Project: Tully Residential Scheme,
County Monaghan
Project No: TBC
Appendix 2- Surface and Groundwater Management Plan
Produced by: Caoimhin Robinson Date produced: 21/02/2025
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
2
Table of Contents
Amendment History
1 Introduction
2 Project Details (inc Roles & Responsibilities)
3 Training & Induction
4 Summary of Environmental Risks & Actions (Impacts & Aspects)
5 Pollution Prevention & Emergency Preparedness Response Plan
6 Surface Water Management
7 Groundwater Discharge Strategy
8 Audits, Inspections & Reporting
Appendices
1 Sample Discharge Set-Up
2 CD138 Site Discharge Record
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
3
Amendment History
This Surface and Groundwater Management Plan (SGMP) is a controlled document in accordance with
our integrated management system (IMS) consisting of ISO9001 and ISO14001. Amendments or
changes to the SGMP can only be authorised by the Environmental Manager.
Produced by: Role:
Copy Number: Date Produced: Holder:
Distribution List: No. Copies:
Date Page No New Issue No Comment Authorised by
21/02/2025 All 1 First Issue of SGMP Caoimhin Robinson
For Further Information Contact:
Caoimhin Robinson- GEDA Construction
Phil Rowland- GEDA Construction
001 Phil Rowland 21/02/2025
Monaghan County Council 1
Caoimhin Robinson Environmental Manager RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
4
1. Introduction
The Surface and Groundwater Management Plan (SGMP) outlines GEDA’s responsibility for ensuring
appropriate mitigation is implemented to maintain environmental protection of surface and
groundwater for the construction phase of the Tully Residential Scheme in County Monaghan.
The SGMP ensures environmental management is considered throughout all stages of work in
accordance with our ISO14001 Environmental Management System and documented procedures. The
SGMP includes works by GEDA and/or subcontractors working for or on behalf of the company. The
CEMP is a controlled document, therefore always ensure you are referring to the most recent version
of this document.
2. Project Description
Proposed residential scheme (Figure 1) to include 49 no. dwellings comprising; 22 no. 3 bed two-storey
semi-detached dwellings, 9 no. 4 bed two-storey semi-detached dwellings, 5 no. 2 bed single-storey
semi-detached dwellings, 1 no. 4 bed single-storey semi-detached dwellings, 11 no. 2 bed terraced
dwellings, 1 no. 2 bed two-storey semi-detached dwelling, boundary treatments, retaining walls, hard
and soft landscaping, public lighting, connection to all main public services, new entrance and access
road onto public road with all ancillary and associated site works at Tully, Monaghan Town, County
Monaghan.
Figure 1- Proposed residential scheme
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
5
2.1 Project Details
Project Name Tully Residential Scheme Location Tully, Monaghan Town,
County Monaghan
Client Monaghan County Council Contractor GEDA Construction
Date SGMP
Produced
21/02/2025 SGMP Review
Frequency
Quarterly
Project Start Date TBC Project Completion
Date
TBC
2.2 Project Roles & Responsibilities
Name Company Company Type Contact details
Who is responsible for
drafting the SGMP?
GEDA Environmental
Manager
GEDA
Construction
Principal
contractor
048 8774 7600
Who is responsible for
implementing the
SGMP?
GEDA Site Manager GEDA
Construction
Principal
contractor
048 8774 7600
Who is the person in
charge of the project?
GEDA Contracts
Manager
GEDA
Construction
Principal
contractor
048 8774 7600
3. Training & Induction
Project specific environmental management training will be delivered at the site inductions using
GEDA’s bespoke SHEQ induction video. Ongoing training in the form of environmental toolbox talks
are delivered throughout the project. Additional training is delivered (Inc externally) as required.
GEDA’s Environmental Manager: Caoimhin Robinson holds a Bachelors of Science in Environmental
Management and Masters of Science in Environmental Engineering. Their expertise will be deployed
through direct liaison with the Tully Residential project team for all training related matters.
3.1 Environmental Toolbox Talks
Environmental toolbox talks are delivered throughout the project both by GEDA Construction and
subcontractors. These environmental toolbox talks are taken from the CIRIA guidance document and
include specific topics for surface and groundwater management such as:
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
6
• Spill Control
• Water Pollution Prevention- COSHH
• Water Pollution - Silt (Figure 2)
• Water Pollution - Cement and Concrete
• Invasive Species
• Storage and Use of Petrol, Diesel and Oils
• Pumping and Over pumping
• Be A Good Neighbour
Figure 2 - Sample pollution prevention toolbox RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
7
3.2 Environmental Management System Work Instructions
GEDA Construction has an implemented ISO14001 environmental management system. In
accordance with our EMS, we have developed the following environmental work instructions. All work
instructions have been produced to assist our site -based teams when carrying out works on site. All
work instructions are externally audited annually and third party accredited by a certified body.
Compliance with company environmental work instructions is audited regularly by the Environmental
Manager. Any non-compliance is recorded and reported as a non-conformance. Suitable corrective
and / or preventative action is agreed and carried out within specific timescales. All actions are verified
by the Company director and closed out. Non-conformances are reviewed on a regular basis and used
to identify trends to drive business improvement.
Our company environmental work instructions for Surface and Groundwater Management are:
Work Instruction No. Title
Env 08 Water
Env 09 Control Of Discharge to Water
Env 10 Spill Containment & Disposal
Env 15 Storage OF COSHH & Spill Containment
Env 18 Soil Management
Our site-based teams have access to our work instructions via our SharePoint system.
4. Summary of Environmental Risks & Actions (Impacts & Aspects)
An environmental risk assessment (impacts & aspects register) has been completed for this project.
The assessment records all environmental risks and scores them using a traffic light system. Those
coloured in red are considered “Significant” with immediate action required. Those coloured yellow
are considered a medium risk while those scored green are considered low risk. The following for
discharge to water risk has been identified for the Tully Residential Scheme:
NO ENVIRONMENTAL
ASPECT
IMPACT SIGNIFICANCE ACTION/COMMENT
2 Discharge to water
Pollution to
ground and
surface waters
Medium
The site is located close to the River
Shambles, which is designated WFD
“Poor” status. Works will not directly
impact the river but good practice
measures will still be deployed.
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
8
5. Pollution Prevention & Emergency Preparedness Response Plan
Our pollution prevention and emergency preparedness response plan will be produced and implemented
at the Tully Residential project. All GEDA Construction staff have received emergency response training
in accordance with our ISO14001 environmental management system . In the event of an emergency
or potential polluting incident, the following CD132 procedure (Figure 4) must be adhered too:
Figure 3- CD132 Procedure RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
9
5.1 Reporting an Emergency Incident
Our Environmental Manager will report emergency incidents through the following procedure:
• Contact the Emergency Response Agencies and the Environmental Protection Agency to
communicate the incident details (this may include the completion and submission of an
incident notification form).
• Be available to take calls regarding the incident.
• Keep appraised of the on-going situation to determine the appropriate response level from staff.
• Provide and support the technical response to the incident.
• Ensure that suitable safety precautions are in place regarding any on-site response.
• Provide and support the monitoring and analytical response.
• Advise on notification to the public and other Agencies.
• Advise on remedial action necessary including preventative action i.e. potable water supplies.
• Ensure compliance with the incident notification conditions of the licence.
Our Environmental Manager will also notify Monaghan County Council in writing within one day of all
incidents affecting or likely to affect the operation of the W orks, immediatel y after they become aware
of the incident and/or its effect. Any contaminated material shall be removed off-site to a suitable
licensed facility using a consignment note.
5.2 Emergency Preparedness Site Plan
Contact Number
GARDAI Emergency- Monaghan Station Call 999 or 047 77200
Environmental Protection Agency (EPA) 053 916 0600
24 Hour Spill Response Team- SEED 0844 381 5650
Waste Contractor- ENVA Carrickmacross 042 967 3587
GEDA Construction Head Office 048 8774 7600
Environmental Manager- Caoimhin Robinson 048 8774 7600
Build Ireland Associate Director- Eddie Murnin 048 8774 7600
6. Surface Water Management
During the construction phase of the Tully Residential Scheme, GEDA Construction shall take all
necessary precautions to prevent the pollution of River Shambles (Figure 5) and Ulster Canal, which is
circa 300m away. GEDA Construction have developed a Surface and Groundwater Management plan
for the construction phase of the Tully Residential Scheme to outline the methodology for controlling
groundwater from site development works into nearby surface water sources ; shown in Section 7
below. This plan will be subject to approval from Monaghan County Council and Island Fisheries. The
construction works will be performed in compliance with the “Guidelines on Protection of Fisheries
During Construction Works in and Adjacent to Waters”.
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
10
Figure 4- River Shambles proximity to proposed scheme (red box)
GEDA Construction shall therefore implement mitigation measures to ensure strict environmental
protection can be maintained in the Tully area. These measures are outlined further in section 6.1 to
6.4 below:
6.1 Excavations to be kept free from groundwater
Groundwater in the excavations shall be dealt with in such manner as will prevent the surfaces on or
against which foundations or other work will be constructed from any deterioration of their natural
condition, or from such condition as improved by work executed under the Contract. GEDA
Construction shall take all necessary precautions to ensure any dewatering of excavations in
accordance with the groundwater discharge strategy in Section 7 below.
6.2 Watercourses
Tully Residential Scheme is located close to both the River Shambles and Ulster Canal and as such,
appropriate silt fencing (Figure 6) will be installed along low points at the site boundary to reduce
surface water runoff risks. In addition, our Emergency Preparedness & Response procedure will be
implemented in the event of a pollution and / or potential polluting incident.
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
11
Figure 5- example silt fence for surface water runoff protection
6.3 Pollution Control Management
All GEDA Construction sites have spill kits located in designated areas. Spill drill training has been
delivered to appropriate members of staff whose names are communicated to all working on site.
Fuels / chemicals will be stored in a designated COSHH storage area on hard standing areas away from
water courses and drainage to eliminate / reduce impact of potential pollution incidents. All bulk fuels
are stored in integrally bunded tanks (capacity 110% volume of contents) with drip trays located close
by. Designated concrete washout areas will be installed within work zones e.g. sealed containers.
Concrete delivery drivers will be encouraged to washout into sealed containers. When the sealed
container is approaching capacity, concrete mixture will be placed inside and allowed to harden. Once
ready, the washout material can then be broken out and reused as general fill or taken off site to a
licensed waste management facility in accordance with the Waste Duty of Care. All spills are
reportable to the Site and Environmental Manager. Emergency contact numbers are included within
section 5.2 of this document.
6.4 Compliments and Complaints Procedure
On the site hoarding, GEDA will display a QR code for compliments and complaints from members of
the public. This procedure allows GEDA to receive compliments and complaints in a timely manner
and respond accordingly. There is also a comments box at the site entrance for members of the public
to submit handwritten feedback to the site team throughout the project. Compliments and Complaints
are then taken and logged onto a software system so that reoccurring trends between GEDA projects
can be reviewed.
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
12
7. Groundwater Discharge Strategy
As part of site development, general groundworks and excavation works will be carried out by GEDA’s
designated groundworks subcontractor. Specific works such as attenuation tank installation may
generate groundwater at larger excavation depths. In ensuring the structural integrity and safety of
excavations, GEDA would like to discharge groundwater through a settlement tank treatment system
before discharge into nearby suitable networks such as storm drains leading to watercourses
downstream. Before work commences, GEDA’s Environmental Manager and Project team will
complete a site investigation to investigate potential discharge options on the existing network. Once
a suitable discharge location is found, this will be documented in Figure 5 below before requesting
approval through Monaghan County Council and Inland Fisheries.
7.1 Discharge Methodology
Groundwater Discharge will be conducted following the below steps:
1. Site team to identify groundwater sources during site development works.
2. Suitable pump (2/3/4/6inch) selected for groundwater discharge dependent on quantity and
speed of groundwater recharge within excavation.
3. Settlement Lamella Tank hired from supplier for groundwater treatment
(See Appendix 1 for sample discharge set-up from supplier “Aska Sykes” that has been used on
other GEDA projects).
4. Suitable pump connects hosing from the groundworks excavation into Settlement Lamella tank
located beside the discharge point.
5. GEDA Site team to monitor water quality at the end of the Settlement Lamella Tank before
allowing groundwater to pass into the approved discharge point.
6. Site team will check the upstream and downstream monitoring points to ensure there is no
visual difference between locations.
7. If there is any difference in upstream and downstream water quality during discharging, GEDA’s
Site team will stop pumping immediately and inform GEDA’s Environmental Manager and the
project client.
8. GEDA Site Team and Environmental Manager will then investigate the groundwater discharge
set-up and ensure corrective actions are installed before allowing pumping to recommence.
9. GEDA Site team will maintain a discharge record (Appendix 2) during all pumping operations,
that will include evidence of daily visual inspections of the watercourse quality.
10. If discharge from the Tully Residential Scheme is ceased for any speciflc reason, a suitably sized
pump will transfer groundwater from excavation works to a contained and fiat location on site,
that will have been pre-agreed and chosen by GEDA’s Environmental Manager and Project team.
This location will be chosen in consideration for avoiding existing drains and sewers on site. RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
13
Figure 5- service drawing for proposed scheme including storm network and attenuation tanks (blue boxes)RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
14
8. Audits, Inspections & Reporting
GEDA Construction will produce and issue a monthly environmental report which will include the
following information:
1. Details of Inspections/Audits
a) Audits and inspections carried out
b) Audits/ Inspections Findings/Reports
c) Actions Arising/Corrective actions put in place
2. Environmental Incidents and Information
a) Environmental Incidents.
b) Environmental near miss incidents.
c) Environmental Complaints
3. Waste records
a) Quantities and types of materials used.
b) Tonnage of various waste streams generated and treatment/disposal routes
implemented for all wastes generated
GEDA Construction will operate a project environmental tracker on SustainIQ Software, which is used
to monitor, measure and report on environmental performance.
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
15
Appendix 1- Sample Discharge Set-Up
RECEIVED: 29/10/2025
APPENDIX 2- SURFACE AND GROUNDWATER MANAGEMENT PLAN
16
Appendix 2- CD138 Site Discharge Record
CD138 Site Discharge Record
Site Reference and Name:
Date of discharge:
Time of discharge:
Monitored by:
Discharge Location:
Comments:
Photos: