltation of surface water runoff, access track construction will consist of crushed aggregates in accordance with the requirements of I.S. EN 13242:2002 +A1:2007 Aggregates For Unbound And Hydraulically Bound Materials For Use In Civil Engineering Work And Road Construction. The use of quarry dust will not be permitted. Also, the use of sedimentary rocks, such as shale will not be permitted. The site track as well as the works to the public road will utilise the following types of crushed stone aggregate:-  Clause 804  Class 6F2  Class 6C The above materials will be sourced from CE and NSAI certified local quarries. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 22 5.7.9 Spoil Management Plan All excavated material generated during construction as far as is practicable will be retained on site and, where appropriate, incorporated into the works and final landscaping to blending seamlessly with the existing terrain. All temporary spoil storage areas and areas subjected to reinstatement will be fenced with stock-proof fencing to prevent livestock disturbance until vegetation has become established. 5.7.10 Excavated Material Use It is proposed to incorporate the excavated material into the works. Stockpiling of excavated material will be kept to a minimum as far as is practicable by incorporating this material into the works as they are carried out. Excavated material will be used as follows:-  Excavated rock will be used a fill under access tracks, subject to confirmation of suitability by the design Engineer.  Excavated sub-soil material will be used as fill turbine foundations, access track edges, edge protection berms and other landscaping.  Surplus excavated material will be integrated into the final landscaping.  Excavated topsoil will be used landscape the Development area. 5.7.11 Management of Excavated Material Excavated Material will be managed as follows:  Excavated material, where possible, will be incorporated into the works as the works progress.  Excavated material not be immediately incorporated into the works and will instead be temporarily stored on-site. This material will be formed into temporary spoil berms and allowed to vegetate.  In general, temporary spoil berms will not remain on site for extended periods, however, if a berm is to be retained through the winter, vegetation will be encouraged during late summer and early autumn to ensure coverage during the winter months.  All excavated spoil will be stored in an environmentally safe manner to eliminate the risk of water pollution until it is required for reuse.  Buffer zones will be established as follows: a 50-metre buffer for registered streams and a 20-metre buffer for all other watercourses, where possible. Excavated material will be stored outside these buffer zones. The designated storage areas are detailed in the updated planning drawings.  Excavated material will be stored outside the 0.01% AEP (Annual Exceedance Probability) Year Storm Flood Zone. The boundaries of this flood zone, along with the storage locations, are outlined in the planning documentation.  The Contractor is responsible for ensuring that the removal and storage of excavated material complies with the requirements of this management plan. Both the temporary storage areas and vegetated berms will be subject to regular ecological inspections. To control surface water runoff, silt fencing will be installed around temporary spoil berms. Additionally, cut-off drains will be constructed to divert runoff into a treatment settlement pond. These combined measures will minimise sediment run-off and protect downstream water quality. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 23 5.7.12 Substation It is proposed to construct a 20kV electricity Substation within the site boundary as shown on Drawing No. 22790- 102. This Substation will provide a connection to the national grid via an underground 20kV transmission cable connection. The construction and electrical components of the on-site Substation will be to ESB, Electrical Designer and Wind Turbine Supplier specifications. The Substation compound will have an area of approximately 256m2 and will include one Substation building and electrical components. The Substation and compound will be surrounded by stockproof fencing. Prior to construction beginning, interception drains will be placed uphill from the planned Substation area to catch any current overland water flows and direct them downhill to minimise water contact with the construction site. The clean water will be released through a level spreader downhill from the construction site, flowing over the current vegetation. The construction will include the following:- 1. The Substation compound's area will be outlined using ranging rods or wooden posts. 2. Perimeter drains will be installed or upgraded to collect surface water run-off from the Substation compound. This will involve the installation of check dams, silt traps and level spreaders to manage surface run-off effectively. 3. Topsoil will be stripped and carefully stockpiled for future landscaping use. 4. Subsoil will be excavated and retained on site by incorporated it into the perimeter of the compound area. 5. The Substation compound will be formed by constructing compacted layers of suitable hardcore; 6. The foundations for both Substation buildings will be excavated down to the level indicated by the designer and appropriately shuttered; 7. Steel reinforcement will be laid in place and concrete foundations will be poured; 8. The Substation building will be constructed on top of the concrete foundations. 9. Construction of underground cable ducts and trenches within the Substation compound will be carried out; 10. On completion of the ground works the area will be re-topsoiled and landscaped; 11. Stockproof fencing and gates will be installed around the compound perimeter on completion of the landscaping works. 5.7.13 Internal Underground Cabling The Wind Turbine will be connected to the proposed on-site Substation via underground MV cables. Fibre-optic cables will also connect the Wind Turbine to a control system located within the Control Building in the Substation Compound. The electrical and fibre-optic cables will be run in cable ducts 0.95m below the ground surface located off the site Access Track. The cabling construction work will include the following:- 1. A trench approximately 0.95m deep and 0.325m wide will be dug to accommodate the cable ducts. 2. The trench base will be graded, smoothened and trimmed when the required depth and width have been obtained. 3. Cable ducts will be installed within the trench, a typical cross section through the cable ducting and cable is contained in drawing 22729-212. 4. The typical fill over the cable ducting and bedding surround will consist of selected excavated backfill material. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 24 5. Surplus spoil for the excavation and refilling works will be deposited in spoil repository areas. 6. Where cable ducting crosses the Access Track; the cable trench will be backfilled with lean-mix concrete in order to protect the ducting from heavy axle loads passing over. 7. Where cable ducting crosses an open drain or watercourse; the ducting will be installed at a lower level to allow it pass under the drain or watercourse. 8. Marker tape will be placed within the trench after part backfilling for identification and safety purposes in accordance with the electrical designer’s requirements. 9. Cable marker posts will be installed at regular intervals and at change of directions along the line of the cable route. Cable marker posts will either be made of concrete, recycled plastic or timber material. Each marker post will contain appropriately worded warning signage highlighting to persons the presence of high voltage electricity cables underneath. 5.7.14 Wind Turbine The proposed Wind Turbines will be a Nordex N133 on a 71.5m tower and will have a maximum tip height of 143.8m. A drawing of the proposed Wind Turbine is shown on Drawing No. 22790-200 & 201. The turbine installed on the site will be the conventional three-bladed, tubular tower model with horizontal axis. The rotor blades are bolted to the central rotor hub, which is connected to the nacelle. The nacelle contains the following turbine components:-  Generator  Electrical components  Aviation lighting to Irish Aviation Authority (IAA) specifications. The entire nacelle and rotor are designed to rotate, or ‘yaw’, in order to face the prevailing wind. A wind vane located on the nacelle of the turbine controls the yaw mechanism. A control unit is typically located at the base of the turbine and an internal lift or ladder leads up to the nacelle where the shaft, generator and gearbox are located. The turbine tower is a conical steel tube with multiple layer paint finish. Towers comprise a steel ring at the base of the tower which is assembled on top of the concrete foundations. The tower will be delivered to site in three sections. The base of the tower is approximately 4.3m in diameter, tapering to approximately 3.2m where it is attached to the nacelle. The tower is accessed by a galvanised steel hatch door, which will be kept locked except during maintenance. The blades of the turbines are typically made of fibreglass or carbon fibre reinforced polyester and are aerodynamically shaped to improve efficiency and lower noise production. The turbines are multi-ply coated to protect against corrosion. It is proposed that the turbines will be of an off-white or light grey colour to blend into the sky background. 5.7.15 Wind Turbine Hardstands The crane hardstand will be constructed to accommodate and support the Wind Turbine components, cranes and other plant during delivery and Turbine erection. The Hardstand will also be used for maintenance activities while the Wind Turbine is in operation. The dimension of a single Hardstand is circa 91 metres in length and 35 metres in width. There will also be smaller temporary stoned areas constructed to store the Wind Turbine parts and components prior to erection, these will be removed, and the areas reinstated on completion of the Wind Turbine erection. See Planning Drawing 22790- 202 for details on the Hardstand. The crane Hardstands will be constructed to support the significant loads imposed by the outriggers of the main lifting crane during the Wind Turbine installation process on site. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 25 Hardstand construction will include the following:- 1. The excavation process will involve hydraulic excavators moving excavated material to on-site repository areas using articulated dumper trucks or tractor and trailers. 2. Topsoil will be excavated in the presence of the Archaeologist and removed to the temporary topsoil repository area for use in the permanent reinstatement works. 3. The Hardstand formation will be formed by excavating subsoil to a suitable bearing stratum in accordance with the requirements of the Design Engineer. 4. The Hardstand will be constructed using imported stone aggregate rolled in layers and tested in accordance with the requirements of the Design Engineer. 5. Temporary set down areas will be created at each crane Hardstand to store Wind Turbine components such as the rotor hub assembly, turbine blades, turbine towers, and nacelle. These areas will be made of compacted stone aggregate, these will be removed, and the areas reinstated on completion of the Wind Turbine deliveries. 6. Plate bearing tests will be conducted on the completed Hardstand surface to verify if the Hardstand bearing strengths meet the crane outrigger load requirements. 7. The main crane outrigger areas are subjected to the highest levels of stress and as such strict minimum requirements are put in place to ensure safety during the works. This includes but is not limited to: a. Surface Evenness of equal or less than 0.25% slope. b. Minimum Bearing Capacity of 220kN/m2. 5.7.16 Turbine Foundation The proposed Wind Turbine foundation type is a Ground Bearing Foundation, see Planning Drawing 2290-203 for foundation details. Construction of the Wind Turbine foundation bases will require excavation of the surrounding soil from the foundation and crane Hardstanding area to suitable bearing strata. The Ground Bearing Foundation Base will require a reinforced concrete foundation comprising a base slab bearing onto rock or other competent substrata with a central upstand to support the tower. The design of the foundation will be provided by the Wind Turbine supplier; Nordex. The appointed Civil Engineering Works Design Engineer, in conjunction with the Geotechnical Engineer will confirm the foundation formation make-up and bearing capacity. The Ground Bearing Foundation Base will be of circular shape on plan with an anticipated diameter of approximately 23m. Figure 5-5 below shows typical Wind Turbine foundation formation works, steel fixing and concrete pouring works. Figure 5-5 - Wind Turbine Foundation Formation, Steel Reinforcement and Concrete Pour The construction of the Ground Bearing Foundation Base will include the following: - The excavation area will be clearly marked and will be adjusted to ensure a safe working environment with sloped sides. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 26 1. The excavation process will involve hydraulic excavators moving excavated material to on-site repository areas using articulated dumper trucks or tractor and trailers. 2. Topsoil will be excavated in the presence of the Archaeologist and removed to the temporary topsoil repository area for use in the permanent reinstatement works. 3. The foundation formation will be formed by excavating subsoil to a suitable bearing stratum. Stone fill will be installed on the excavated subsoil and rolled in layers and tested in accordance with the requirements of the Design Engineer. 4. A concrete blinding layer will be installed on the stone fill. This concrete blinding will be laid approximately 75mm thick directly on top of the stone fill, tamped and finished with a screed board to leave a flat level surface. 5. Temporary drainage measures will be installed to de-water the excavation. Water entering the excavation may have a relatively high concentration of suspended solids, the settlement ponds receiving this water will be designed to accommodate this flow. 6. Pumping water from Wind Turbine base excavations can lead to substantial flow rates into settlement ponds. Where possible drainage channels will be installed to de-water excavations via gravity flow. Where pumping is required to de-water deeper excavations, temporary storage will be provided within the excavations and dewatering will be carried out at a flow rate that matches the capacity of the settlement ponds. 7. Shutters and steel reinforcement will be installed on the concrete blinding, and the foundation of the Wind Turbine will be prepared for pouring of concrete. 8. Steel reinforcement will be installed as per the Wind Turbine foundation designers’ drawings and schedules. The foundation anchorage system will be set up, adjusted, and fastened to the blinding using steel box section stools. 9. Ductwork will be installed as needed, and formwork will be erected around the steel cage and propped from the backside as necessary. 10. The foundation anchorage system will be inspected for level and alignment before pouring the concrete into the base. These checks will be submitted to the Wind Turbine supplier for their approval. 11. Ready-mix concrete will be delivered to the foundation by ready-mix concrete trucks via the site Access Track. 12. Concrete will be poured into each base using a concrete pump, and vibrating pokers will be utilised to ensure proper compaction around the reinforcement. 13. When concrete installation and finishing is complete, the foundation base will be covered and left to cure. 14. After the curing process, the formwork around the Wind Turbine base will be dismantled and taken away. 15. Earth wires will be installed around the base prior to backfilling around. 16. The base area will be backfilled and filled over to make up the final levels using selected excavated material and crushed stone fill. As part of this, the crane Hardstand will be completed in the vicinity of the base. 17. To complete the area a stone Access Track will be created to the Wind Turbine door and around the Wind Turbine for maintenance purposes. The remaining area will be topsoiled and landscaped. Figure 5-6 & Figure 5-7 below shows typical Wind Turbine foundation finishing and backfilling works. Figure 5-6 - Wind Turbine Shuttering, Finishing and Curing RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 27 Figure 5-7 - Wind Turbine Foundation Backfilling 5.7.16.1 Wind Turbine Erection The erection of the Wind Turbine will occur in the last month of the construction phase. The erection process generally takes one week. The erection of Wind Turbines is a specialist process with specially designed large- scale cranes required to erect the turbine components. The cranes themselves will be constructed on site at the Wind Turbine Hardstand location and will have to be dismantled before progressing to the next Wind Turbine base location. The construction will include the following: 1. Components are delivered and stored on Hardstands prior to assembly; 2. The first section is bolted to the steel base, which is cast into the concrete foundation; 3. The tower sections of the Wind Turbine are erected; 4. The nacelle is then installed on top of the top tower section; 5. Once the nacelle is installed the rotor hub is then installed in place; 6. The blades are then lifted one by one and connected to the rotor hub; 7. Once the Wind Turbine is installed, electrical commissioning and final energisation follows. The Wind Turbine erection process is a carefully managed and precision operation and is heavily dependent on specialist plant and good weather windows. Figure 5-8 below shows typical set up arrangements during Wind Turbine erection. Figure 5-8 - Wind Turbine Erection RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 28 5.7.17 Reinstatement Reinstatement works will commence as soon as possible after completion of individual sections of work. Reinstatement will include grading of slopes left by the construction works, followed by the careful placement of topsoil previously excavated and stored on site. Topsoil reinstatement and re-seeding is to be carried out as soon as practical after completion of the main earthworks in a work area. Reinstated areas will be seeded out with native species or allowed to vegetate naturally. Upon completion of the construction works, all remaining excavated material will be integrated into the final landscaping, blending seamlessly with the existing terrain to avoid leaving any mounds of spoil around the site. Landscaping will allow for sympathetic restoration of the ground surface and ground profile to reduce the visual impact of new infrastructure, facilitate vegetation regrowth and reduce scour and erosion of bare surfaces prior to vegetation establishment. Reinstatement landscaping is to be carried out as soon as possible after completion of individual sections of work. All areas subjected to reinstatement will be fenced with stock-proof fencing to prevent livestock disturbance until vegetation has become established Figure 5-9 shows typical wind farm finishing works around a Wind Turbine base and hardstand. Figure 5-9 - Turbine Basse and Hardstand Finishing Works 5.7.18 Commissioning The final stage of the Development’s construction is the final commissioning of the Wind Turbines. This will involve testing of the Wind Turbines for compliance with standards and for compliance with the National Electricity Grid Code. Once the tests results are satisfactory, the wind farm will be authorised by ESB Networks / EirGrid to export electricity onto the national grid. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 29 5.7.19 Decommissioning The design life of the proposed Development is 35 years after which time decommissioning will occur, unless planning permission is granted to extend the duration of operation. At the end of the design life of the Development, the Wind Turbine, Substation, and all their associated above ground components will be dismantled and removed from site using appropriate decommissioning and reinstatement practices in place at that time. Prior to commencement a decommissioning plan will be prepared for agreement with Monaghan County Council The plan will include a material recycling / disposal plan and traffic management plan and other similar mitigation measures to those implemented during the construction phase. In terms of traffic effects, the decommissioning stage will generally mirror that of the constructions stage, although the effects will be significantly reduced as the volumes of materials removed from the site will be less than delivered. There will be no hazardous waste generated or the need for complex environmental remediation. During decommissioning structures will be dismantled in the opposite order of their construction. Wind Turbine and other components located above ground will be dismantled and taken off-site for recycling. The Wind Turbine foundations and Hardstanding portions will be left in place underneath and covered with soil to allow for natural revegetation or reseeding. Leaving the Wind Turbine foundations in place is seen as a more ecologically responsible choice since removing that amount of reinforced concrete might cause environmental disturbances including noise, dust, and vibration. The site Access Track will serve functions beyond operation of the proposed Development, such as forest/agricultural access. Therefore, subject to agreement with Monaghan County Council it is proposed to keep the site Access Track in place for future use. After completion of decommissioning works the affected areas will be reinstated to their former agricultural use. 5.8 Construction in a Flood Zone All infrastructure, where feasible has been sited more than 50m from EPA registered watercourses. A localised part of the proposed access track is located within a flood plain, see Planning Drawings 22790-102 and 103. The access track in this location has been designed to match the existing ground levels and so the flood plain water storage capacity and existing surface water and ground water flow paths are unaffected. There will be no storage of excavated material in the Flood Zone. 5.9 Turbine Delivery Route The components for the Wind Turbines will be delivered by cargo ships to the Port of Waterford, which is also known as Belview Port, located in County Kilkenny. The components for the Wind Turbine will be delivered in separate loads, some of which are abnormal in terms of their width and length. The components will be transported from Belview to the site along the motorway, national, regional and local road network. Several junction locations along the national road and both bends and junctions on the regional road network require temporary works to accommodate these deliveries of Wind Turbine components to the site, as well as construction works at the site access on the R183. These works will include the temporary alterations at locations on the N54 and the R183. This will include the temporary hardstanding’s, making signposts, lighting columns and kerbs demountable / hinged, utility diversions, minor drainage works (i.e. temporary relocated interceptor ditches) hedgerow / vegetation cutting for oversail. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 30 At construction stage a transportation plan will be prepared by the Wind Turbine component delivery company. Permits for moving the abnormal loads on the public roads to the Wind Farm site will be obtained from An Garda Síochána and the applicable local authorities on the selected haulage route. Further detail on the Turbine Delivery Route are contained in the TMP. 5.10 Grid Connection Works The proposed grid connection consists of connecting the Wind Farm to the national electricity grid via circa 1.9km of underground 20kV electrical cabling connecting to Clones 38kV Substation in the townland of Clones, County Monaghan. See drawing 22790-102 to 22790-105 for proposed grid route layout details. Figure 5-10 – Grid Route Layout 5.10.1 Cable Trenching Methodology Cable ducts will be placed within a trench approximately 0.95m deep and 0.325m wide. The following list is a non- exhaustive list of items that will be adhered to during the construction of the grid route:  All trenching works will be undertaken to ensure that only short sections of trench are open at any one time.  At watercourse crossings, the contractor will be required to adhere to the environmental control measures outlined within the planning application reports, the CEMP and best practice construction methodologies;  Where the cable route intersects with culverts, the culvert will remain in place (where possible) and the ducting will be installed either above or below the culvert to provide minimum separation distances in accordance with ESB and Irish Water specifications; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 31 Typical trench layouts for an UGC within a roadway and within grassed areas are shown in Figure 5-11. Figure 5-11 – Typical Cable Trench Layouts RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 32 The proposed sequence of works is as follows: 1. Prior to commencement, the proposed design for the grid connection works including proposed traffic management will be reviewed and agreed with Monaghan County Council’s Road Engineer. 2. The proposed works will also be reviewed and agreed with other stakeholders including; the OPW , Iarnród Éireann Irish Rail, ESB Networks. 3. The contractor will carry out an on-site assessment of the works area and prepare a proposed works methodology for review and agreement with Monaghan County Council 4. Road opening licence, road closure and partial lane closure permits will be obtained from Monaghan County Council 5. Existing underground services along the UGC route will be surveyed; 6. Traffic control measures will be implemented. 7. Pollution control measures will be implemented in advance of any excavation works being undertaken. 8. The trench will be excavated to the required dimensions, approximately 0.95m deep and 0.325m wide. 5.10.2 Managing Excess Material from Trench Excavated materials from grassed areas (topsoil, subsoil) will be stored separately for use during the reinstatement of the trench or in the reinstatement of areas as part of the Development. Stockpiles will be restricted to less than 0.75m in height. Excavated material from the public road network will be recycled as appropriate. Excavated bitumen macadam will be place in dumper trucks and transported to a temporary stockpile area for eventual recycling. Other excavated material will be transported off site by an appropriately authorised waste collector and disposed of at an appropriately licenced waste facility. 5.10.3 Cable Ducting Methodology The 20kV medium voltage underground cable duct construction is to be a 20kV XLPe cable duct in accordance with ESB Networks’ Specification for the Installation of Ducts & Structures for Underground 10-20kV Power Cables & Communication Cable’. The 20kV power cable will be laid in a single 125mm diameter uPVC duct in a cable trench. The proposed sequence of works is as follows: 1. Grade, smooth and trim trench base when the required depth and width have been obtained. 2. Lay the 125mm cable duct and surround with 275mm of lean mix concrete CBM4 3. Place red marker strip above. 4. Lay and compact min 375mm of CBM4 lean mix concrete (in Access Track) or selected excavated material (in fields) and place a yellow marker warning tape above. Yellow warning tape to be 300mm below the finished surface. 5. Place Clause 804 material (in Access Track) or selected excavated material (fields) to within 100mm of surface. 6. Reinstate existing surface; a. For road sections, carry out immediate permanent reinstatement in accordance with the specification of the local authority, TII and/or private landowners, which ever applies; b. For unsurfaced/grass sections, backfill with suitable excavated material to ground level leaving at least 100 mm topsoil or match existing level at the top to allow for seeding or replace turves as per the specification of the local authority or landowner; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 33 7. Clean and test the ducts in accordance with the specification by pulling through a brush and mandrel. Install 12 mm polypropylene draw rope in each duct and seal all ducts using robust duct end seals fitted with rope attachment eyes in preparation for cable installation at a later date. All the works should be witnessed by ESBN Clerk of Works (CoW) as required. 5.10.4 Joint Bays Joint bays will be provided to meet the requirements of standard cable drum lengths and/or as required to limit cable pulling forces. Joint bays will be no further than 500m centre to centre apart. Joint bays will be constructed as per ESBN requirements. Where possible, joint bays will be located in areas where there is a natural widening/wide grass margin on the road in order to accommodate easier construction, cable installation and create less traffic congestion. Where possible Joint Bays will be located in the non-wheel bearing strip of roadways, however given the narrow profile of local Access Track this may not always be possible. During construction the joint bay locations will be fenced off once they have been constructed, they will be backfilled until cables are being installed. On installation of the cable, the cable will be jointed, and the joint pit will then be permanently backfilled with thermally suitable material together with protective tiles and hazard marking tape. On completion of the backfill work, the existing surface will be reinstated. Typical details on the 20kV joint bay is outlined in Figure 5-12 Figure 5-12 - Typical 20Kv Joint Bay 5.10.5 Surface Cable Markers & Marker Posts Surface Marker posts will be used on non-roadway routes to delineate the cable route and joint bay positions. Marker posts will also be placed in the event that burial depth is not to standard. Marker posts will be in accordance with Figure 5-13. The design of the marker posts shall be agreed with EirGrid and ESBN as part of the detailed design process. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 34 Figure 5-13 below shows a Typical Cable Marker Post. Figure 5-13 Typical Cable Marker Post 5.10.6 Crossings 5.10.7 Existing Underground Services In order to facilitate the installation of the underground cable, it will be necessary to cross or relocated existing underground services such as drainage lines, water mains, telecom networks or existing cables. Crossing existing services will be carried out using open trenching with either an undercrossing or an overcrossing, depending on the depth of the service. Where this method is not suitable, the directional drilling method will be used. 5.10.8 Watercourses Where the cable route intersects with existing watercourses, a detailed construction method statement will be prepared by the Contractor prior to the commencement of construction and for agreement with the Local Authority, IFI and other relevant agencies. Where required, horizontal directional drilling (HDD) will be employed. Watercourse crossings will be designed and constructed in accordance with the requirements of the documents listed above in 5.7.2 Site Drainage. 5.10.9 Bridges For bridge crossings, the cable will be located within the bridge deck where there is sufficient depth and width available on the bridge, where there is insufficient depth and width available horizontal directional drilling (HDD) will be employed as an alternative. 5.10.10 Culverts Crossing existing culverts will be carried out using open trenching with either an undercrossing or an overcrossing, or by directional drilling depending on the depth of the culvert. Details on crossings are contained in Section 7.11; Surface Water Management Plan. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 35 5.10.11 Horizontal Directional Drilling Methodology Horizontal Direction Drilling (HDD) is a method of drilling under obstacles such as bridges, railways, water courses, etc. in order to install cable ducts under the obstacle. This method is employed where installing the ducts using standard installation methods is not possible. There are TWO crossings on this UGC route which will require HDD. The drilling methodology is as follows: 1. A works area of circa. 40m2 will be fenced on both sides of the crossing, 2. The drilling rig and fluid handling units will be located on one side of the bridge and will be stored on double bunded 0.5mm PVC bunds which will contain any fluid spills and storm water run-off. 3. Entry and exit pits (1m x 1m x 2m) will be excavated using an excavator, the excavated material will be temporarily stored within the works area and used for reinstatement or disposed of to a licensed facility. 4. A 1m x 1m x 2m steel box will be placed in each pit. This box will contain any drilling fluid returns from the borehole. 5. The drill bit will be set up by a surveyor, and the driller will push the drill string into the ground and will steer the bore path under the watercourse. 6. A surveyor will monitor drilling works to ensure that the modelled stresses and collapse pressures are not exceeded. 7. The drilled cuttings will be flushed back by drilling fluid to the steel box in the entry pit. 8. Once the first pilot hole has been completed a hole-opener or back reamer will be fitted in the exit pit and will pull a drill pipe back through the bore to the entry side. 9. Once all bore holes have been completed, a towing assembly will be set up on the drill and this will pull the ducting into the bore. 10. The steel boxes will be removed, with the drilling fluid disposed of to a licensed facility. 11. The ducts will be cleaned and proven, and their installed location surveyed. 12. The entry and exit pits will be reinstated to the specification of ESBN, EirGrid and Monaghan County Council. 13. A transition coupler will be installed at either side of the crossing following the horizontal directional drilling as per ESB and EirGrid requirements, this will join the HDD ducts to the standard ducts. 14. The directional drilling details have been submitted as part of this planning application. Figure 5-14 – Typical HDD Installation RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 36 5.11 Consents The key consents, licenses, notifications and permissions required for this Development include the following:-  Planning Permission and associated Planning Compliance;  Commission for Energy Regulation (CER) Authorisation and Licence to Generate;  ESBN Functional Specification;  Building Control Commencement Notice;  Building Control Fire Certificate;  Office of Public Works (OPW) Section 50 Consent for watercourse crossings;  Public Road Abnormal Load Permits;  Public Road Opening Licenses;  Public Road Closure and Partial Lane Closure Permits;  Irish Aviation Authority Consent;  Waste collection permits. The consents, licenses, notifications and permissions list above is a non-exhaustive list and will be reviewed prior to construction and regularly thereafter to ensure that the programme is achieved, and new consent requirements are identified as early as possible. To avoid delays to the Development programme, all required construction stage consents is to be sought by the appointed designers and contractors in a timely manner. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 37 6.0 Safety, Health and Welfare at Work As stated in section 3.3.4 Project Supervisor Design Process above, the design and construction of wind energy Developments is governed by the Safety, Health and Welfare at Work Act 2005 and also by S.I. No. 291 of 2013 the Safety, Health and Welfare at Work (Construction) Regulations 2013 (H&S Construction Regulations). Safety, Health and Welfare management for the Development will include the following:- 1. During the detailed design stage of the Development a Preliminary H&S Plan will be prepared by the PSDP and circulated to designers, potential contractors and other stakeholders. This plan will identify potential safety hazards associated with the site and the works and assess the associated risks. Mitigation and control measures will be recommended to minimise the identified risks. 2. The Preliminary H&S Plan will then be developed further by the PSCS to create the Construction Stage H&S Plan for the works. This plan will address all safety and health aspects of the construction process and provide relevant contact details and emergency response procedures for the Development. 3. The Construction Stage H&S Plan will detail the site induction and training requirements for site personnel. 4. Evidence of completion of construction safety training, typically in the form of a Safe pass Card, will be required from all construction personnel prior to commencing work on the site. 5. A record of safe pass Cards and personnel approved for entrance to site will be completed as part of a site induction process. 6. Where relevant, equipment operators or specialist works will require personnel to hold a valid Construction Skills Certification Scheme (CSCS) card. 7. All equipment and machinery used on site will be appropriately certified for its intended purposes. 8. The Developer via the Construction Manager will ensure that only competent contractors are appointed to carry out construction works on the site. 6.1 Construction Compound and Facilities A Temporary Construction Compound will be established initially during the Enabling Works and completed at commencement of the main construction works. The compound will measure circa 600m2 in total as shown on the Planning Drawings. The compound will be used as a secure storage area for construction materials and also contain temporary site units to provide welfare facilities for site personnel. Facilities will include office space, meeting rooms, canteen area, a drying room and sanitary provisions. The construction of the compound will be as follows:- 1. The temporary compound's area will be outlined using ranging rods or wooden posts. 2. Perimeter drains will be installed or upgraded to collect surface water run-off from the temporary compound. This will involve the installation of check dams, silt traps and level spreaders to manage surface run-off effectively. 3. Topsoil will be stripped in the presence of an Archaeologist and carefully stockpiled for future landscaping use. 4. Subsoil will be excavated and retained on site for refilling into the compound area at reinstatement stage. 5. The temporary compound will be formed by constructing compacted layers of suitable hardcore. 6. Site offices and storage containers will be installed, and electric power will be provided by means of a temporary generator. 7. Parking areas and material storage areas will be provided within the Temporary Construction Compound. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 38 8. For the storage of lubricants, oils, site generators, etc., a bunded refuelling area will be provided within the compound. 9. For sanitary provisions self-contained toilets and wash areas with integrated waste holding tanks will be provided. A temporary water storage tank will be used as the site's source of water. 10. The compound will be fenced and secured with locked gates. 11. On completion of the construction works the Temporary Construction Compound area will be dismantled and the hardcore will be grubbed up. This hardcore will be incorporated into the final finishing of the Development. The area will be backfilling with stockpiled subsoil and topsoil, landscaped and re-seeded. 6.2 Safety and Security Members of the public will be prevented from accessing the Development site through implementation of adequate security measures. A contact information board will be erected at the site entrances. All those entering the site during construction will be required to sign in at the Temporary Construction Compound on site. Security fences will be erected at the perimeter of active construction areas to prevent unauthorized entry. These fences will be regularly inspected and maintained. Security measures will be in place at all times when construction activities are not taking place to safeguard site materials and equipment. This will include fencing, locked off areas, surveillance systems and security lighting. Materials will be stored in the Temporary Construction Compound and fuels and chemicals will be stored it the bunded areas within the compound. The compound will be secured by means of a 2.4m high perimeter chain-link fencing with secure access gates. 6.3 Site Access Safe Access around the Development will be provided for both construction personnel and personnel visiting the site and later for other personnel attending the site during operation and decommissioning. The Development has been designed to ensure access along the stream and rivers on site area maintained. Access along the River, Streams and tributaries will be provided to IFI during the construction works and at operation stage. At construction stage a Site Induction will be provided to personnel visiting the site to ensure safe access is maintained. Site Management contact details will also be provided to IFI to ensure access can be arranged at out of hours times. On completion – at operation stage, contact details for the Wind Farm Operator to ensure access can be arranged as required. 6.4 Signage Warning signs will be erected at the construction works areas to notify people of the construction site and of particular construction related risks in area. Signage will be regularly inspected by the site management team to ensure that they are securely fixed and in good condition. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 39 6.4.1 Site Signage A notice board will be erected at the site entrance and at the Construction Compound gates with information on the contact details for site management, PPE requirements for the site and any other information deemed necessary in accordance with the H&S Plan. Within the site, maximum speed signage will be erected along the Access Track for construction vehicles and health and safety signage will be erected where deep excavations, or other areas of increased risk, are occurring. Signage will also be erected as a reminder to concrete delivery drivers that concrete truck wash-out is not permitted on-site and to direct concrete lorries to the concrete washout area. 6.4.2 Signage on the Public Road Signage will be erected on the L5046 and L50462 Local Access Track both sides of the site entrance locations to warn approaching vehicles, cyclists and pedestrians of the construction site entrance location and the potential presence of slow-moving vehicles. Signage will also be erected along the public road during grid connections works. Public road signage will be in accordance with Monaghan County Council’s requirements and relevant planning conditions. Road signage on the public road will also be in accordance with the current Traffic Signs Manual Chapter 8 and associated best practice guidelines. Signage in respect of traffic management is discussed in the TMP which forms part of the planning applciation. This CEMP is to be read in conjunction with the TMP. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 40 7.0 Environmental Management 7.1 Ecology Impact Mitigation Mitigation by Avoidance The design of the Development has sought to avoid significant negative effects to habitats by minimising the extent of loss of habitats to the footprint of the proposed Development and siting the infrastructure elements of the proposed Development in habitats of low nature conservation value. The positioning of the turbine to the west of the landholding within an area of industrial cutover bog has minimised the potential for habitat loss as well as disturbance to adjacent habitats and fauna occurring in the landholding. Mitigation by Reduction Habitat disturbance during construction work will be confined strictly to within the direct land-take of the proposed Wind Turbine and associated infrastructure, in accordance with the outlined mitigation measures. A Project Ecologist will be appointed for the construction phase and the Project Ecologist will meet with the contractor on site to identify and mark out the required work area. The construction footprint will be kept to a minimum and an impermeable barrier will be installed around the construction area for the turbine base to ensure no surface runoff to surface watercourses. The area of vegetation removal will be kept to a minimum to reduce the exposure of bare soil and peat and the risk of sediment runoff and peat desiccation. An approximate 125m of hedgerow habitat will be removed in order to provide for the proposed turbine hardstand and the access track. An additional 215m of hedgerow habitat will be removed as part of the bat buffer mitigation measure. The loss of this hedgerow habitat will be compensated for by providing a broadleaved hedgerow along the length of the access track from the site entrance to the substation. This will provide for new replacement hedgerow habitat either side of sections of the access track that will at minimum exceed the 340m plus 100% (i.e. the provision of a minimum length of 680m of replacement hedgerow habitat. This will result in a net increase in the extent of this habitat occurring at and in the vicinity of the Development site. It is noted that all new replacement hedgerow will be positioned outside the 50m bat buffer of the rotor swept area of the turbine. 7.2 Mitigation to prevent the spread of non-native invasive plant species Best Practice & Biosecurity The following additional measures will be implemented as standard best practice approach to construction works on site. These measures will be put in place with the aim of avoiding the introduction of other non-native invasive plant species during the construction and decommissioning phase of the Development. The potential for importation or introduction of non-native plant species (such as Japanese Knotweed, Himalayan Balsam, etc.) can arise during construction works on Development sites. Section 49 of the European Communities (Birds and Natural Habitats) Regulations 2011 prohibits the introduction and dispersal of invasive alien species (particularly plant species) listed on Part 1 (third column) of the ‘Third Schedule’. All construction at the Development site will have due regard to the relevant biosecurity measures outlined below:  All plant machinery will be restricted from disturbing known colonies of invasive species.  All plant machinery will avoid unnecessary crossings to adjoining lands. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 41 Good site hygiene will be employed to prevent the introduction and spread of problematic invasive alien plant species (i.e. Japanese Knotweed (Lesser Knotweed), Himalayan Balsam (Impatiens glandulifera), Himalayan Knotweed (Persicaria wallichii), etc.) by thoroughly inspecting and washing vehicles prior to entering the works area. The biosecurity measures outlined above are in line with best practice guidelines issued by the National Roads Authority (NRA, 2010) – The Management of Noxious Weeds and Non-native Invasive Plant Species on National Roads and broadly based on the Environment Agency’s (2013) – The Knotweed Code of Practice: Managing Japanese Knotweed on Development Sites (Version 3, amended in 2013, accessed on the Environment Agency’s website on the 11th of July 2016). In addition to the above, measures for the prevention and spread of Crayfish plague, as detailed under SI 354/2018, the European Union (Invasive Alien Species) (Freshwater Crayfish) Regulations 2018 will be adhered with throughout all construction works and activities. With regard to such measures the simplest is to implement routine cleaning and drying of equipment once leaving a river, and before using it again. This is especially important as it is known that the crayfish plague organism can be carried on wet equipment to new sites. The ‘Check, Clean and Dry’ protocol is an effective barrier. 7.3 Mitigation measures for spoil disposal Spoil will be generated during excavations for foundations at turbines and along new Access Tracks. Minimisation of the production of this spoil will be treated as a high priority, but it is nevertheless expected that peat will be excavated during site works. Spoil types will be treated separately. Glacial soils and peat will be separated during excavation and these two types of spoil will be disposed of generally as follows: A. Glacial soils will be deposited directly on top of other glacial soils. This will require the removal of peat where present to facilitate the process. B. Peat can be disposed of either on top of glacial soils, on top of inactive peat or on top of the “Acrotelm” where the “Top Mat” has been removed. 1. Glacial spoil disposal will take place within a 100m radius of each structure. 2. It is intended that spoil movements will be minimised by disposing of the material within or immediately adjacent to the construction footprint of the structure from whence it was excavated. 3. Preparation of the Spoil Disposal site will involve the removal of the “Top Mat” which will be transplanted to an area of inactive bog and maintained for re-use during restoration operations. 4. Spoil will be deposited, in layers of 0.50m and will not exceed a total thickness of 1.50m. 5. Spoil will only be deposited on slopes of < 10 degrees to the horizontal and greater than 10m from the top of a cutting. The exact location of such areas will be determined on consultation with the geotechnical specialist. 6. A Peat Stability Register will record the location of each Spoil Disposal Site used and regular weekly assessment will be made by the construction manager or other suitably qualified individual. 7. Once disposal is complete the disposal sites will be re-vegetated with the “Top Mat” removed at the commencement of disposal operations. Upon commencement of the restoration phase guidance from a suitably qualified ecologist will be sought to provide a suitable methodology and programme of maintenance for the restored areas. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 42 7.4 Mitigation by Remediation When excavating the Access Track, peat material will be removed and stored separately. This peat will be stored in designated areas and reinstated along the edges of the completed Access Track on completion of construction. The surface of this peat will be seeded with heathland species such as Calluna vulgaris, Erica tetralix, Myrica gale etc. that are typical of the surrounding peatland habitats. All spoil material excavated during the construction phase will be reinstated following the completion of the construction phase of the proposed Development. Suitable temporary storage areas will be identified in advance in association with the site contractors. The Project Ecologist will review any suggested storage areas for possible ecological interests. 7.5 Bird Impact Mitigation The following mitigation measures will be implemented to minimise potential impacts to bird species:  Construction activity such as vegetation stripping will be timed to commence prior to the start of the breeding bird season, which includes the months of March to August inclusive.  A Project Ecologist will be appointed for the duration of construction works to advise the contractor and will visit as necessary when works are in progress to ensure that all mitigation measures are adhered to. The Project Ecologist will be responsible for completing pre-construction transect/walkover surveys over the proposed Development site to ensure that disturbance to breeding birds (such as skylarks) is avoided.  The Project Ecologist will be responsible for undertaking ongoing ornithological monitoring during periods of the construction phase that overlap with the breeding bird season. The ornithological monitoring will focus on identifying the presence of sensitive bird species at the proposed Development site. In the event that sensitive bird species are identified as nesting at or within a 500m buffer zone of the construction footprint, the timing of works will be scheduled to minimise disturbance to nests and/or an appropriate buffer distance between the works and any nest site will be implemented. 7.6 Protection of Bats The Natural England guidance (2014) and NatureScot (2021) recommends that potential collision to bats from Wind Turbine Developments can be minimised by siting the proposed turbines so that all parts of the turbine rotor swept area are over 50 m from the nearest vegetated feature. The location of the proposed turbine will satisfy this recommendation with no vegetated features occurring within 50 m of a turbine rotor diameter. To this end a “bat buffer” area will be implemented around turbine such that the buffer area will remain free of suitable foraging habitat, consisting of conifer plantation edge and scrub. This will require the clearance of conifer plantation within a 91m radius of the turbine hub. The implementation of this buffer will increase the total extent of hedgerow clearance to a total length of 340m. In order to avoid the potential for future interactions between the now proposed turbine and local bat populations all structures associated with the Development (i.e. the substation building) will be built in a manner to ensure no roosting opportunities are present to bats. Also, no structured vegetation will be permitted to establish at these locations during the operational phase of the turbine. 7.7 Noise and Vibration Mitigation The operation of plant and machinery, including construction vehicles, is a source of potential impact that will require mitigation at all locations within the site. Proposed measures to control noise include: RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 43  Diesel generators will be enclosed in sound proofed containers to minimise the potential for noise impacts;  Plant and machinery with low inherent potential for generation of noise and/or vibration will be selected. All construction plant and equipment to be used on-site will be modern equipment and will comply with the European Communities (Construction Plant and Equipment) (Permissible Noise Levels) Regulations;  Regular maintenance of plant will be carried out in order to minimise noise emissions. Particular attention will be paid to the lubrication of bearings and the integrity of silencers;  All vehicles and mechanical plant will be fitted with effective exhaust silencers and maintained in good working order for the duration of the works;  Compressors will be of the “sound reduced” models fitted with properly lined and sealed acoustic covers which will be kept closed whenever the machines are in use and all ancillary pneumatic tools shall be fitted with suitable silencers.  Machines, which are used intermittently, will be shut down during those periods when they are not in use; 7.8 Dust Mitigation Measures The following section details plans to ensure that air quality (airborne dust and pollutants) within the environs of the Development site is maintained at acceptable levels throughout the construction period Best practice construction methodologies will be employed to minimise the creation and dispersion of airborne dust created and to limit construction vehicle emissions. Specific measures which will be implemented at the site include:  Transport of materials to and from the site will take place in normal working hours and along routes agreed with the local authority.  Where necessary lorries accessing and egressing the facility will be covered.  Vehicle speeds will be restricted on haul tracks.  Vehicles will be routinely maintained to minimise vehicular emissions.  Site haul tracks will be dampened down using water bowsers during prolonged dry periods if necessary.  Dusty materials such as excavated materials will be stored and handled appropriately (e.g. covering where necessary and minimising the drop heights of materials).  Materials likely to be a source of dust will be transported in an appropriate manner (e.g. covering of load).  Use of suitable hoardings at construction site to prevent wind blow of materials.  Incorporation of appropriate dust monitoring into site management practices.  Timely completion of all construction.  Good maintenance of internal haul tracks. 7.9 Fuels and Oils Management Construction vehicles will be refuelled off-site, wherever possible. This will primarily be the case for road vehicles such as vans and trucks. However, for construction machinery that will be based on-site continuously, a limited amount of fuel will have to be stored on site. The construction machinery refuelling on site will be required to refuel in a bunded refuelling area in the temporary compound. Oils, lubricants, and other hazardous liquids required for maintenance of equipment during the construction phase will be stored on the dedicated impermeable storage platform in the construction compounds. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 44 At least daily checks prior to start-up of plant and machinery will minimise the risk of breakdown and associated contamination risks for on-site repairs. Records of daily pre-start checks will be maintained and kept in the site office. A clean site policy and diligent housekeeping will also reduce the potential of hydrocarbon release on-site. 7.10 Climate There is the potential for a number of embodied greenhouse gases (GHGs) and GHG emissions during the construction phase of the Development. Construction vehicles, generators etc., may give rise to CO2 and N2O emissions as well as the large quantities of material such as stone, concrete, and steel that will be required for the proposed Development. The Institute of Air Quality Management (IAQM) document Guidance on the Assessment of Dust from Demolition and Construction (2014) states that site traffic and plant is unlikely to make a significant impact on climate. To minimise climate impacts associated with delivery of construction materials to the site, the Contractor will source quarry materials as close to the site location as possible and use local builder’s providers where possible. 7.11 Surface Water Management Plan Details on the proposed surface water drainage and surface water management are contained in Planning Drawings 2290-102 to 105 and 150 to 154. 7.11.1 Design Principles Dirty water is generated on wind farm sites predominantly during the construction phase. The dirty water is generated through movement of soil material around the site and breaking down of the track surface under sustained loading from construction traffic. Silt removal from dirty water runoff will be either by filtration or by means of Settlement Ponds as described below. An important aspect of the treatment process is that clean water from outside the works area is not mixed with dirty water from within the works area. This minimises the quantity of water to be treated and consequently reduces the size and quantity of Settlement Ponds where they are used. Clean water flows from the uphill side of catchments to the downhill side. Having this water pass through the works unimpeded reduces the risk of mixing with dirty water and ensures a smaller quantity of dirty water remains for treatment. Clean water will pass through tracks of stone construction due to its porosity via overland flow. Separation of clean and dirty water drains is shown in Figure 7-1. Clean water cut-off drains will be provided on the uphill side of infrastructure where it is undesirable to have clean water enter the works. Such locations would be on the uphill side of material storage areas where overland flow is unlikely to pass through unimpeded and mixing with dirty water is likely to occur. These drains are routed through to the downhill side of the works and discharged through buffered outfalls. Where drains are constructed, they will incorporate a series of check dams that will attenuate the flow and provide storage for the increased runoff from exceptional rainfall events. Check dams will comprise single size drainage stone a geotextile barrier that will be embedded into the base and sides of ditches by at least 100mm. 7.11.2 Design Methods Two distinct methods will be employed in the management of construction surface water runoff. The first method involves ‘keeping clean water clean’ by avoiding disturbance to natural drainage features, minimising any works in or around artificial drainage features, and diverting clean surface water flow around excavations, construction areas RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 45 and temporary storage areas. The second method involves collecting any drainage waters from works areas within the site that might carry silt or sediment, and nutrients, and to route them to Settlement Ponds prior to controlled diffuse release over vegetated natural surfaces. At the construction phase, there will be no direct discharge to streams or rivers; and all release of wind farm drainage is to be carried out outside of hydrological buffer zones. A schematic of this approach is presented in Figure 7-1. During the construction phase all runoff from works areas (i.e. dirty water) will pass through a series of In-Line Control measures, to Water Treatment Control measures prior to being released via buffered outfalls to vegetated natural surfaces. Figure 7-1 - Surface Water Drainage Control Measures Schematic 7.11.3 General Drainage Provisions The Temporary and Permanent Surface Water Drainage network and systems has been designed to be easily maintained and suitable for the duration of the Construction and Operation of the proposed Project. Crossfalls on constructed elements will have a minimum cross fall of 1:40 to avoid ponding of surface water. Existing drainage networks will be retained and protected where possible. At the construction phase there will be no direct discharge to existing watercourses; discharge will be by means of Level Spreaders discharging over vegetated natural surfaces. On completion of the works, constructed permanent works drainage will be incorporated and discharge into the existing drainage arrangements but will include Attenuation / Settlement Ponds at discharge points to ensure drainage discharges are controlled, inspected and managed throughout the operational phase of the proposed Project. 7.11.4 Buffer Zones Buffer zones will be maintained around all identified watercourses and surface water open drains. 50m buffer zones are to be provided to watercourses and 10 m buffer zones are to be provided to open drains where possible. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 46 7.11.5 Office of Public Works Section 50 Approval All works to watercourses and related structures require the approval of the Office of Public Works (OPW) in accordance with Section 50 of the Arterial Drainage Act 1945. As part of the construction phase detailed design process, Section 50 consent will be sought from the OPW for all works that watercourses and related structures. 7.11.6 Watercourse Crossings 7.11.7 Culvert Crossings All new permanent works culvert crossings will have a minimum pipe diameter of 900mm and pipe embedment of 300 mm. All new culverts and upgrades to existing crossings will be designed to accommodate the projected peak flow rates, factoring in local hydrology and the depth of the track subbase. In locations with constrained depth, the installation of multiple smaller diameter pipes may be necessary, though this practice will be minimized to reduce the risk of blockages. Where feasible, culverts will be oversized to facilitate easy access for cleaning and long-term maintenance. Culverts will be installed with a minimum internal gradient of 1% (1 in 100) to ensure optimal water conveyance and to prevent sediment accumulation. In areas with higher water energy, downstream armouring with large stones (riprap) will be employed to dissipate flow energy and prevent erosion, safeguarding the integrity of both the infrastructure and the surrounding environment. For smaller watercourses, properly sized pipes will be buried in the track’s subbase at the correct invert levels to avoid ponding or pooling either upstream or downstream of the culvert, ensuring that natural water flow remains uninterrupted. 7.11.8 Stream Crossing – Bridge Installation A 10.2m clear span bridge will be constructed to cross the EPA Registered Stream, Code; IE_NW_36F010500, Segment; 36_436, Name; Legarhill. The bridge will be designed to minimize environmental disturbance, while still accommodating peak water flow during periods of heavy rainfall or storm events, ensuring that the natural hydrology of the stream remains intact. As far as is practicable the bridge crossing works over the Legarhill stream will be programmed to be carried out between the time period 1st May to 30th September. Further details on the proposed bridge location and design can be found on the Planning Drawing 2290-154. 7.11.9 Maintenance and Inspection Protocols During the construction phase, all culverts will undergo regular weekly inspections, particularly following heavy rainfall or storm events, to ensure they remain clear of obstructions such as debris, vegetation, or sediment. During the operational phase and after a storm event, biannual inspections will be conducted to monitor the condition of the crossings, ensuring the continued free flow of water and early detection of any maintenance needs. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 47 7.11.10 Control Measures Control Measures designed to control and manage silt in construction-related surface water runoff will be deployed during the works. Table 7-1 below provides detail on the proposed Control Measures and locations where’re they will be deployed. Management Type Description of SuDS drainage control method Applicable Works Area Avoidance Controls:  Application of 20m buffer zones to natural watercourses where possible;  Using small working areas;  Working in appropriate weather and suspending certain work activities in advance of forecasted wet weather. Construction work areas where sediment is being generated. Source Controls:  Use of upstream interceptor drains and downstream collector drains / oversized swales, vee-drains, diversion drains, flumes and culvert pipes. Construction work areas where sediment is being generated.  Erosion and velocity control measures such as: o sand bags; o filter fabrics; o weirds or check dams; o and other similar/equivalent or appropriate systems. Drainage crossings  Using small working areas; o Covering stockpiles; o Weathering off / sealing peat stockpiles where applicable. Stockpiles areas In-Line Controls:  Interceptor drains; vee-drains, oversized swales/collector drains;  Erosion and velocity control measures such as: o sand bags; o filter fabrics; straw bales; flow limiters; weirs or check dams; o and/or other similar/equivalent or appropriate systems.  Silt fences, filter fabrics;  Collection sumps, temporary sumps, pumping systems;  Attenuation ponds;  Swales  Sediment traps, stilling / Settlement Ponds. Interceptor and collection drainage systems Water Treatment Controls:  Temporary sumps;  Swales  Sediment traps, stilling / Settlement Ponds.  Silt bags, proprietary settlement systems such as Siltbuster, and/or other similar / equivalent or appropriate systems. Pumping and surface water treatment locations Outfall Controls:  Level Spreaders;  Buffered outfalls;  Vegetation filters;  Flow limiters and weirs. Drainage run outfalls and overland discharge points Table 7-1 – Control Measures and their Applications RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 48 7.11.11 Surface Water Drainage Measures The surface water drainage will be designed to ensure that surface water runoff from the development matches the existing “Green Field” runoff rate. 7.11.11.1 Construction Stage At construction stage this will be achieved by the provisions of Dirty Water Cut-off Drains which will intercept runoff from tracks, hardstands and other works and direct it to infiltration and settlement ponds. The Dirty Water Cut-off Drains will also provide attenuation storage and soakage infiltration. The Dirty Water Cut-off Drains will flow into Settlement Ponds, these will designed to attenuate the surface water flow allowing soakage into the subsoil and settlement of suspended solids. The outflow from the Settlement Ponds will discharge overland via buffered outfalls. Silt fencing, check dams and swales have also been incorporated into the design to provide filtration measures, to slow the flow rate of runoff water into the Dirty Water Cut-off Drains. Measures that will be implemented at the construction phase will include:-  Clean Water Cut-off Drains;  Dirty Water Cut-off Drains;  Silt Fencing;  Check Dams;  Swales;  Buffered Outfalls;  Settlement Ponds;  Silt Buster;  Wheel Wash;  Vegetation Filters;  Level Spreaders. The above features are described further in the sub section below, further details can be found on the Planning Drawings 150 to 153. 7.11.11.2 Operation Stage Measures – the Permanent Works At completion of the permanent works (operation phase), attenuation ponds with infiltration drains and level spreader outfalls will be provided to permanent drainage measures to ensure flow is discharged in a controlled manner. These measures will provide filtration and settlement thus ensuring adequate removal of suspended solids and sediments and prevent any deleterious matter from discharging into any natural watercourses. The existing surface water and ground water flow patterns will also be maintained by the uses of “Plugs” and diffuse flow paths details. Water quality will be monitored on site once construction is complete – this will involve a visual inspection of open drains as well as monthly sampling and testing. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 49 Sampling will cease when Roscommon County Council, IFI and other appropriate Stakeholders are satisfied that there are no adverse impacts to the natural watercourses and that surface water quality parameters are in line with baseline levels. Measures that will be implemented at Operation Phase will include:-  Maintenance Manual and Regime;  Open Drains and Swales;  Check Dams;  Level Spreaders; 7.11.11.3 Decommissioning Phase Measures that will be implemented at decommissioning phase will be as per the measures listed at construction phase above. 7.11.11.4 Clean Water Cut-off Drains Clean Water Cut-off Drains will be installed on the uphill side of works areas to intercept surface water runoff. The Clean Water Cut-off Drains will direct upslope clean surface water away from the works area, thus preventing it from coming into contact with exposed surfaces and picked up silt and sediment. The drains will divert the upslope clean surface water to a location where it can be redistributed over the ground surface as sheet flow. This will minimise the volume of potentially silty runoff to be managed within the construction area. Clean Water Cut-off Drains will be installed in advance of any main construction works commencing. The material excavated to make the drain will be placed on the downslope edge of the drain. The velocity of flow in the Clean Water Open Drains will be controlled by the use of Check Dams, (see Section 7.11.11.7 below), which will be installed at regular intervals along the drains to ensure flow in the channel is non- erosive. On steeper sections where erosion risks are greater, a geotextile membrane will be added to the channel. The check dams will also promote sedimentation behind the dam. The check dams will be installed as the Clean Water Open Drains are being excavated. Clean Water Open Drains will be installed horizontally across slopes to run in parallel with the natural contour line of the slope. Intercepted water will travel along the Clean Water Open Drains to areas downgradient of works areas, where the drain will terminate at a Buffered Outfall or Level Spreader. Across the entire length of the Clean Water Open Drains, the design elevation of the water surface along the route of the drains will not be lower than the design elevation of the water surface in the outlet at the Buffered Outfall or Level Spreader. On completion of the construction works, the Clean Water Open Drains will either be removed or reconfigured to be incorporated into the operational phase surface water drainage. Where the drains are to be removed, they will be backfilled with the material placed on the downslope edge of the drain. 7.11.11.5 Dirty Water Cut-off Drains Dirty Water Cut-off Drains will be installed downgradient of works areas to collect surface flow runoff and to prevent run off from excavations and construction areas of the site into existing watercourse, where it might have come RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 50 into contact with exposed surfaces and picked up silt and sediment. The drains will be used to take runoff from the works area to a location where it can be treated via Settlement Ponds or other silt and sediment removal measures. The velocity of flow in the Dirty Water Open Drains will be controlled by the use of Check Dams, (see Section 7.11.11.7 below), which will be installed at regular intervals along the drains to ensure flow in the channel is non- erosive. On steeper sections where erosion risks are greater, a geotextile membrane will be added to the channel. The check dams will also promote sedimentation behind the dam. The check dams will be installed as the Dirty Water Open Drains are being excavated. On completion of the construction works, the Dirty Water Open Drains will either be removed or reconfigured to be incorporated into the operational phase surface water drainage. Where the drains are to be removed, they will be backfilled with the material excavated from the Site. 7.11.11.6 Silt Fencing Silt fences will be installed as a water protection measure along cut-off drains and around existing watercourses in certain locations, particularly where works are proposed within the 50-metre buffer zones. Silt fences will also be installed around existing access track crossing culverts and pipes. Silt fences will be installed as single, double or a series of triple silt fences, depending on the space available and the anticipated sediment loading. The silt fence designs follow the technical guidance document ‘Control of Water Pollution from Linear Construction Projects’ published by Construction Industry Research and Information Association (CIRIA, No. C648, 1996). Up to three silt fences may be deployed in series. All silt fencing will be formed using Terrastop Premium or equivalent silt fence product. Silt fences will be inspected regularly to ensure water is continuing to flow through the fabric, and the fence is not coming under strain from water backing up behind it. A typical silt fence is shown in Figure 7-2. Figure 7-2 – Typical Terrastop Silt Fence RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 51 7.11.11.7 Check Dams The velocity of flow in the Clean Water Open Drains and drainage swales, particularly on sloped sections of the channel, will be controlled by check dams, which will be installed at regular intervals along the drains to ensure flow in the swale is non-erosive. Check dams will restrict flow velocity, minimise channel erosion and promote sedimentation behind the dam. The check dams will be installed as the Clean Water Open Drains are being excavated. Check dams may also be installed in some of the existing artificial drainage channels on the Site, downstream of where drainage swales connect in. The proposed check dams will be made up of straw bales or stone, or a combination of both depending on the size of the drainage swale it is being installed in. Where straw bales are to be used, they will be secured to the bottom of the drainage swale with stakes. Clean 4 to 6 inch stone will be built up on either side and over the straw bale to a maximum height of 600mm over the bottom of the interceptor drain. In smaller channels, a stone check dam will be installed and pressed down into place in the bottom of the drainage swale with the bucket of an excavator. Figure 7-3, below, shows illustrative examples of check dams. The check dams will be installed at regular intervals along the Clean Water Open Drains to ensure the bottom elevation of the upper check dam is at the same level as the top elevation of the next down-gradient check dam in the drain. The centre of the check dam will be approximately 150mm lower than the edges to allow excess water to overtop the dam in flood conditions rather than cause upstream flooding or scouring around the dams. Check dams will not be used in any natural watercourses, only artificial drainage channels and Clean Water Open Drains. The check dams will be left in place at the end of the construction phase to limit erosive linear flow in the drainage swales during extreme rainfall events. Check dams are designed to reduce velocity and control erosion and are not specifically designed or intended to trap sediment, although sediment is likely to build up. If necessary, any excess sediment build up behind the dams will be removed. For this reason, check dams will be inspected and maintained regularly to ensure adequate performance. Maintenance checks will also ensure the centre elevation of the dam remains lower than the sides of the dam. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 52 Figure 7-3 – Typical Check Dam 7.11.11.8 Swales Swales are shallow drains that will be used to intercept and collect run off from construction areas of the Site during the construction and operational phase. A swale is an excavated drainage channel located along the down-gradient perimeter of construction areas, used to collect and carry any sediment-laden runoff to stilling ponds for attenuation and treatment. Swales will be installed in advance of any main construction works commencing. All swales and ponds will be kept as shallow as possible so that they do not pose a health and safety risk to personnel. Maximum depth of standing water will be limited to 0.3m within the swales. 7.11.11.9 Buffered Outfalls Buffered Outfalls will be constructed at the end of Cut-off Drains, Silt Ponds and other Control Measures to convert concentrated flows into diffused sheet flow on areas of vegetated ground. Buffered Outfalls will be located downgradient of any proposed works areas in locations where they are not likely to contribute further to water ingress to construction areas of the Site. Buffered Outfalls will distribute clean drainage water onto vegetated areas where the water will not be re- concentrated into a flow channel immediately below the point of discharge. The discharge point will be on level or only very gently sloping ground to prevent erosion. The slope in the channel leading into the Buffered Outfall will be less than or equal to 1%. The slope downgradient of the spreader onto which the water will dissipate will have a grade of less than 6%. The availability of slopes with a grade of 6% or less will determine the locations of Buffered Outfalls. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 53 7.11.11.10 Settlement Ponds Settlement Ponds will be used to attenuate runoff from works areas of the Site during the construction phase. The purpose of the Settlement Ponds is to intercept runoff potentially laden with sediment and to reduce the amount of sediment leaving the disturbed area by reducing runoff velocity. Reducing runoff velocity will allow larger particles to settle out in the Settlement Ponds, before the run-off water is redistributed as diffuse sheet flow in filter strips downgradient of any works areas. The points at which water enters and exits the Settlement Ponds will be stabilised with rock aprons, which will trap sediment, dissipate the energy of the water flowing through the Settlement Pond system, and prevent erosion. Water will flow out of the secondary Settlement Pond through a stone dam, partially wrapped in geo-textile membrane, which will control flow velocities and trap any sediment that has not settled out. Figure 7-4 shows an illustrative example of a Settlement Pond system. Water will flow by gravity through the Settlement Pond system, they will be sized according to the size of their catchment area. The Settlement Ponds will be dimensioned so that the length to width ratio will be greater than 2:1, where the length is the distance between the inlet and the outlet. Each Settlement Pond will be a minimum of 1-1.5 metres in depth. Deeper ponds will be used to minimise the excavation area needed for the required volume. The embankment that forms the sloped sides of the Settlement Ponds will be stabilised with vegetated turves, which will have been removed during the excavation of the Settlement Ponds area. All material excavated during pond construction will be used locally for landscaping and berm construction around these ponds. Settlement Ponds will be located towards the end of swales, close to where the water will be reconverted to diffuse sheet flow. Upon exiting the Settlement Pond system, water will be immediately reconverted to diffuse flow via a fan-shaped rock apron if there is adequate space and ground conditions allow. Otherwise, a swale will be used to carry water exiting the Settlement Pond system to a Buffered Outfall or Level Spreader to reconvert the flow to diffuse sheet flow. Settlement Ponds will be inspected weekly and following rainfall events. Inlet and outlets will be checked for sediment accumulation and anything else that might interfere with flows. Settlement Pond Design Settlement Ponds will be designed in accordance with the requirements set out in the following documents:-  Roscommon County Development Plan 2022-2028  The SuDS Manual (C753) 2015, CIRIA;  The Greater Dublin Regional Code of Practice for Drainage Works.  Inland Fisheries Ireland (IFI) Guidelines on protection of fisheries during construction works in and adjacent to waters; EPA - Environmental Management Guidelines; Environmental Management in the Extractive Industry (Non-Scheduled Minerals) The size of the Settlement ponds will be based on the following parameters:- RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 54  A 1 in 10 year rainfall return design.  11 hour retention period.  Outlet flow rate from the pond will be the appropriate Greenfield runoff rate for the pond catchment area..  The rational method is subsequently applied to calculate the flow volumes into each attenuation pond over these respective periods. The Rational Method is expressed by the formula V = 2.78.C.A.I.t , where V is the volume of water generated in the stilling pond, C is the run-off co-efficient, A is the area of the hardstanding / catchment, I is the rainfall depth and T is the duration of rainfall occurrence.  A runoff coefficient of 0.95 (95%) is conservatively applied to all hardstanding areas. Figure 7-4 – Settlement Pond 7.11.11.11 Silt Buster A “Siltbuster” or similar equivalent piece of equipment will be available to filter any water pumped out of excavation areas, if necessary, prior to its discharge to stilling ponds or swales. Siltbusters are mobile silt traps that can remove fine particles from water using a proven technology and hydraulic design in a rugged unit. The mobile units are specifically designed for use on construction sites. The unit stills the incoming water/solids mix and routes it upwards between a set of inclined plates for separation. Fine particles settle onto the plates and slide down to the base for collection, whilst treated water flows to an outlet weir after passing below a scum board to retain any floating material. The inclined plates dramatically increase the effective settling area of the unit giving it a very small footprint on site and making it highly mobile. Figure 7-5 below shows an image of the Siltbuster. The Siltbuster units are now considered best practice for the management of dirty water pumped from construction sites. The UK Environment Agency and the Scottish Environmental Protection Agency have recommended the use of Siltbuster units on construction projects. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 55 Figure 7-5 – Typical Silt Buster 7.11.11.12 Vegetation Filters Vegetation filters are the existing vegetated areas of land that will be used to accept surface water runoff from upgradient areas. The selection of suitable areas to use as vegetation filters will be determined by the size of the contributing catchment, slope and ground conditions. Vegetation filters will carry outflow from the Level Spreaders as overland sheet flow, removing any suspended solids and discharging to the groundwater system by diffuse infiltration. Vegetation filters will not be used in isolation for waters that are likely to have higher silt loadings. In such cases, silt-bearing water will already have passed through Settlement Ponds prior to diffuse discharge to the vegetation filters via a Level Spreader. 7.11.11.13 Level Spreaders Level Spreaders will be utilised at the permanent works surface water drainage outfall points. These will be used to convert concentrated surface water flows in drains into diffuse sheet flow on areas of vegetated ground. The Level Spreaders will distribute clean drainage water onto vegetated areas where the water will not be re- concentrated into a flow channel immediately below the point of discharge. Levels Spreaders will be located down slope of works areas, the spreader will be constructed in-line with ground contours. Concentrated surface water flow will be diffused into overland flow via a “capping” perforated drainage pipe surrounded in clean single sized drainage stone. The length of the capping pipe will be subject to the ground conditions local to the Level Spreader and the design drainage flow at that location. A Level Spreader detail is provided in Figure 7-6. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 56 Figure 7-6 - Level Spreader 7.12 Land, Soils, and Geology The disturbance of soil, subsoil and bedrock is an unavoidable effect in the Development of the proposed infrastructure at the site, however excavations for the infrastructure will be kept to a minimum to limit disturbance of the current ground conditions and to minimise costs associated with earthmoving. The management of excavated materials is an important component of controlling dust as well as sediment and erosion control. Excavated topsoil, subsoils, where encountered, will only be moved short distances from the point of extraction and will be used locally for landscaping and benching/battering, where possible. Excavated material will not be stored in excessive mounds on the site. 7.13 Site Meetings Site Meetings between the site management team and site personnel will be held at regular intervals. The objectives of the Site Meetings are to discuss the coming weeks proposed activities and identify the relevant work method statements and sub plans that will be relevant to that week’s activities. Additionally, any non-compliance identified during the previous week would also be discussed with the aim to reduce the potential of the same noncompliance reoccurring. 7.14 Toolbox Talks A Toolbox Talk is a short presentation to site personnel on a single aspect of health and safety, environmental awareness and work methodologies on site. They are given to ensure that site personnel are aware of the standard of work practices that are expected and to make them aware of their responsibilities. Toolbox Talks will be given on site by a member of the site management team. There will be generally 2 to 4 Toolbox Talks each week throughout the construction period. The toolbox talks will include training and awareness on:-  Ecological sensitive areas on site;  Buffers zones on site – e.g. At watercourses, archaeological exclusion zone, ecological zone;  Sediment and erosion control; RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 57  Site housekeeping;  On-site traffic routes and vehicle use;  Site rules;  Strictly adhering to the Development footprint;  Fuel storage on site;  Fuel spill prevention and control;  Materials and waste recycling procedures;  Water pollution in relation to cement and concrete handling;  Dust management. 7.15 Site Monitoring All mitigation measures and works for compliance with planning conditions and the planning reports will be implemented on site across the duration of the works. The Construction Manager & ECoW will provide Audit Checklists to ensure regular checks of the site’s control measures for the ongoing construction works and protection of the environment. Checklists for daily, weekly or monthly site audits will be finalised by the Construction Manager & ECoW and the relevant personnel informed of their duties. Checklists will include:-  Confirmation that fuel is stored appropriately;  Waste management rules are adhered to;  All environmental buffers are maintained;  Surface water and run-off control measures of the area in place and functioning;  Concrete wash-out procedure is being followed All environmental records, including completed checklists, will be retained at the site office. 7.16 Complaints A provisional Complaints Management Plan has been prepared for the Development; this is included in Appendix A. The CMP will be developed further at construction stage and adopted by contractors prior to commencement of construction activities. The CMP will form part of the overall site induction and will be reviewed with site personnel regularly as part of Toolbox Talks and Site Meetings. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 58 8.0 Waste Management Plan This section of the CEMP provides a Waste Management Plan (WMP), which outlines the best practice procedures during the construction phase of the Development. 8.1 Objectives The following section details plans to maximise the re-use and/or recycling of construction materials throughout the construction of the Development. The management of all waste arising from construction activities will be in accordance with EU, National and Regional waste management policy. The Contractor acting as the project supervisor construction stage will be the organisation appointed for managing waste and will strive to adopt a systematic approach to waste management to ensure compliance with all laws and achieve continuous performance improvement. Waste management objectives are to reduce the production of waste to a minimum, to reuse or recycle where practicable and to ensure that people and the environment are not compromised by poor waste management practices. In accordance with the EU Waste Hierarchy, the following Waste Management priorities will be established going from 1st priority to 6th priority; 1. Prevent material wastage where possible. 2. If prevention is not possible then minimise the quantities of waste. 3. Reuse of site materials where possible. 4. Recycling of waste where reuse is not possible. 5. Energy recovery where none of the above options are feasible. 6. Disposal as a last resort. The management of materials is key when implementing an effective waste prevention and minimisation policy on site. Important considerations include the following;  Avoidance of ‘over ordering’ of materials and generating materials surplus to requirements.  Agreeing a ‘take back’ arrangement with suppliers for surplus materials.  Inspection of delivered materials to ensure they are not damaged and can be used on site.  Selection of correct materials storage systems to avoid damage and unnecessary generation of waste.  Consideration of materials packaging. 8.2 Anticipated Waste Streams C&D waste will arise on the Development as a result of the unavoidable waste of construction materials and the equally unavoidable damage of materials on site. It is the responsibility of the Project Manager to ensure that such waste is minimised. This WMP sets out the framework for the management of all wastes generated from construction related activities. This WMP will assist in delivering an integrated materials management system for the Development which is based on best practice principles of waste minimisation and source separation. As the construction advances, the WMP may be revised to take account of any relevant changes. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 59 Construction activities on-site will lead to the generation of multiple waste streams, all of which will need to be managed within the site. The key wastes which have been identified as being likely to occur during the Development are outlined in Table 8-1 below. Waste Stream Source Metals Steel Reinforcement Concrete Reinforcing Works Mesh Concrete Reinforcing Works Concrete Brick, Tile And Ceramic Waste Concrete Foundation Pour Concrete Wash Water Concrete Lorry Washout Timber Waste Pallets Deliveries Timber Offcuts Normal Construction Activities Plastic Ducting Offcuts Internal Cables Wrapping / Packaging Deliveries General Waste Mixed ‘municipal type’ solid waste Canteen Waste Dry mixed recyclable wastes Packaging, office paper, newspapers, magazines, spent drinks cartons, cans, plastic bottles and tetrapak. Packaging Packaging Hazardous Waste Ink cartridges Office Waste Table 8-1 – Key Wastes 8.3 Separation & Handling A policy of source separation will maximise material recycling and recovery and minimise the quantity of waste requiring disposal. Segregated waste streams can facilitate downstream recovery at third party recycling facilities and will be adopted on this Development. During construction all waste materials will be segregated into one of the waste streams detailed in Table 8-2 below. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 60 WASTE TYPE STORAGE LOCATION Metal waste Metal Waste Skip Material Storage Area Concrete / Brick / Tile Stockpile Material Storage Area Timber Waste Timber Waste Skip Material Storage Area Plastic Waste Bins in Site Office / General Waste Skip Office / Material Storage Area General recyclable waste Stored in Site Office Site Office General ‘municipal type’ solid waste General Waste Skip Material Storage Area Hazardous waste Chemical Store Temporary Compound Liquid Waste No liquid waste to be stored on site NA Excavated Material’s No storage – Either removed to form embankments on the site or removed from site as generated Not stored onsite Table 8-2 Waste Streams Each of these waste streams will be stored separately in clearly labelled and isolated containers and/or areas. Each stream will be collected by waste handling firms who will further segregate materials for downstream recovery / processing / recycling and final disposal. Each third-party waste handler is required to hold the appropriate licence or permit for each particular waste stream that they handle. The implementation of a waste separation approach requires all site staff, contractors, and sub-contractors to be made fully aware of, and to adopt the principles that underline this plan. The following actions will be implemented to ensure the level of reuse and source separation of material will be maximised over the course of the Development:  The waste streams described above will be kept segregated through the use of separate bins, storage containers or clearly defined areas for stockpiling;  Individual waste streams continue to be kept separate during all handling activities;  All site operatives are made aware of the waste management policies and procedures on-site through appropriate training and signage;  All site operatives are responsible for wastes generated during the works.  During construction, reusable and recyclable waste streams will be stored separately to residual wastes. This will avoid contamination and will maximise their reuse potential. All wastes will be stored at the Material Storage Area in a purposely constructed Waste Management Compound (WMC). 8.4 Waste Description and Management Principles Procurement of Development construction materials will be accurately quantified in order to prevent unnecessary C & D waste. Material procurement and deliveries will be carefully managed to prevent and minimise waste, typically resulting from over-ordering and spoilage due to lengthy storage. The following sections describe Development waste expected to be generated. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 61 8.5 Concrete Concrete will be required throughout the construction works. Care will be taken to ensure careful handling and placement of ready-mix concrete. Precast concrete will not be stored onsite to minimise the potential for spoilage and waste. Any concrete waste will be source-segregated and stored in a suitable receptacle or isolated storage stockpile to prevent cross-contamination. This waste material will be removed off-site for recovery/recycling to a permitted or licensed facility or will be used onsite as fill. Concrete wash waters have potential to cause pollution if managed inappropriately. Typically, this by-product has a high pH (11-12), high suspended solids, and other trace materials, some originating from cement, others from additives or from the mixing equipment. Concrete mixers, delivery lorries and related equipment (chutes, pump lines, drums, barrows etc.), need to be washed off regularly to ensure concrete material is not deposited unintentionally at locations around the site or on the public roadway. The amount of wash water produced daily will vary depending on the volume of concrete delivered to site each day. Typically, 20 litres of wash water is generated per concrete delivery load. To eliminate the risk of pollution the Contractor will provide a dedicated wash out area/lagoon with an impermeable membrane for the storage of concrete wash water. Wash down water from exposed aggregate surfaces, cast-in-place concrete and from concrete trucks will be trapped within the washout area to allow sediment to settle out. Water will be clarified and allowed to reach neutral pH before it is released to a site drainage system. Prior to any discharge of wash water, the pH will be checked and recorded. Should wash water have a pH above 9 then there will be no discharge to drainage channels onsite, instead wash water will be tankered offsite to a wastewater treatment facility for disposal. Should wash water consistently have a pH above 9 (even after settlement and clarification) then onsite pH adjustment may be investigated to facilitate discharge to site drainage. 8.6 Metal Metal materials will be used throughout the construction site in the form of piping, structural reinforcement, and other applications. All metal materials will be stored securely until required. Metals will be stored separately to ensure maximum recovery of the material off-site at a licensed metal recycling facility. 8.7 Wood /Timber Wood /timber materials will be used extensively throughout the construction works. Virgin wood materials delivered on-site will require careful handling to prevent dampness, warping and fungal attack. All wood materials will be kept dry and bound, packaging will only be removed immediately prior to use. Timber waste includes general timber off-cuts, timber sheeting or general timber materials. The bulk of this material will be considered a resource and will be reused onsite. Where timber is no longer of any value it will be removed to a dedicated waste timber storage area, kept separate from other waste materials until sufficient quantities have been collected to warrant removal from site. Timber materials removed off-site for recovery/recycling will be handled by a permitted or licensed collector and removed to a recycling facility. 8.8 Packaging Materials delivered to the construction site are often wrapped and protected by packaging material such as plastic film, wooden pallets, cardboard, metal wrap, cellophane wrapping, and Styrofoam. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 62 Since the establishment of the REPAK producer responsibility scheme, many building suppliers will take back packaging waste. Over the course of the Development, the nominated contractors will be encouraged to source such suppliers, to minimise packaging waste on-site and associated waste management costs for recovery/disposal. Once packaging is removed it will be stored in a closed skip to prevent windblown littering. 8.9 General Wastes The general waste can be broadly grouped into the following categories:  Mixed Dry Recyclables (MDR): Non-confidential waste paper, newspaper, leaflets, card, plastic bottles and packaging, aluminium cans/tins and Tetra Pak.  Food Waste: food waste generated at the site.  Mixed Residual Waste (MRW): Mixed waste that is not collected in the separate recycling bins.  Glass containers glass (bottles and jars). This waste stream should be collected separately from other recyclables.  Textiles such as clothing, rags and any other textile materials. Due to the small quantities of these wastes that are likely generated on site the majority of ‘General wastes’ will be incorporated into the mixed residual wastes (MRW) fraction. This waste will be generated throughout all working areas such as site offices, canteens and equipment storage areas. General waste will be bagged and stored in a 240-litre wheelie bin at each point of generation. A covered skip will be provided for the storage of general wastes prior to its collection and removal off-site by a permitted waste collector. Where possible a waste collector will be selected that delivers waste to a downstream waste processing facility rather than a contractor who delivers waste straight to landfill. It is the policy of The Contractor to promote the use of a 4-bin source segregated recycling system for dry recyclables where it is practical to do so. This recycling system segregates food waste, glass and general waste at source. 8.10 Hazardous Materials Hazardous wastes generated on-site are likely to include, aerosols, paints, glues/adhesives, batteries, ink cartridges, insulating materials, used containers for hazardous materials, light bulbs and fluorescent tubes as well as small quantities of oils, fuels, hydraulic fluids. Hazardous materials will arise in a number of different locations around the site including all works areas, the canteen/office areas, storage areas as well as any area used for vehicle or equipment maintenance. The exact storage arrangements for hazardous wastes will be dependent on the segregation requirements of the waste handler who will be contracted to remove hazardous waste from the site. In general, however, all hazardous wastes will be stored inside lockable cabinets or containers and will not be left out in the open. Suitable storage containers for hazardous waste will vary depending on the type of material requiring storage. Liquid hazardous wastes will be stored in sealed, bunded storage tanks of varying capacities. Light bulbs and fluorescent tubes will require suitably sized rigid containers. All hazardous waste containers will be clearly labelled to indicate the contents. If applicable, hazardous wastes will be stored in accordance with the details outlined in the relevant Material Safety Data Sheets (MSDS). All hazardous waste materials will be removed off-site by a contractor permitted to transport RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 63 hazardous wastes for safe disposal at a licensed facility. A contractor selection process will be conducted which will adhere to specific criteria and include a due diligence audit. 8.11 Other materials It is envisaged that other materials such as textiles (e.g. Personal Protective Equipment), glass, etc. will be generated in relatively small amounts. Where this equipment is not hazardous it will be incorporated into the general waste stream. Where it is deemed hazardous it will be disposed of in accordance with safety instructions supplied with the equipment or in the appropriate hazardous waste container. In keeping with the management principles, all other materials will be kept bound, with packaging only to be removed when the materials are ready to be used. Any breakable materials such as glass or PVC piping will be stored in a safe location away from vehicular movements onsite. Further miscellaneous wastes include waste electrical equipment such as mobile phones, kitchen appliances and power tools. Small quantities of wet and dry batteries and waste electrical wiring will also be generated. All such items will be disposed of in accordance with the WEEE Directive at an appropriate recycling facility. It is not anticipated that such items will be generated in sufficient bulk to warrant collection but will instead be brought to a facility on an ‘as needs’ basis by site personnel. All excess materials, will be incorporated into the general waste stream, stored safely, and removed by appropriate permitted waste contractor to a licensed/ permitted waste facility. subcontractors will be responsible for the disposal of such material in an appropriate manner or provide alternative disposal arrangements. All subcontractors will be made aware of this requirement prior to arrival on site. It is not anticipated that any bulk wastes will be generated by third party contractors. 8.12 Responsibilities The contractor will be designated as the person with overall responsibility for the implementation of the Waste Management Plan. The Project Manager will be assigned the authority to instruct all site personnel to comply with the specific provisions of the Plan. The Site Manager and each sub-contractor on the site shall be assigned the direct responsibility to ensure that the discrete operations stated in the Waste Management Plan are performed on an on-going basis. All site personnel and sub-contractors will be instructed about the objectives of the Waste Management Plan and informed of the responsibilities which fall upon them as a consequence of its provisions. Where source segregation techniques apply, each member of staff will be given instructions on how to comply. The designated person shall arrange for full details of all arisings, movements and treatment of wastes to be recorded during the construction stage of the Project. Each consignment of C&D waste taken from the site will be subject to documentation, which will ensure full traceability of the material to its final destination. 8.13 Signage Clear signage will be provided to reduce contamination of source segregated waste streams and identify bins and corresponding materials. All waste awareness signage will be developed to reinforce the key messages of minimisation and source separation and will be prominently displayed at strategic locations around work locations. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 64 8.14 Permitted or Licensed Waste Collectors The Contractor will complete a register of all the waste collectors who have been selected to remove waste from the site and the final destination of all wastes which leave the construction site. Only facilities licenced to do so will be permitted to accept any wastes from the Development of the site. RECEIVED: 07/10/2025 Document Ref. Number: 22790-CEMP-P1 _____________________________________________________________________________________________________________ 65 9.0 Summary This CEMP presents a summary of the overall proposed Development works, the management of the site during the construction works and the mitigation measures required to ensure the proposed works do not have a significant effect on the environment. This document has been prepared in accordance with Best Practice documents as set out above and in all relevant documents submitted with this planning application. The details provided in this CEMP confirms that the Development can be carried out without impacting water quality and fisheries habitat. Key to the implementation of this CEMP is the delegation of responsibility for the CEMP to the Construction Manager, the ECoW and their Site Management Team. The measures detailed in this CEMP ensures that each member of the construction team including site management and general site operatives will be aware of their responsibilities in terms implementing good construction and environmental practices RECEIVED: 07/10/2025