Construction Environmental Management Plan
Produced by: Caoimhin Robinson Date produced: 21/02/2025
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
2
Table of Contents
Amendment History
1 Introduction
2 Project Details (inc Roles & Responsibilities)
3 Training & Induction
4 Environmental Management System Procedures
5 Summary of Environmental Risks & Action Plans
6 Pollution Prevention & Emergency Preparedness & Response Plan
7 Surface Water Management
8 Contaminated Land
9 Energy Management
10 Waste Management
11 Construction Nuisance
12 Resources
13 Landscape Works
14 Biodiversity & Ecology (inc Protected & Invasive Species)
15 Archaeology
16 Soils, Geology and Hydrogeology
17 Stakeholder Liaison, Public Stakeholders & Indirect Impacts
18 Supply Chain
19 Legislation & Other Requirements
20 Audits, Inspection & Reporting
21 Traffic Management
Appendices
1 Resource Waste Management Plan
2 Surface and Groundwater Management Plan.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
3
Amendment History
This Construction Environmental Management Plan (CEMP) is a controlled document in accordance
with our integrated management system (IMS) consisting of ISO9001 and ISO14001. Amendments or
changes to the CEMP can only be authorised by the Environmental Manager.
Produced by: Role:
Copy Number: Date Produced: Holder:
Distribution List: No. Copies:
Date Page No New Issue No Comment Authorised by
21/02/2025 All 1 First Issue of CEMP Caoimhin Robinson
For Further Information Contact:
Caoimhin Robinson- GEDA Construction
Phil Rowland- GEDA Construction
001 Phil Rowland 21/02/2025
Monaghan County Council 1
Caoimhin Robinson Environmental Manager RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
4
1. Introduction
The Construction Environmental Management Plan (CEMP) outlines GEDA’s responsibility for ensuring
appropriate mitigation is implemented to maintain environmental protection for the construction
phase of the Tully Residential Scheme in County Monaghan.
The CEMP ensures environmental management is considered throughout all stages of work in
accordance with our ISO14001 Environmental Management System and documented procedures. The
CEMP includes works by GEDA and/or subcontractors working for or on behalf of the company. The
CEMP is a controlled document, therefore always ensure you are referring to the most recent version
of this document.
2. Project Description
Proposed residential scheme (Figure 1) to include 49 no. dwellings comprising; 22 no. 3 bed two-storey
semi-detached dwellings, 9 no. 4 bed two-storey semi-detached dwellings, 5 no. 2 bed single-storey
semi-detached dwellings, 1 no. 4 bed single-storey semi-detached dwellings, 11 no. 2 bed terraced
dwellings, 1 no. 2 bed two-storey semi-detached dwelling, boundary treatments, retaining walls, hard
and soft landscaping, public lighting, connection to all main public services, new entrance and access
road onto public road with all ancillary and associated site works at Tully, Monaghan Town, County
Monaghan.
Figure 1- Proposed residential scheme
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
5
2.1 Project Details
Project Name Tully Residential Scheme Location Tully, Monaghan Town,
County Monaghan
Client Monaghan County Council Contractor GEDA Construction
Date CEMP
Produced
21/02/2025 CEMP Review
Frequency
Quarterly
Project Start Date TBC Project Completion
Date
TBC
2.2 Project Roles & Responsibilities
Name Company Company Type Contact details
Who is responsible for
drafting the CEMP?
GEDA Environmental
Manager
GEDA
Construction
Principal
contractor
048 8774 7600
Who is responsible for
implementing the
CEMP?
GEDA Site Manager GEDA
Construction
Principal
contractor
048 8774 7600
Who is the person in
charge of the project?
GEDA Contracts
Manager
GEDA
Construction
Principal
contractor
048 8774 7600
3. Training & Induction
Project specific environmental management training will be delivered at the site inductions using
GEDA’s bespoke SHEQ induction video. Ongoing training in the form of environmental toolbox talks
are delivered throughout the project. Additional training is delivered (Inc externally) as required.
GEDA’s Environmental Manager: Caoimhin Robinson holds a Bachelor’s of Science in Environmental
Management and Masters of Science in Environmental Engineering. Their expertise will be deployed
through direct liaison with the Tully Residential project team for all training related matters.
3.1 Environmental Toolbox Talks
Environmental toolbox talks are delivered throughout the project both by GEDA Construction and
subcontractors. These environmental toolbox talks are taken from the CIRIA guidance document and
include topics such as:
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
6
• Carbon Reduction (Figure 2)
• Spill Control
• Water Pollution Prevention (Fuel & Oil)
• Dust and Air Quality
• Noise and Vibration
• Water Pollution - Silt
• Water Pollution - Cement and Concrete
• Tree Protection
• Waste Management – Reduce/Reuse/Recycle (Figure 3)
• Storage and Segregation of Waste
• Invasive Species
• Storage and Use of Petrol, Diesel and Oils
• Material Handling and Housekeeping
• Archaeology
• Pumping and Over pumping
• Ecology
• Be A Good Neighbour
• Working on Previous Developed Land
Figures 2 and 3- Sample toolbox talks
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
7
4. Environmental Management System Work Instructions
GEDA Construction has an implemented ISO14001 environmental management system. In
accordance with our EMS, we have developed the following environmental work instructions. All work
instructions have been produced to assist our site -based teams when carrying out works on site. All
work instructions are externally audited annually and third party accredited by a certified body.
Compliance with company environmental work instructions is audited regularly by the Environmental
Manager. Any non-compliance is recorded and reported as a non-conformance. Suitable corrective
and / or preventative action is agreed and carried out within specific timescales. All actions are verified
by the Company director and closed out. Non-conformances are reviewed on a regular basis and used
to identify trends to drive business improvement.
Our company environmental work instructions are:
Work Instruction No. Title
Env 01 Managing Wildlife & Protected Species
Env 02 Trees & Hedgerows
Env 03 Invasive Plants & Designated Wildlife Species
Env 04 Air Pollution
Env 05 Dust, Noise & Nuisances
Env 06 Transport
Env 07 Noise & Vibration
Env 08 Water
Env 09 Control Of Discharge to Water
Env 10 Spill Containment & Disposal
Env 11 Contamination
Env 12 Waste & Special Wastes
Env 13 Carbon Footprint Management
Env 14 Archaeology
Env 15 Storage OF COSHH & Spill Containment
Env 16 Waste Duty of Care Process Flowchart
Env 17 Swift Boxes
Env 18 Soil Management
Our site-based teams have access to our work instructions via our SharePoint system.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
8
5. Summary of Environmental Risks & Actions (Impacts & Aspects)
An environmental risk assessment (impacts & aspects register) has been completed for this project.
The assessment records all environmental risks and scores them using a traffic light system. Those
coloured in red are considered “Significant” with immediate action required. Those coloured yellow
are considered a medium risk while those scored green are considered low risk.
The following categories are considered when completing the risk register:
• Emissions to Air
• Discharges to Water
• Waste Management (inc hazardous waste)
• Contaminated Land
• Noise Dust Vibrations Disruption
• Buried Utility Services
• Use of Natural Resources
• Eco Systems / Biodiversity / Ecology
• Indirect Effects
Each risk is then scored high, medium or low based upon the following factors:
• Normal / Abnormal / Emergency Occurrence
• Legislative Requirements
• Control or Influence
• Severity
• Scale
• Probability
• Duration
• Compliance
All significant risks are immediately addressed through agreed actions, who / person(s) responsible for
completing action, and a timescale for when it must be completed. All risks and management
programmes are regularly reviewed. The following environmental risks have been identified for the
Tully Residential Scheme:
NO ENVIRONMENTAL
ASPECT
IMPACT SIGNIFICANCE ACTION/COMMENT
1 Emissions to Air
Increased carbon
footprint during
construction
Low
Groundworks is required throughout
site development works. All plant will
be modern with high energy efficiency
and subcontractors will be audited on
idling plant compliance.
2 Discharge to water
Pollution to
ground and
surface waters
Medium
The site is located close to the River
Shambles, which is designated WFD
“Poor” status. Works will not directly
impact the river but good practice
measures will still be deployed. RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
9
3 Waste
Management
Waste Pollution
including
hazardous wastes
Low
Resource waste management plan will
be implemented. Site team will
consider direct re-use on site and
Article-27 By Product Notification to
encourage material re-use off-site.
4 Contaminated
Land
Waste Pollution
including illegal
disposal
Medium
Further chemical testing is required to
confirm contaminated land. As it is a
greenfield site, it is likely that soil will be
uncontaminated and can be
considered for reuse on/off site.
5 Noise, Dust &
Vibration
Noise, dust &
vibration leading
to potential
pollution to local
residents /
businesses
Medium
The proposed scheme is adjacent to
existing residential properties within
the Tully and Manor Wood estates. Site
Hoarding will be installed to limit
nuisance off-site and dust suppression
will be applied when required.
6 Buried Utility
Services
Potential for
damage to existing
buried services
from excavation
works
Low
All utility drawings will be sourced from
providers prior to works. The scheme is
taking place within a greenfield site, so
existing buried services will be limited
to the main road only.
7 Use of Natural
Resources
Potential
exploitation of
natural resources
Low
Temporary Electricity supply will be
preferred for the project compound.
Use of petrol and diesel will be limited
to groundworks only and will be stored
away from all sensitive receptors.
Resources such as timber will be
sourced from schemes such as FSC.
8 Biodiversity/
Ecology
Potential
disturbance to
local ecosystems
Low
Tully Residential Scheme is located
circa 13km from “Slieve Beagh SPA”
and 18km from “Kilroosky Lough SAC”.
A proposed NHA “Wrights Wood” is
also located circa 1.5km away. Due to
the distance between the Tully scheme
and designated sites, the impact to
Biodiveristy is expected to be low.
9 Indirect Effects
Potential
disturbance
caused by works
e.g. traffic
Low
Traffic Management Plan will be
created within the construction phase
plan to ensure traffic is managed
adequately on the scheme.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
10
6. Pollution Prevention & Emergency Preparedness Response Plan
Our pollution prevention and emergency preparedness response plan will be produced and implemented
at the Tully Residential project. All GEDA Construction staff have received emergency response training
in accordance with our ISO14001 environmental management system . In the event of an emergency
or potential polluting incident, the following CD132 procedure (Figure 4) must be adhered too:
Figure 4- CD132 Procedure
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
11
6.1 Reporting an Emergency Incident
Our Environmental Manager will report emergency incidents through the following procedure:
• Contact the Emergency Response Agencies and the Environmental Protection Agency to
communicate the incident details (this may include the completion and submission of an
incident notification form).
• Be available to take calls regarding the incident.
• Keep appraised of the on-going situation to determine the appropriate response level from staff.
• Provide and support the technical response to the incident.
• Ensure that suitable safety precautions are in place regarding any on-site response.
• Provide and support the monitoring and analytical response.
• Advise on notification to the public and other Agencies.
• Advise on remedial action necessary including preventative action i.e. potable water supplies.
• Ensure compliance with the incident notification conditions of the licence.
Our Environmental Manager will also notify Monaghan County Council in writing within one day of all
incidents affecting or likely to affect the operation of the W orks, immediatel y after they become aware
of the incident and/or its effect. Any contaminated material shall be removed off-site to a suitable
licensed facility using a consignment note.
6.2 Emergency Preparedness Site Plan
Contact Number
GARDAI Emergency- Monaghan Station Call 999 or 047 77200
Environmental Protection Agency (EPA) 053 916 0600
24 Hour Spill Response Team- SEED 0844 381 5650
Waste Contractor- ENVA Carrickmacross 042 967 3587
GEDA Construction Head Office 048 8774 7600
Environmental Manager- Caoimhin Robinson 048 8774 7600
Build Ireland Associate Director- Eddie Murnin 048 8774 7600
7. Surface Water Management
During the construction phase of the Tully Residential Scheme, GEDA Construction shall take all
necessary precautions to prevent the pollution of River Shambles (Figure 5) and Ulster Canal, which is
circa 300m away. GEDA Construction have developed a Surface and Groundwater Management plan
for the construction phase of the Tully Residential Scheme, which is shown in Appendix 2. This plan will
outline the methodology for controlling groundwater from site development works into nearby surface
water sources. This plan will be subject to approval from Monaghan County Council and Island
Fisheries. The construction works will be performed in compliance with the “Guidelines on Protection
of Fisheries During Construction Works in and Adjacent to Waters”.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
12
Figure 5- River Shambles proximity to proposed scheme (red box)
GEDA Construction shall therefore implement mitigation measures to ensure strict environmental
protection can be maintained in the Tully area. These measures are outlined further in sections 7.1 to
7.3 below:
7.1 Excavations to be kept free from groundwater
Groundwater in the excavations shall be dealt with in such manner as will prevent the surfaces on or
against which foundations or other work will be constructed from any deterioration of their natural
condition, or from such condition as improved by work executed und er the Contract. GEDA
Construction shall take all necessary precautions to ensure any dewatering of excavations in
accordance with the approved surface and groundwater management plan.
7.2 Watercourses
Tully Residential Scheme is located close to both the River Shambles and Ulster Canal and as such,
appropriate silt fencing (Figure 6) will be installed along low points at the site boundary to reduce
surface water runoff risks. In addition, our Emergency Preparedness & Response procedure will be
implemented in the event of a pollution and / or potential polluting incident.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
13
Figure 6- example silt fence for surface water runoff protection
7.3 Pollution Control Management
All GEDA Construction sites have spill kits located in designated areas. Spill drill training has been
delivered to appropriate members of staff whose names are communicated to all working on site.
Fuels / chemicals will be stored in a designated COSHH storage area on hard standing areas away from
water courses and drainage to eliminate / reduce impact of potential pollution incident. All bulk fuels
are stored in integrally bunded tanks (capacity 110% volume of contents) with drip trays located close
by. Designated concrete washout areas will be installed within work zones e.g. sealed container.
Concrete delivery drivers will be encouraged to washout into sealed containers. When the sealed
container is approaching capacity, concrete mixture will be placed inside and allowed to harden. Once
ready, the washout material can then be broken out and reused as general fill or taken off site to a
licensed waste management facility in accordance with the Waste Duty of Care. All spills are
reportable to the Site and Environmental Manager. Emergency contact numbers are included within
section 6.2 of this document.
8. Contaminated Land
HANMAR Site Investigation Services conducted a ground investigation report entitled “23-102 Report
Proposed Development at Tully Co Monaghan”, in November 2023 to explore current ground
conditions on the proposed scheme. The report does not complete a chemical suite of testing to
confirm reuse suitability under the soil generic assessment criteria for residential plant uptake. The
chemical suite of testing would therefore also confirm contaminated land requirements through WM3
Waste Classification criteria as non-hazardous or hazardous waste. This testing will be required prior
to the start of the proposed scheme.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
14
9. Energy Management
9.1 Construction Stage
Carbon emissions associated with this project will be monitored and recorded. The following will be
recorded and reported on a monthly basis:
• White Diesel
• Business Travel (inc site personnel and sub-contractors)
• Temporary Electricity Supply
• Deliveries to site
• Water
• Waste
The above will be recorded and sent to the Environmental Manager on a monthly basis so that the
project environmental tracker can be updated on SustainIQ software. The emissions to air associated
with this project are not considered as significant but GEDA will continue to monitor and report them.
10. Waste Management
10.1 Construction Stage
GEDA Construction will audit licensed waste management contractors to ensure we comply with
applicable legislation and receive regular up to date and accurate waste management reports. This
ensures compliance with the W aste Management (Collection Permit) (Amendment) Regulations 2016
and Waste Management (Facility Permit and Registration) (Amendment) Regulations 2019.
Each approved waste contractor must provide copies of their waste collection and facility permits
before waste transfer. GEDA Project teams complete waste spot checks on approved waste
contractors and detail evidence with CD134 “Waste Spot Check” documents. GEDA Construction
have appointed TBC as the waste management contractor for the Tully Project:
Waste Collection Permit- TBC
Valid From:
Valid to:
Permit Number:
Waste Facility Permit – TBC
Date of issue:
Date of Expiry:
Location:
Permit Number:
GEDA Construction have produced a Resource Waste Management Plan to be submitted for
approval prior to commencement of works. Refer to Appendix 1.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
15
10.2 Demolition and Site Preparation
There are no demolition requirements on the proposed scheme, as the site is greenfield in nature. The
topographical survey entitled “T01396-04-19”, conducted on 16/04/19 by Benchmarking Surveying,
indicates the site slopes from the northwest to the southeast, at an elevation of between 87.00 & 66.00
metres AOD. A significant cut and fill exercise will need to be conducted during site preparations to
allow the project team to achieve suitable levels for development. This should mean that surplus
material will be restricted due to reuse requirements.
10.3 Disposal of Surplus Material
GEDA Construction will submit a Resource Waste Management Plan for approval by Monaghan County
Council. Material may be removed off -site, as a by-product in accordance with Article 27 of the
European Communities (Waste Directive) Regulations 2011, which requires that certain conditions
are met and that by-product notifications are made to the EPA via their online notification form.
Excavate d material will not be removed from site until approval from the EPA has been received. The
potential to reuse material as a by-product will be confirmed during the course of the excavation
works, with the objective of eliminating any unnecessary disposal of material. If the material is
deemed to be a waste, then removal and reuse / recovery / disposal of the material will be carried
out in accordance with the Waste Management legislation.
11. Construction Nuisance
11.1 Noise Management
Noise exposure aspects within the scheme will be managed in accordance with the requirements of
Safety, Health and Welfare at Work (General Application) Regulations as amended by the Safety,
Health and Welfare at Work (General Application) (Amendment) Regulations 2016 and associated
guidance from the Health and Safety Authority.
Noise levels during construction shall comply with the NRA construction noise criterion : Maximum
Permissible Construction Noise Levels at the Facade of Dwellings during Construction (NRA, 2004):
• 70dB(A) LAeq 1hr and 80dB(A) LAmax between 08:00 and 18:00 Monday to Friday
• 65dB(A) LAeq 1hr and 75dB(A) LAmax between 09:00 and 13:00 Saturday
In accordance with best practice, noise during construction of the Tully Residential Scheme will be
managed in accordance with the recommendations in BS 5228. General guidelines for limiting the
disturbance from these works are outlined below:
• Limit noisy construction works to 08.00 to 18.00 weekdays with Saturday working from 09.00 -
13.00 hours (relatively quiet construction activities could be carried out outside these hours,
subject to prior agreement and strict controls).
• Use modem, silenced and well-maintained equipment conforming to applicable EU Directives.
• Shut down equipment when not in use, where practicable.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
16
• Site semi-static equipment such as generators, mixers, and compressors as far away as
possible from sensitive locations and ensure that the orientation is the optimum for low noise.
• Ensure that all Workers are given training with respect to minimizing noise and disturbance.
Noise Acoustic Barriers will be installed as necessary on-site boundary equipment such as Heras
panels so that they can be transported between work zones. A temporary timber hoarding may also be
installed around long-term work locations such as site compounds, particularly where noise levels are
anticipated to exceed 70dB(A) during 08:00 to 18:00 Monday to Friday.
11.2 Vibration Management
Vibration exposure is expected to be negligible on the proposed but nonetheless, GEDA Construction
shall comply with NRA construction vibration criterion for protection of buildings : Maximum
Permissible Construction Noise Levels at the Facade of Dwellings during Construction (NRA, 2004):
• 8 mm/s (vibration frequency <10Hz)
• 12.5mm/s (vibration frequency 10 to 50Hz)
• 20 mm/s (vibration frequency >50 Hz)
• 2.5mm/s (tolerable level)
11.3 Dust Management
Dust may be emitted from a number of site activities on the Tully Residential Scheme project including
plant and vehicle movements between work locations, cutting of materials such as pipework, and
stockpiling of excavated spoil. Where possible, GEDA Construction will reduce dust emissions at
source by:
• using appropriate tools for cutting with built in dust suppression,
• limiting stockpiling and selecting appropriate locations when stockpiling is required,
• using localised dust suppression to dampen down dusty atmospheres such as traffic routes
with water as appropriate. Special attention will be given when using water for dust suppression,
due to the increased risk of surface water runoff.
12. Resources
GEDA Construction have developed and implemented a Sustainability Procurement Policy to increase
the level of responsible and sustainably sourced materials being purchased by the Company. This
includes reused and recycled materials. We actively encourage local companies within the Monaghan
Town area to compete for work. The Company is currently implementing procedures to ensure we can
provide Monaghan County Council with “Chain of Custody” documentation for sustainability
schemes such as FSC for Timber. We work closely with our Buyers, Quantity Surveyors and Site Teams
to reduce the amount of over ordering within the Company. We ensure suitable storage provisions for
all materials to reduce damage caused through weather or misuse. The Site Plan will highlight the
location for material storage on site.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
17
13. Landscaping Works
McElwaine Landscape Architects have produced a landscape management plan (Figure 7) entitled
“2412-MLA-XX-XX-RP-L-9020-P01” on behalf of GEDA Construction, to include planting schedules and
landscape specifications. Open amenity space areas will be provided to the centre of the site and along
the southern boundary, consisting of extensive species-rich grass areas, close-mown grass areas for
general amenity. The central open space will also be home to a formal play are a, designed by others /
play specialist. Upon chemical testing and subject to approval through the soil generic assessment
criteria for residential plant uptake, soil will be reused within these open spaces and residential
gardens to further minimise off-site waste. If this material is unsuitable for reuse, then clean imported
topsoil will be imported into the project subject to testing clearance.
Figure 7- Proposed Landscape Plan
14. Biodiversity & Ecology
The proposed Tully Residential scheme is situated in the townland of Tully, approximately 0.5
kilometers southeast of Monaghan town centre, covers an area of circa. 2.1 hectares and is currently
utilized for grazing sheep / cattle. It is encircled by native species hedges on its northern, eastern and
western sides, while the southern boundary is marked by timber fences and walls. Several housing
estates bound the site. Manor Wood to the north, Glenview Drive to the east and Tully Estate to the
south. Beyond the western boundary is grazing lands. The current site is considered to be of low
ecological value but mitigation measures will still be installed by the project team as detailed in
sections 14.1 to 14.3 below.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
18
14.1 Natura 2000 Designated Sites
Tully Residential Scheme is located circa 13km from “Slieve Beagh SPA” (Figure 8) designated under
the EU Birds Directive and 18km from “Kilroosky Lough SAC” (Figure 9), designated under the EU
Habitats Directive. Due to the distance between the Tully scheme and designated sites, it is anticipated
that the impact to Natura 2000 will be extremely low.
Figure 8- Slieve Beagh SPA proximity to proposed scheme (red box)
Figure 9- Kilroosky Lough Cluster SAC proximity to proposed scheme (red box) RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
19
14.2 Local Areas of Ecological Importance
A proposed Natural Heritage Area “Wrights Wood” is located circa 1.5km away from the proposed
scheme. Other local areas of ecological importance include Convent Lake (circa 350m), Mullaghmatt
Forest (circa 600m) and Rossmore Forest (circa 800m), all of which should not be significantly
impacted by the proposed residential works due to the mitigation measure outlined within this CEMP.
Figure 10- Wrights Wood proposed NHA proximity to proposed scheme (red box)
14.3 Protection of Trees
The Wildlife Amendment Act 2000 (S.46.1) stipulates that it is an offence to cut, grub, burn or destroy
any vegetation on uncultivated land or such growing in any hedge or ditch from the first of March to the
31st of August. Within the project landscape plan “2412-MLA-XX-XX-RP-L-9020-P01”, tree removal is
expected along the main access road into the proposed site only (Figure 11).
Figure 11- Proposed Tree removal for the scheme (red circles) RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
20
All other trees/hedgerows are to be retained and protected in accordance with BS 5837:2012, Trees in
relation to design, demolition & construction. GEDA Construction will ensure that required tree
removal will be carried outside of the breeding season. In particular, removal during the peak-breeding
season (April-June inclusive) will be avoided on the Tully Residential Scheme.
15. Soils, Geology and Hydrogeology
HANMAR Site Investigation Services conducted a ground investigation report entitled “23-102 Report
Proposed Development at Tully Co Monaghan”, in November 2023 to explore current ground
conditions on the proposed scheme. The initial scope of the investigation (Figure 12) included:
• 4 No. rotary percussion boreholes with continuous sampling and SPTs in order to establish the
rock, soil and groundwater conditions beneath the site.
• 21 No. Dynamic Probes in order to establish geotechnical properties of the subsoils.
• 4 No. Trial Pits in order to establish the soil and groundwater conditions beneath the site.
• 1 No. infiltration tests in order to establish geotechnical properties of the subsoils.
Figure 12 – Ground Investigation Map for proposed scheme
15.1 Investigation Results
• Topsoil cover between 0-0.6m within borehole logs.
• No Made Ground was encountered within the boreholes BH 01 – 03 during excavations.
• Glacial deposits were established within all boreholes, consisting of firm to stiff light brown
slightly gravelly slightly sandy silty CLAY containing occasional smooth subrounded cobbles
between 0.6m and 2.6m.
• Slight flow of ground water was encountered within borehole BH 03 at 3.50m below existing
ground level during excavation.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
21
16. Archaeology & Cultural Heritage
GEDA Construction will consult with relevant parties for completion of an Archaeology Assessment
prior to the construction phase of the Tully Residential scheme. If required, appropriate mitigation will
be deployed to ensure archeological heritage is maintained in the Tully area.
17. Public Stakeholder Liaison
GEDA Construction will engage and liaise with all project stakeholders involved/affiliated with the Tully
project. We will issue monthly environmental update reports and liaise regularly with the following non-
exhaustive list of bodies / organisations during the course of Contract;
• The Employer,
• The Employer’s Representative(s),
• Operational and maintenance staff,
• Local Monaghan County Council departments,
• Any relevant Government Departments including the Environmental Protection Agency
• Inland Fisheries Ireland,
• Adjacent landowners / residents.
GEDA Construction’s designated Corporate Social Responsibility (CSR) Coordinator will engage with
all outlined above. Our Coordinator will be responsible for coordinating all communications including
information events, and all letter / mail drops (local residents).
17.1 Compliments and Complaints Procedure
On the site hoarding, GEDA will display a QR code for compliments and complaints from members of
the public. This procedure allows GEDA to receive compliments and complaints in a timely manner
and respond accordingly. There is also a comments box at the site entrance for members of the public
to submit handwritten feedback to the site team throughout the project. Compliments and Complaints
are then taken and logged onto a software system so that reoccurring trends between GEDA projects
can be reviewed.
18. Supply Chain
GEDA Construction will operate a Supply Chain Charter for all approved suppliers and sub-contractors
appointed to this project. A pre-qualification questionnaire will be completed by GEDA’s supply chain
to ensure they can demonstrate adequate competency towards environmental standards.
Once appointed, this CEMP will be communicated to all personnel on site via induction, toolbox talks
and method statements for specific work packages. A Meet the Buyer event to inform local supply
chain members of the opportunities associated with the Tully Residential Scheme will be arranged.
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
22
19. Legislation & Other Requirements
In accordance with our ISO14001 Environmental Management System, we have produced a Register
of Environmental Legislation for the Republic of Ireland. Our Legal Register is available to all site teams,
supply chain and further guidance is provided by GEDA’s Environmental Manager as required. Our
Registers are updated regularly to ensure ongoing compliance with all applicable legis lation. GEDA
will liaise with all applicable bodies (i.e., Monaghan County Council, Environmental Protection Agency
etc.) to ensure compliance with legislation.
20. Audits, Inspections & Reporting
GEDA Construction will produce and issue a monthly environmental report which will include the
following information:
1. Details of Inspections/Audits
a) Audits and inspections carried out
b) Audits/ Inspections Findings/Reports
c) Actions Arising/Corrective actions put in place
2. Environmental Incidents and Information
a) Environmental Incidents.
b) Environmental near miss incidents.
c) Environmental Complaints
3. Waste records
a) Quantities and types of materials used.
b) Tonnage of various waste streams generated and treatment/disposal routes
implemented for all wastes generated
GEDA Construction will operate a project environmental tracker on SustainIQ Software, which is used
to monitor, measure and report on environmental performance.
21. Traffic Management
GEDA Construction will ensure that all vehicle movements for construction of the works shall be
controlled for the purposes of safe access and egress to the site, as presented in the Preliminary
Construction Traffic Management Plan submitted as part of the planning application. Plant and
machinery will not be permitted to use routes other than those agreed in principle with Monaghan
County Council Traffic Section.
GEDA Construction’s Traffic Management Plan shall consider the following:
• Construction traffic management procedures agreed with Monaghan County Council;
• Description of the access route(s) for construction traffic;
• Efficient site control systems to ensure that traffic backlogs don’t develop at access points;
• Appointment of a Liaison Officer who shall organise and attend meetings as deemed required
by GEDA Construction, the client, the client’s representative and members of the public .
RECEIVED: 29/10/2025
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
23
Appendix 1
Resource Waste Management Plan
Appendix 2
Surface and Groundwater Management Plan.
RECEIVED: 29/10/2025