CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
FOR THE
PROPOSED DEVELOPMENT
AT
TULLYNAHINNERA, CASTLEBLANEY,
CO. MONAGHAN
FOR
RONAN BOYD.
October 2025
Issued by:
Name: Dylan Cox
Position: Environmental Consultant
ESC Environmental Ltd.
T: 085 250 0223
E: DylanESCenvironmental@outlook.com
RECEIVED: 21/11/2025
2
User is responsible for checking the revision status of this document
Rev. Description of
Changes
Prepared by: Checked by: Approved by: Date:
1 Issued for
Review
Dylan Cox Peter
McCormick
Peter
McCormick
31/10/2025
RECEIVED: 21/11/2025
3
Table of Contents
1. Introduction: ................................................................................................................................... 5
2. Site Location ................................................................................................................................... 6
3. Scope and Purpose ........................................................................................................................ 7
4. Project Organisation and Responsibilities ..................................................................................... 8
4.1 Project Communication and Coordination .............................................................................. 9
4.2 Operational Control .............................................................................................................. 9
4.3 Checking and Corrective Action........................................................................................... 9
4.4 Environmental Incident Procedure ..................................................................................... 10
4.5 Anticipated Plant and Equipment ...................................................................................... 10
5. Potential Environmental Impacts ................................................................................................. 11
6. Construction Environmental Management Plan ......................................................................... 12
6.1 Good Housekeeping ............................................................................................................... 12
6.1.1 Resourcing and Training Development ......................................................................... 12
6.1.2 Site Security ..................................................................................................................... 12
6.1.3 General Good Housekeeping Measures ....................................................................... 13
6.1.4 Monitoring ...................................................................................................................... 13
6.2 Air Quality and Dust Management .................................................................................... 13
6.2.1 Plant and Machinery ....................................................................................................... 13
6.2.2 Earthworks....................................................................................................................... 14
6.2.3 Materials Handling and Storage .................................................................................... 14
6.2.4 Monitoring ...................................................................................................................... 14
6.3 Noise and Vibration ............................................................................................................ 14
6.3.1 General Measures ........................................................................................................... 14
6.3.2 Working Hours ................................................................................................................ 15
6.3.3 Monitoring ...................................................................................................................... 15
6.4 Soils ...................................................................................................................................... 15
6.4.1 General ............................................................................................................................ 15
6.4.2 Monitoring ...................................................................................................................... 15
6.5 Waste ................................................................................................................................... 15
6.5.1 Minimising Waste ........................................................................................................... 16
6.5.2 Concrete Waste .............................................................................................................. 16 RECEIVED: 21/11/2025
4
6.5.3 Hazardous Waste ........................................................................................................... 16
6.5.4 Storage of Soil, Materials, and Waste ............................................................................ 16
6.5.5 Monitoring ...................................................................................................................... 17
6.6 Drainage .............................................................................................................................. 17
6.6.1 Consents ......................................................................................................................... 17
6.6.2 Site Drainage .................................................................................................................. 17
6.6.3 Pollution Controls ........................................................................................................... 17
6.6.4 Managing Run Off and Silty Water ................................................................................ 18
6.6.5 Monitoring ...................................................................................................................... 18
6.7 Ecology ................................................................................................................................ 18
6.7.1 Monitoring ...................................................................................................................... 18
6.8 Construction Phase Traffic .................................................................................................. 18
7. Checking and Corrective Action .................................................................................................. 19
Appendix: Water Protection Plan Checklist ......................................................................................... 20
RECEIVED: 21/11/2025
5
1. Introduction:
The project is the infill of an agricultural field to raise the ground level in a site in Tullynahinnera ,
Castleblaney, Co. Monaghan. The project is to import 55,880 tonnes of soil for the infilling of the
site. The maximum depth of cut material is to be 2.306m and the maximum depth of fill material is
4.540m. The total bank area, including both the fill and cut area is 15,695.3m3.
In general, this Construction Environmental Management Plan (CEMP) sets out:
• An environmental management framework to which the Principal Contractor’s
management systems will apply.
• Environmental management and monitoring measures to be adopted and implemented
throughout the infrastructure construction phase.
• Responsibilities for implementation of management and monitoring measures during
infrastructure construction phase.
Measures set out in this CEMP are assumed to be adopted for the purposes of assessing likely
environmental effects of this phase of the development. The CEMP applies to infrastructure works
within the boundary of the site and compliance with its content will be a mandatory requirement in
all associated construction contracts.
In response to the requirements this plan will address the following issues all specifically referred to:
• Noise
• Vibration
• Dust
• Water Quality Management
• Contact arrangements
• Waste Storage, Separation and Disposal
• Ecology
• Emergency Incident Response Plan
The construction phase of the project needs to be carefully controlled so as not to have any
significant impact on the environment and the local community. The Client and Construction
Contractor both have key responsibilities to ensure that these environmental impacts are controlled
adequately. Management during the construction works will be delivered through the development
of a Construction Environmental Management Plan (CEMP). The CEMP will detail how construction
works will be undertaken and managed in accordance with the planning application, planning
conditions, contractual and legislative requirements and construction industry best practice.
This Construction Environmental Management Plan forms part of the planning application
documentation for the project and provides details on the requirements for the management of
environmental impacts associated with the construction phase of the project, together with a
suggested framework from which the CEMP will be produced.
RECEIVED: 21/11/2025
6
The contract documentation for the works will include the CEMP (updated to take into account any
commitments agreed during the planning process) and will ensure that there is a requirement on
the contractor to comply with the actions set out in the CEMP and to demonstrate to the Client how
they intend to identify further environmental impacts and implement the detailed mechanisms for
managing the impacts of works on site. The CEMP will be developed, and all site works should be
undertaken in compliance with the CEMP. The CEMP shall include details of the topics listed below,
further information on which is given in the following sections:
• Project Organisation and Responsibilities
• Project Communication and Co-ordination
• Training
• Operational Control
• Checking and Corrective Action
• Complaints Procedure
The CEMP will be reviewed during the construction process and will include information on the
review procedures.
2. Site Location
The site is located at Tullynahinnera, Castleblaney, Co. Monaghan at Grid Ref (ITM): 678812, 815551.
The location is displayed in Fig 1 outlined in red.
Fig 1: Site Location
RECEIVED: 21/11/2025
7
3. Scope and Purpose
The CEMP defines the approach to waste management at the site during the construction phase
works. Compliance with this CEMP, the procedures, work practices and controls will be mandatory
and must be adhered to by all Construction personnel and personnel employed on the project. This
Plan seeks to:
• Provide a basis for achieving and implementing the construction related control measures,
• Comply with all relevant conditions attached to the Local Authority Planning Permission,
• Promote best environmental on-site practices for the duration of the works.
This Construction Waste Management Plan has been prepared to ensure that the management of
waste during the construction phase of the proposed development is undertaken in accordance
with current legal and industry standards, including Monaghan County Council Waste Segregation
Byelaws.
The purpose of this document is to communicate key waste management obligations that apply to
Ronan Boyd, their sub-contractors and employees while carrying out any form of construction
activity on the project to meet the specified requirements which include Contractual, Regulatory
and Statutory Requirements, Waste Management, Environmental Mitigation Measures and Planning
Conditions.
The principal objective of this CEMP is to avoid, minimise and control adverse impacts associated
with all aspects of the of the project. In essence, this CEMP is intended to provide Ronan Boyd with
a practical guide to ensure compliance by all parties with any Planning and Waste Management
requirements.
This CEMP outlines the work practices, construction management procedures, management
responsibilities, mitigation measures and monitoring proposals that are required to be adhered to,
in order to complete the project in an appropriate environmental manner so to manage the quantity
of waste generated by construction activities.
Key Objectives;
• To ensure that all waste materials are segregated into different waste streams and stored
on site in a managed and dedicated waste storage area for removal by licenced contractors.
• To ensure minimum environmental impact to the existing site location.
RECEIVED: 21/11/2025
8
4. Project Organisation and Responsibilities
Project Role Company / Address Contact Email/Telephone
Contracts Manager/
Site Manager
Tullynahinnera,
Castleblaney, Co.
Monaghan
Ronan Boyd
Project Supervisor for
the Construction
Stage (PSCS)
Mitchell
Environmental,
Tankardrath, Kilberry,
Navan, Co. Meath.
Daniel McManus daniel@mitchellenvironmental.ie
085 2526496
Client Project Manager Responsibilities:
• Review and approve the Contractor’s CEMP together with any specialist procedures and
identify the need for any improvements
• Identify the competence of all contractors to be employed for the works
• Review method statements with regard to environmental aspects and advise and agree any
suggested improvements prior to works commencing
• Provide main contact between Contractor and Client’s project team on environmental and
construction issues
Ronan Boyd will act as the Contracts Manager and Site Manager (Contractor to confirm name of
both parties on appointment as Main Contractor)
Contracts Manager Responsibilities:
• Develop and review the CEMP, construction method statements, work instructions and
other specialist procedures
• Identify competence requirements for all staff and ensure delivery of training to the project
team
• Review and agree method statements for all environmental aspects of project works prior
to works starting with client Project Manager
• Monitor construction activities to ensure that identified appropriate control measures are
effective and ensure compliance with the CEMP
• Act as a main point of contact between the regulatory authorities and the project on all
issues
• Provision of advice and liaison with subcontractors to ensure that risks are identified, and
appropriate controls developed, which are identified within method statements
• Assist with the development and undertaking of training for site staff
• Liaison with the Client Project Manager
RECEIVED: 21/11/2025
9
Site Manager Responsibilities:
• Assist the contract manager in developing and maintain the C EMP together with other
documentation
• Monitor construction works to ensure any necessary control measures are in place and meet
requirements of the CEMP
• Monitor construction works to ensure all staff are complying with and implementing CIF
Covid-19 procedures
• Carry out weekly site inspections and complete inspection report identifying any actions
required
• Maintain training register and provide training where necessary
• Assist in responding to complaints
• In the event of an environmental incident, advise Contracts Manager and Client Project
Manager immediately, confirm their instructions and ensure correct procedures are adhered
to
• Provide information on waste management/reduction procedures to relevant staff
• Implementation and operation of environmental controls on site
• Respond to any minor environmental incidents on site, such as spills
4.1 Project Communication and Coordination
Frequent meetings will be held between all team members to discuss performance to date, the
need for improvements (if any), results of inspections and any complaints received. Upcoming work
operations will be reviewed in order to plan any necessary actions to mitigate risks and to
disseminate information on best practice. If necessary, representatives of the Statutory Authorities
may also be invited to attend such meetings, as and when required.
4.2 Operational Control
Site works will be checked against each of the CEMP requirements. Any mitigation measures that
have been agreed with the Statutory Authorities, or are part of the planning conditions, must be
put into place before the undertaking of the works for which they are required and all relevant staff
will be briefed accordingly. Method statements that are prepared for the works will be
reviewed/approved and recorded by the Client Project Manager.
4.3 Checking and Corrective Action
Daily inspections of the site and the works will be undertaken to minimise the risk of environmental
damage and to ensure compliance with the CEMP. Any environmental incidents are to be reported
immediately to the Site Manager. The Contracts Manager will undertake weekly/fortnightly
inspections as appropriate and complete an assessment of the project’s performance with regard
to the relevant standards/legislation and the contents of the CEMP. Following these inspections, the RECEIVED: 21/11/2025
10
Manager will produce a report detailing the findings which will be provided to the Client Project
Manager and reviewed at the fortnightly project meeting. The Client Project Manager will carry out
weekly inspections of the works in addition to attending the fortnightly project meetings and will be
present on site for certain key operations.
4.4 Environmental Incident Procedure
The Principal Contractor (Ronan Boyd) will establish and implement an environmental incident
procedure. This procedure will be designed to respond to anticipated environmental hazards and
risks on site and will include emergency control measures.
The environmental procedure will include:
• An environmental incident / pollution reporting and response plan.
• Measures to mitigate the adverse effects of an environmental incident.
• Emergency contact details and method of notifying emergency services, Local Authorities,
other statutory authorities and key personnel.
• Measures to be adopted to investigate and prevent the recurrence of an environmental
incident.
4.5 Anticipated Plant and Equipment
Consideration has been given to the type of plant that is likely to be used during construction works.
The anticipated vehicle type and use, as well as the anticipated plant and equipment associated with
the construction process are set out in the tables below.
Table 1: SUMMARY OF VEHICLE TYPE, USE, AND DISTRIBUTION FOR CONSTRUCTION
Vehicle type Use Distribution
Rigid Heavy Goods Vehicle Excavated material transport Strategic road network to
motorway
Vans Small plant, Plant service,
materials, other Suppliers
Distributed to local roads and
motorways
Cars Personnel Distributed to local roads and
motorways
Table 2: ANTICIPTATED TYPES OF PLANT FOR THE CONSTRUCTION PHASE
360 Excavator
Dumper
HGV/Articulated Lorry
RECEIVED: 21/11/2025
11
5. Potential Environmental Impacts
Table 3: POTENTIAL IMPACTS AND HEADLINE MITIGATION MEASURES DURING IMPLEMENTATION
Issue Potential Mitigation
Noise Increased road noise levels from
vehicles. Increased noise levels
from plant during works and
excavation and depositing soil.
Defined working hours, baffles to
certain plant, local acoustic
screening.
Vehicle rerouting.
Beepers, radios etc. to be silenced
where possible.
Engines turned off when not in
use.
Vibration Increased vibration levels from
vehicles and plant during
excavation and depositing soil.
Defined working hours.
Selection of appropriate plant.
Minimise deliveries and vehicle
movement.
Engines switched off when
vehicles are on idle
Quality Windblown dust from ground
surfaces, stockpiles, vehicle work
faces.
Exhaust emissions from lorries
and plant including dust
particulates
Cover all open backed vehicles.
Water down dust generating
activities
Road sweeping
Waste Minimal waste generation is
anticipated.
Separate waste and cover waste
bins.
Soil classed as waste will be
removed according to specialised
method statements
RECEIVED: 21/11/2025
12
Issue Potential Mitigation
Traffic An increase in traffic is expected
during the movement of soil.
Increased vehicle movements
mainly consisting of Heavy Goods
Vehicles.
Transfer of mud and material
onto public road
Phased deliveries and minimise
vehicles attending site.
Switch off engines when parked.
Road sweeper will be on site full-
time
Storage of Fuels and Materials Accidental spills, discharges to
drain/storm-water systems
All fuel tanks and containers to be
bunded.
No significant storage of fuels is
expected onsite
Ecology
Water/mud run off into drains
and surface water
Do not allow direct discharge of
water into to surface waters.
Utilise silt fences where
possible/necessary
6. Construction Environmental Management Plan
6.1 Good Housekeeping
The Principal Contractor (Ronan Boyd) will ensure that the site is always kept in clean and good
working order, including the maintenance and management of all entrances.
6.1.1 Resourcing and Training Development
The Principal Contractor and ESC Environmental will instigate and maintain an induction process for
all workers detailing ways in which to understand the site logistics, health, safety and the
environmental aspects. This will include security measures and a Safe pass is mandatory for all site
operatives. Continued on-site training in the form of targeted toolbox talks will help to maximise
awareness of evolving site-specific hazards and the mitigating measures being implemented to
reduce risk.
6.1.2 Site Security
Ronan Boyd will control access and egress to area around this site for the duration of the
development. In addition, it will be recommended that valuable items and power tools should be
securely stored in site strong boxes or storage containers. Site boundaries will be secured when not
in use and potentially hazardous materials will be safely secured e.g. fuel outlets will be locked, plant
and equipment will be immobilised overnight.
RECEIVED: 21/11/2025
13
6.1.3 General Good Housekeeping Measures
Measures to ensure the site is safe, secure and presentable at all times will include but will not be
limited to the following:
• Clear access routes with appropriate high visibility signposting.
• Segregation and regular removal of waste including food stuffs.
• Keeping the site tidy and clear to minimise hazards.
• Visual inspections of plant, equipment and material storage areas for leaks and spills and
other possible faults.
• Open fires will be prohibited at all times.
• Hard standings for vehicles will be cleaned frequently.
• Mud will be minimised on access routes and cleaned when needed.
• Road sweeper is on site full time to ensure control of soil.
6.1.4 Monitoring
Regular recorded site inspections will be undertaken which will include a review of good
housekeeping practices on site.
6.2 Air Quality and Dust Management
Air quality effects will be controlled through the selection of appropriate plant and machinery,
careful planning of works and effective site management. Planning of works will take into
consideration local topography, prevailing wind patterns and local sensitive receptors. The principle
of prevention and mitigation is to be used to identify if the activity can be achieved minimising dust
and air pollution. Where possible best practice guidance will be applied.
A road sweeper will be present on-site full time to reduce dust generation on the access roads.
Direct dust control by damping down will be used when dust generating activities are occurring
during dry conditions.
6.2.1 Plant and Machinery
In order to mitigate the impact of construction traffic during network peak hours, a Traffic
Management Plan will be developed and implemented by the Contracts Manager. This plan will
focus on the:
• Implementation of ‘just in time’ contract plant hire
• Restriction of unnecessary vehicle movements during the day
• Co-ordination of deliveries to arrive outside of peak times where appropriate
RECEIVED: 21/11/2025
14
6.2.2 Earthworks
Completed earthworks will be sealed or seeded as soon as practicable. Exposed earthworks will be
kept damp to minimise airborne dust emissions.
6.2.3 Materials Handling and Storage
Stockpiles will be located out of the prevailing wind or protected to minimise the potential for dust
generation.
• Stockpiles will be sited away as possible from sensitive receptors including watercourses.
• Tipping height of potentially dust generating materials will be minimised.
6.2.4 Monitoring
Beyond the measures to prevent, control and mitigate the factors affecting air quality, monitoring
will be carried out to include regular visual inspections of dust levels undertaken particularly during
dry periods and action will be taken to reduce levels where necessary.
6.3 Noise and Vibration
6.3.1 General Measures
Measures will be identified and employed to reduce the noise and vibration arising from this phase
of the development. Specific measures will include:
• Selection of routes and programming for the transport of materials, spoil and personnel to
minimise noise and vibration at sensitive receptors.
• Avoidance of vehicles waiting or queuing on the Public Road with engines running.
Only plant conforming to relevant national & international standards, directives and
recommendations on noise and vibration emissions will be used. Plant or equipment liable to create
noise or vibration will be located away from sensitive receptors or will be controlled by the use of
lined and sealed acoustic covers or enclosures.
Any covers or enclosures will remain in place whilst the relevant noise generating equipment is in
use.
RECEIVED: 21/11/2025
15
6.3.2 Working Hours
Normal working hours will be from:
08:00 – 18:00 weekdays
08:00 – 13:00 Saturdays (if works require)
When unforeseen circumstances result in noisy works (audible beyond the boundary of the site)
extending beyond normal working hours, Ronan Boyd will notify and seek approval from Monaghan
County Council and records will be kept of such events by them.
6.3.3 Monitoring
The impact of noise will be mitigated by the selection of appropriate plant and/or techniques and/or
use of noise barriers.
6.4 Soils
6.4.1 General
Excess inert soils and sub-soils excavated that is not required for use as fill on site will be recovered
off-site. Any fill material excavated at the site, which is deemed to be contaminated (i.e. non -
hazardous or hazardous) will be stored separately to the inert material, sampled and tested, in order
to appropriately classify the material as non-hazardous or hazardous. This will establish the criteria
for the acceptance of waste at landfills before being transported to an appropriately authorised
facility by permitted contractors.
6.4.2 Monitoring
Dust generation will be monitored during the project to ensure that dust generation is kept at a
minimum during the course of the project.
Drainage ditches and watercourses in the vicinity of the project will be visually inspected on a daily
basis to monitor for siltation. If excess siltation is noted during the inspection, the import of soil will
be stopped until mitigation such as silt fences are implemented to prevent further contamination.
6.5 Waste
C & D waste can arise on the project from excavation activities if some soil is found to be
contaminated. It is not expected that there will be any wastes produced due to the nature of the
site and the project. The developers shall ensure that materials are ordered so that the quantity
delivered, and the storage is not conducive to the creation of unnecessary waste. RECEIVED: 21/11/2025
16
6.5.1 Minimising Waste
In order to minimise the generation of waste and waste disposed to landfill, all spoil, construction
arisings and wastes will be managed in accordance with the waste hierarchy and relevant regulatory
controls.
6.5.2 Concrete Waste
Concrete waste is not expected due to this project as there is no building to take place on the site.
6.5.3 Hazardous Waste
The management of hazardous waste will comply with current legislation:
• The Waste Management Acts (WMA) 1996 to 2005
• Waste Management Regulations 1998
Hazardous waste which may be encountered on site include:
• Waste oils or fuels
• Soils contaminated with waste oils or fuels
• Soils contaminated with septic tank runoff
• Used aerosol containers
Hazardous wastes will be kept from other C & D waste materials in order to avoid further
contamination and will be stored on site in suitable receptacles for subsequent separation and
disposal at a suitable permitted remote facility. Other C & D waste materials will be collected in
receptacles with other mixed C & D waste materials for subsequent separation and disposal at a
remote facility. Packaging will be source separated for recycling and return to the suppliers.
6.5.4 Storage of Soil, Materials, and Waste
During the development, waste will be clearly labelled and segregated on site. Measures will be
taken to ensure that wastes cannot blow away.
For the soils that require disposal Waste Acceptance Criteria (WAC) testing has been carried out
and a waste characterisation has been conducted. Arrangement have been made for all the
acceptance of the soils by the licenced end destination.
Housekeeping measures will be followed for the storage of materials to ensure that materials are
protected as much as possible.
The burning of waste on site will not be permitted.
RECEIVED: 21/11/2025
17
Site management will ensure that materials are not delivered to site too early and are not exposed
to damage from weather or poor storage.
To mitigate the effect on the development on the surface water next to site, any plant parked at
least 10m away from surface water or storm water drains, drip tray used and spill kits available on
site.
6.5.5 Monitoring
Materials and waste taken off site will be measured and monitored. As a minimum, the following waste
management data will be provided:
• Quantity of materials and waste removed from site by type in volume and weight.
• Outcome of the materials and waste on and off site.
• Waste transfer notes.
• Hazardous waste consignment notes
6.6 Drainage
6.6.1 Consents
Where discharges are required to controlled waters or sewers, consent will be obtained. This is not anticipated.
6.6.2 Site Drainage
It is not expected that any discharge to watercourses will occur but if it becomes necessary they will only be
permitted where discharge consent or other relevant approval has been obtained.
6.6.3 Pollution Controls
• All potentially polluting substances will be stored on impermeable surfaces with controlled drainage
or at least 10m away from storm water sewers, grids, channels, watercourses and ditches.
• All fuel, chemicals and oils will be stored within bunded areas.
• All tank discharge pipes, valves and trigger guns will be contained securely within the bund when not
in use.
• Bowsers will be stored within secure areas when not in use to protect against theft or vandalism.
• Leaking or empty drums will be removed and stored in a suitably bunded area separating from other
drums prior to disposal by an appropriate licensed waste disposal contractor.
• All hazardous substances on site will be controlled in accordance with COSHH Regulations (2004).
• Refuelling of plant and machinery will take place on concrete hard standing with controlled drainage.
• Washing out of plant will take place in areas away from storm water sewers, grids, channels and
watercourses.
• Spill kits will be held on site with a variety of absorbent materials to be used in the event of a spill of
fuel, oil or chemicals.
RECEIVED: 21/11/2025
18
6.6.4 Managing Run Off and Silty Water
Measures will be taken to ensure that run off from earthworks does not enter drains, watercourses or ditches
including the use of silt fences. Areas of exposed ground and stockpiles will be minimised where possible to
reduce silty run off.
Water unpolluted other than with coarse particles and with relatively small flows may be treated by passing
through tanks or skips with a suitable filter such as gravel, geotextiles, straw bales or silt traps.
Where periods of prolonged or heavy rainfall are forecast, appropriate additional measures will be taken to
control surface run off and move potentially polluting activities out of the areas susceptible to flood risk.
6.6.5 Monitoring
All discharges will be visually monitored in accordance with the consents held. The use of water will be
minimised during the project.
6.7 Ecology
An Appropriate Assessment Screening was carried out by ESC Environmental and the project was screened
out for potential for impact on the conservation objectives of connected designated site. This report noted
that there are no designated sites located within 15 km of the site location.
A range of generic mitigation/enhancement measures have been suggested in this CEMP. When
implemented effectively, would reduce the impact of the works on the local environment.
6.7.1 Monitoring
The site management team will as part of their site inspections monitor the site. If any creature is found to be
nesting in the site area measures will be taken as described above and relevant advice sought.
6.8 Construction Phase Traffic
In order to mitigate the impact of traffic during network peak hours, a Traffic Management Plan will
be developed and implemented by the Contracts Manager. This plan will focus on the:
• Co-ordination of car parking for construction personnel
• Implementation of ‘just in time’ contract plant hire
• Restriction of unnecessary vehicle movements during the day
• Co-ordination of deliveries to arrive outside of peak times where appropriate RECEIVED: 21/11/2025
19
The construction phase of the road will increase the road traffic movements as the area is situated
in a quiet rural area. It is not anticipated that any extra traffic measurements need to be implemented
for the vehicles entering and departing the works.
7. Checking and Corrective Action
Daily inspections of the site and the works will be undertaken to minimise the risk of environmental
damage and to ensure compliance with the CEMP. Any environmental incidents are to be reported
immediately to the Site Manager. The Contracts Manager will undertake weekly/fortnightly
inspections as appropriate and complete an assessment of the project’s performance with regard
to the relevant standards/legislation and the contents of the CEMP. Following these inspections, the
Manager will produce a report detailing the findings which will be provided to the Client Project
Manager and reviewed at the fortnightly project meeting. The Client Project Manager will carry out
weekly inspections of the works in addition to attending the fortnightly project meetings and will be
present on site for certain key operations.
RECEIVED: 21/11/2025
20
Appendix: Water Protection Plan Checklist RECEIVED: 21/11/2025
MONAGHAN LOCAL AUTHORITIES
Environment Protection Plan Checklist
This is a checklist to be completed by applicant to be backed up by an appropriate level of detail
depending. To be accompanied by a Site Drainage Plan – as set out in the Monaghan County
Development Plan 2025 – 2031.
General Site and Water Body Details
Planning Ref. No. Applicant
Townland Water Supply Source
X Co-ordinate 1 Y Co-ordinate 1
WFD River Sub Catchment2 WFD River Sub Basin2
WFD River Waterbody latest
Status 2
Status Year WFD River Waterbody
Risk2
WFD River Waterbody
Objectfve2
Groundwater Vulnerability Aquifer Importance
Proximity to sensitfve receptors (Private Wells, Public and Private Water Supply
Sources, Amenity Areas, SPA’s, SAC’s , NHA) (meters)
Proximity to nearest watercourse (culverted or open), wetland or lake (meters)
Existfng EPA Licence (insert licence no)
Existfng Sectfon 4 licence (insert licence no)
Proposed Development
Is the development entirely or part of one of the following? (tick)
Domestfc dwelling Agricultural (cattle/dairy) Industrial-food related
Public Works Agricultural (mushrooms) Industrial-non food
Housing Agricultural (poultry) Quarrying/extractfve
industries
Instftutfonal Agricultural (piggery) Transport related
Commercial/Retail Other agricultural –
specify below
Filling statfon/Fuel depot
Mixed Use
Development
Other
Waste Permit
Type of wastewater Produced by the proposed development (tick)
No wastewater produced
Domestfc type waste waters <5m3 per day
Domestfc type waste waters >5m3 per day 4
Waste waters produced from any trade, food,
preparatfon or business 4
Wheel wash, vehicle wash, cooling waters 4
Waste waters produced from quarrying etc 4
Other waste waters 4
N/A Ronan Boyd
Tullynahinnera N/A
78867 15534
Dromore_SC_010 Major Lough Stream_010
Poor 2019 -
2024
At Risk
No
Extreme Poor Aquifer
Well: 730m NE
630m
N/A
N/A
X
Infill for land improvement
X RECEIVED: 21/11/2025
Have proposals for Wastewater Management during the operational phase and full details of same
been included with the application? (tick)
Public Sewer Connectfon details (Uisce Eireann)
Existfng Wastewater Treatment System
Proposed new onsite wastewater treatment
system
No wastewater generated
Have proposals for Waste Facility aftercare and use been included with the application? (tick)
Agricultural Improvement Plan where
applicable
Closure plan and aflercare details
Proposed water sampling locatfons clearly
identffied
License or Lease agreement for the site if not
owned by the applicant.
Fuel or Outdoor Material Storage for Non-Domestic Developments - operational phase (tick)
Number of fuel storage tanks existfng or proposed on site?
Are fuel storage tanks bunded 5?
Any liquid / feedstuffs / organic / chemical / waste oil storage
on outdoor sites ?
Proposals for protection of water receptors during the Construction Phase
Has a CEMP relatfng to water protectfon and
waste management been included with the
applicatfon?
Name of person appointed to oversee the
implementatfon of the CEMP.
Hard Surface and Open Yard Areas for Non Domestic Developments (tick)
If yes, are silt trap(s), interceptor(s), soiled water tanks or other control
measures shown on drainage plan?
Has the use of SUDS (Sustainable Urban Drainage Systems –
http://www.susdrain.org ) been included in the design of this
development?
Development History – All Developments (tick)
Have previous pollutfon preventfon planning conditfons been complied with 6?
Does existfng development have an up to date (as constructed) site drainage plan?
Is the existfng/proposed development sewered or unsewered?
If unsewered, is the existfng wastewater treatment system fit for purpose7?
Has the storm water drainage system been examined and/or surveyed for
misconnectfons?
Is there an existfng Certfficate of Registratfon or Waste Facility Permit at the site?
Checklist of items to be included on the Site Drainage Plan (tick)
Locatfon of lakes, watercourse, wells used for water supply, or karst features on or within
25m of domestfc or 100m of non-domestfc development site
Locatfon of all clean drainage outiall points
Foul water drainage system (in Red)
Footprint of proposed development including yard areas in m2 No Hardstanding/yard
Is there potentfal for soiled yard areas from material, product waste or
manure handling, fuel dispensing, silt and soil, yard washing etc.
X
X
Ronan Boyd RECEIVED: 21/11/2025
Storm water drainage system (in Blue)
Soiled yard area, soiled water drainage and management system
Storm water management system, including silt traps, oil interceptor(s) and SUDS
facilitfes
Locatfon of waste water treatment facilitfes
Locatfon of fuel storage tank(s)
Stream/Lake/Wetland/Riparian Corridors/Wells
Footnotes and Useful Information
1Projectfon in the Irish Grid
2WFD informatfon available online at www.catchments.ie
WFD mapping available online at https://gis.epa.ie/EPAMaps/Water
3Available in the groundwater mapping sectfon www.gsi.ie
4If a trade eftfuent or discharge >5m3 of domestfc type wastewater to ground is proposed a Sectfon 4
discharge licence may be required https://monaghan.ie/environment/discharge-licences/
Proposals for wastewater treatment shall be sufficient to demonstrate that the discharge will not cause
deterioratfon in water quality of the receiving water body in accordance with the requirements of the
European Communitfes Environmental Objectfves (Surface Waters) Regulatfons 2009 as amended and
the European Communitfes Environmental Objectfves (Groundwater) Regulatfons 2010 as amended.
5Guidance on Best practfce for Oil Storage (BPGCS05) and note requirements of Building Regulatfons.
6Have previous planning conditfons been complied with e.g. Has certfficatfon of installatfon for
previously granted wastewater treatment system been required and if so, has it been submitted with
this applicatfon.
7Refer to EPA Guidance at: https://www.epa.ie/publicatfons/compliance--enforcement/waste-
water/2021_CodeofPractfce_Web.pdf
8 Refer to Water Body, Sensitfve Waters and Sensitfve Land Maps in the Monaghan County
Development Plan 2025-2031.
Abbreviations
WFD Water Framework Directfve
SAC Special Area of Conservatfon
SPA Special Protectfon Area
NHA Natural Heritage Area
EPA Environment Protectfon Agency
CEMP Constructfon Environmental Management Plan
For Office Use: Sensitivity of Location –
Is the development located upstream of a high river quality site 8?
Is the development located within a good status waterbody 8?
Is the development located in the catchment of a water supply source 8?
Is the development located within the Source Protectfon Zone (SPZ) of a groundwater supply
source 8?
Does the development require a discharge licence to surface or ground waters under the Water
Pollutfon Acts?
Risk to waters in relatfon to scale of development, previous planning/environmental history, IPPC
or EIA aspects, site management and locatfon in a sensitfve area
Applicant_______________________________
Agent:_________________________________ Date_____________
Ronan Boyd
Michael Hetherton Architectural
& Engineering Services
31/10/2025 RECEIVED: 21/11/2025