HomeMy WebLinkAbout2560469 - F.I. Received Doc. - Revised CEMP
Prepared in response to Request for Further Information – Item 4
Planning Ref. 25/60469
Proposed 850 kW Wind Turbine
Connolly Meats
Co. Monaghan, Ireland
May 2026
Energy next to you
REVISED OUTLINE CONSTRUCTION
ENVIRONMENTAL MANAGEMENT PLAN
(CEMP) RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
CONTENTS
1. INTRODUCTION .......................................................................................................................................... 5
PURPOSE OF THE CEMP .............................................................................................................................................. 5
2. OBJECTIVES AND SCOPE .............................................................................................................................. 5
OBJECTIVES ................................................................................................................................................................. 5
SCOPE OF WORKS ....................................................................................................................................................... 5
OBLIGATIONS OF CONTRACTORS AND SITE PERSONNEL ........................................................................................... 5
3. PROJECT DESCRIPTION ................................................................................................................................ 6
SITE LOCATION ............................................................................................................................................................ 6
KEY PROJECT COMPONENTS ....................................................................................................................................... 7
PURPOSE AND BENEFITS ............................................................................................................................................. 7
4. CONSTRUCTION MANAGEMENT FRAMEWORK ............................................................................................ 7
CONSTRUCTION SCHEDULE ........................................................................................................................................ 7
PROJECT ROLES AND RESPONSIBILITIES ..................................................................................................................... 8
5. CONSTRUCTION PLAN ................................................................................................................................. 8
OVERVIEW .................................................................................................................................................................. 8
CONSTRUCTION STAGES ............................................................................................................................................. 8
ON-SITE ACCESS TRACKS ............................................................................................................................................. 9
CONSTRUCTION OF SERVICES ................................................................................................................................... 10
WATER MANAGEMENT ............................................................................................................................................ 11
SITE POTENTIAL FOR HISTORIC CONTAMINATION OF LAND .................................................................................... 12
6. HEALTH AND SAFETY ................................................................................................................................. 12
7. EMPLOYMENT AND ACCOMMODATION .................................................................................................... 13
8. SITE ENVIRONMENTAL AWARENESS .......................................................................................................... 13
WORKING HOURS ..................................................................................................................................................... 13
SITE CONDUCT .......................................................................................................................................................... 13
DO / DON’T ............................................................................................................................................................... 14
ENVIRONMENTAL BRIEFINGS ................................................................................................................................... 14 RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
INCIDENT RESPONSE ................................................................................................................................................. 14
9. ENVIRONMENTAL RISKS & CONTROL MEASURES ....................................................................................... 14
NOISE ........................................................................................................................................................................ 14
DUST ......................................................................................................................................................................... 15
LITTER, MUD & HOUSEKEEPING ............................................................................................................................... 15
SOIL, GROUND WATER & SURFACE WATER PROTECTION ....................................................................................... 16
TRAFFIC MANAGEMENT & CONSTRUCTION TRAFFIC .............................................................................................. 17
10. ECOLOGY: BASELINE & MITIGATION MEASURES ........................................................................................ 18
11. OPERATIONAL LIFESPAN OF THE PROPOSED WIND TURBINE ...................................................................... 21
ROUTINE MAINTENANCE .......................................................................................................................................... 21
MONITORING DURING OPERATION ......................................................................................................................... 21
SAFETY MEASURES.................................................................................................................................................... 21
OPERATIONAL NOISE MANAGEMENT ...................................................................................................................... 21
ENVIRONMENTAL PROTECTION IN OPERATION ....................................................................................................... 21
12. DECOMMISSIONING PLAN ......................................................................................................................... 22
WIND TURBINE REMOVAL ........................................................................................................................................ 22
TURBINE FOUNDATIONS ........................................................................................................................................... 22
UNDERGROUND CABLING ........................................................................................................................................ 22
TRAFFIC MANAGEMENT ........................................................................................................................................... 22
13. PRELIMINARY WASTE MANAGEMENT PLAN .............................................................................................. 22
14. IMPLEMENTATION OF CEMP ..................................................................................................................... 23
Appendix 1: WATER SAMPLING PLAN .................................................................................................................. 25
Section 1: INTRODUCTION ................................................................................................................................... 26
Section 2: SURFACE WATER MONITORING ........................................................................................................... 27
2.1 Appointed Personnel .............................................................................................................................................. 27
2.1.1 Training ............................................................................................................................................................ 27
2.2 Recording and Reporting ........................................................................................................................................ 27
2.3 Water Sample Monitoring ...................................................................................................................................... 28 RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
2.3.1 Water Sample Locations .................................................................................................................................. 28
2.3.2 Surface Water Monitoring Schedule ............................................................................................................... 30
Section 3: CONCLUSION ...................................................................................................................................... 33
Appendix 2: SITE DRAINAGE PLAN ....................................................................................................................... 34 RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
1. INTRODUCTION
This site-specific revised Outline Construction and Environmental Management Plan (CEMP) defines the
project-specific environmental measures to be implemented and the procedures to be followed for the
temporary and permanent construction works associated w ith the proposed wind turbine installation at
Connolly Meats Limited, Scotstown, Co. Monaghan.
This revised CEMP has been prepared in response to Item 4 of the Request for Further Information issued by
Monaghan County Council under Planning Ref. 25/60469. It has been updated to address surface water
pathways, EPA PIP-P flow delivery pathway information, drainage buffers, water quality monitoring, Inland
Fisheries Ireland guidance, pollution prevention and environmental supervision during the construction phase.
This document forms part of the overall documentation for the project. The CEMP will be reviewed and
updated during the works as required. Any significant variations to this document will be notified to the
regulatory authorities, where required, prior to the relevant construction works taking place.
PURPOSE OF THE CEMP
The objective of this document is to communicate and record the construction processes and the key
environmental obligations that apply to the construction of the proposed wind turbine.
2. OBJECTIVES AND SCOPE
OBJECTIVES
The purpose of this Construction and Environmental Management Plan (CEMP) is to set out the construction
methods, environmental controls and management procedures that will be applied during the construction of
the proposed 1 no. 850 kW wind turbine at Connolly Meats, Scotstown, Co. Monaghan.
The CEMP aims to:
• Ensure that all construction activities are planned and undertaken in a manner that prevents, reduces
or mitigates adverse impacts on the environment and on nearby receptors.
• Provide a clear framework for roles, responsibilities, communication and reporting during the
construction phase.
• Demonstrate to the Planning Authority and other regulators how construction will be managed in
compliance with relevant legislation, guidance, and planning conditions.
SCOPE OF WORKS
This CEMP applies to all works required to construct, commission and make safe the proposed wind turbine
and associated infrastructure, including but not limited to:
• Site establishment, temporary compound and welfare facilities.
• Construction of the crane hard standing and short access track from the existing entrance.
• Excavation, shuttering, reinforcement and concrete works for the turbine foundation.
• Installation of underground ducts, cabling and associated electrical works between the turbine and the
existing on-site substation.
• Delivery, lay-down, assembly and erection of the turbine tower, nacelle and blades.
• Surface water and groundwater management during excavation and construction.
• Temporary storage and handling of materials, including topsoil, subsoil and construction materials.
• Site reinstatement, seeding and landscaping of disturbed areas on completion of works.
The CEMP covers the construction phase only. Operational phase and decommissioning measures are
described separately in the Planning Report and Decommissioning / Waste Management sections.
OBLIGATIONS OF CONTRACTORS AND SITE PERSONNEL RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
All contractors, subcontractors and site personnel engaged in the works are required to:
• Comply with the measures, procedures and controls set out in this CEMP and any subsequent updates
agreed with the Planning Authority.
• Prepare and implement method statements, risk assessments and emergency response procedures
that are consistent with this CEMP.
• Attend site inductions and toolbox talks, and follow all environmental, health and safety instructions
given by the Site Supervisor or Project Manager.
• Immediately report any incident, near miss, spill, pollution event or non-compliance to the Site
Supervisor and cooperate fully in implementing corrective actions.
• Use plant, equipment and construction methods that minimise noise, dust, vibration, waste generation
and risks to soil, surface water and groundwater.
• Store, handle and dispose of fuels, oils, chemicals and wastes in accordance with this CEMP, the
Waste Management Plan and all relevant legislation.
Compliance with this CEMP is a contractual requirement for all contractors working on the project, and
adherence will be monitored through regular site inspections and audits.
3. PROJECT DESCRIPTION
The proposed development consists of the installation of one 850kW Vestas V52 wind turbine, with a hub
height of 65 metres and a blade length of 26 metres, located within the lands to the north of the Connolly Meats
facility in Scotstown, Co. Monaghan. The turbine will support the facility’s energy demands and contribute to
reduced carbon emissions through on-site renewable energy generation.
SITE LOCATION
The turbine will be positioned in an agricultural field approximately 252.6 metres north of the main Connolly
Meats plant. All works will be contained within the applicant’s landholding, with no requirement for off -site
construction activities apart from the temporary delivery of turbine components using the public road network. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
KEY PROJECT COMPONENTS
The development includes the following principal elements:
• Wind turbine: 850kW Vestas V52 model, comprising tower, nacelle, hub, and three blades.
• Foundation: A reinforced concrete foundation sized approximately 14.5m × 14.5m, incorporating
around 420m³ of excavation, 15 tonnes of reinforcement steel, shuttering, and an estimated 320m³ of
concrete (subject to final manufacturer design).
• Hardstand and crane pad: A stone-surfaced area for delivery, assembly, and crane operations,
constructed using approximately 100m³ of stone and geotextile materials, depending on ground
conditions.
• Access and internal haul road: Temporary and/or permanent stone access routes to facilitate safe
movement of construction vehicles and cranes.
• Electrical infrastructure: Underground ducting, cabling, earthing, and associated equipment
connecting the turbine to the designated point within the Connolly Meats electrical network.
• Wind turbine assembly: Delivery of components in sections, followed by mechanical and electrical
assembly. Erection of the tower, nacelle, and blades is typically completed within a single day, subject
to suitable weather conditions.
PURPOSE AND BENEFITS
The installation of the wind turbine will enhance the renewable -energy capacity of the Connolly Meats facility,
reducing reliance on imported grid electricity and contributing to long -term sustainability objectives.
4. CONSTRUCTION MANAGEMENT FRAMEWORK
This section describes the management systems and procedures that will govern the preparation and
construction activities associated with the proposed wind turbine development. It outlines the construction
elements included within the scope of this CEMP, the environmental controls that will be applied, and the
responsibilities of personnel involved in the works.
The scope of this CEMP includes:
• All construction elements associated with the proposed development.
• The implementation and management of environmental controls and mitigation measures during each
phase of works.
• Procedures to ensure that all measures identified during the planning process are effectively
implemented on site.
CONSTRUCTION SCHEDULE
Construction is anticipated to commence approximately two months after obtaining planning permission,
typically between April and October, allowing time for final design procurement and preparatory activities.
Appropriate site signage will be erected in advance of works.
A temporary site compound will be established within or adjacent to the Connolly Meats facility to provide
access to required services and welfare facilities.
The main construction activities will include:
• Site setup and mobilisation
• Foundation excavation and construction (estimated duration: 3 weeks)
• Curing period prior to turbine erection
• Delivery of turbine components
• Crane operations and turbine assembly
• Electrical installation, cabling and connections
• Final testing and commissioning
Turbine erection will be scheduled following the curing period and will depend on safe weather conditions,
including wind and precipitation levels, as well as contractor availability. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
PROJECT ROLES AND RESPONSIBILITIES
Project Manager
• Responsible for the overall development and implementation of this CEMP.
• Allocates resources to ensure successful implementation of environmental and safety measures.
• Ensures all relevant instructions and guidance are communicated to supervisors and site personnel.
• Establishes procedures for incident reporting, investigation and corrective actions.
• Plans and manages site operations to minimise risk and incorporates environmental considerations
when appointing subcontractors and approving method statements.
Site Supervisor
• Understands and enforces the requirements of the CEMP.
• Ensures that all staff are briefed on their responsibilities and adhere to environmental and safety
controls.
• Implements daily measures to eliminate or reduce on -site risks.
• Oversees compliance with environmental mitigation measures during all phases of the construction
process.
Site Personnel
• Comply with all requirements of the CEMP and associated site rules.
• Carry out works in a safe and environmentally responsible manner.
• Report any incidents, non-compliances or environmental risks to the Site Supervisor.
• Follow all instructions related to environmental protection, health and safety.
Environmental Clerks of Work (EnvCoW)
• Undertake water sampling and review water sampling data.
o Halt works where there is a where trigger levels have been exceeded. Establish new mitigation
measures to avoid further breaches in water quality (See Appendix 1).
5. CONSTRUCTION PLAN
This section outlines the step-by-step construction methodology for the proposed wind turbine. The plan is
indicative and may be refined by the appointed contractors, but all updates must remain consistent with this
CEMP and the planning permission requirements.
The construction plan covers:
• Construction stages (1–9)
• Access and haul routes
• Construction of services
• Water management
• Contamination considerations
OVERVIEW
All works will be undertaken in accordance with the environmental controls and mitigation measures set out in
this CEMP. The construction methodology may be updated as further site information becomes available or as
required by safety considerations, weather conditions or Connolly Meats operational needs. Any such updates
will be reviewed by the Project Manager before implementation.
CONSTRUCTION STAGES
Stage One: Hard Stand
• Clearing of all topsoil to prepare the haul road.
• Installation of a separation geotextile on the formation, followed by placing and compacting
crushed stone in layers to construct the haul road.
• Clearing of all topsoil from the crane pad and foundation area.
• Installing geotextile and stone in all areas except the foundation excavation area. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• Compacting the stone in layers using excavators, dumpers, delivery vehicles, and rollers.
Stage Two: Delivery of the tower and blades
• The tower and blades will be transported to the site on flatbed extendable trailers.
• Unloading will be done using two cranes in tandem for the towers and a single crane with a
spreader beam for the blades.
• All towers will be stored and cleaned before erection.
• Blades will be examined and surveyed prior to erection.
Stage Three: Foundation Construction
• Excavating the foundation to formation level.
• Installing a 50mm base of lean mix concrete with a sump for pumping to one side.
• Tying the foundation piece for the tower with the necessary reinforcing into the steel.
• Installing shuttering around the external perimeter of the foundation.
• Inspecting and pouring the foundation.
Stage Four: Curing and Backfilling
• Allowing the foundation to cure for the required number of days.
• After curing, striking the shuttering, and commencing backfilling.
Stage Five: Tower Erection
• The foundation can be backfilled after 3 days but normally the tower cannot be erected for 28
days until the concrete has reached design strength.
Stage Six: Preparing for Erection
• While the foundation is curing, preparing the towers, blades, nacelle, and ancillary equipment
for erection.
Stage Seven: Turbine Erection
• Planning the turbine erection based on weather suitability.
• Mobilizing cranes to the site and using tandem lifts to install the tower sections.
• Installing the nacelle and tightening all bolts before installing the blades and torquing all bolts to
full strength.
Stage Eight: Electrical Connection
• Establishing the electrical connection to the tower at both low and medium voltage, terminating
in the main plant switch room.
Stage nine: Testing and Commissioning
• Testing and commissioning the tower, including EGIP (Electrical Generation, Injection, and
Protection) testing witnessed by the ESB (Electricity Supply Board).
• Once successfully tested and commissioned, the tower is put into production.
ON-SITE ACCESS TRACKS
Proposed Road track
To establish a sustainable and environmentally considerate approach, the proposed on -site access tracks
have been thoughtfully designed. From the site entrance, the newly created track will be utilized to reach the
wind turbine location, spanning approximately 25 meters.
Throughout the wind farm's operational lifetime, these access track will play a dual role —initially supporting
construction vehicles and subsequently facilitating maintenance vehicles' access and benefiting the
landowners. The access track's width will ave rage around 5 meters.
The complete design and details of the road will be produced if permission is obtained.
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Environmental Integration
The addition of new access tracks will be confined to reaching the wind turbine site. The track's layout will
follow existing hedgerows whenever possible, capitalizing on their natural screening to mitigate visual impact.
To ensure minimal disruption, the choice of route has been carefully guided by environmental considerations,
conforming to guidelines aimed at ecological preservation.
Low-Impact Construction
The construction approach is rooted in low-impact techniques. Initial surface preparation will involve
vegetation clearance solely where necessary, utilizing biodegradable or eco-friendly erosion control materials.
Innovations such as geotextile mats or geogrids will stabilize the road surface without extensive excavation.
Gravel or crushed stone will form the road base, a reversible choice facilitating eventual removal and site
restoration post-decommissioning. Water management strategies will be integral, encompassing drainage
techniques, culverts, and ditches to avert erosion and water accumulation.
Disturbance Mitigation and Restoration
To curtail impact, both the width and length of the access road will be restricted to the minimum requisite for
accessibility. This prudent approach minimizes resource usage and area of influence. An integral element, the
restoration plan will be established prior to construction initiation, outlining the comprehensive post -road-use
restoration strategy. Precise details encompassing reseeding, replanting, and other necessary restorative
actions will be incorporated.
Ongoing Monitoring and Responsible Removal
Vigilant monitoring throughout the road's use will promptly identify and address any potential environmental
concerns, ensuring their timely mitigation. To conclude the road's service, a meticulous removal plan will be
implemented. After wind turbine installation completion, the road will be systematically dismantled, with the
disturbed area reinstated using topsoil and native vegetation, restoring the site to its original state.
By adhering to these ecologically conscious practices, the temporary access road will efficiently serve its
purpose of facilitating safe wind turbine site access while harmonizing with the surrounding environment. Our
commitment to sustainable construction underscores our dedication to both operational effectiveness and
environmental preservation.
CONSTRUCTION OF SERVICES
Electrical Connections
During the construction phase, temporary electrical power for site cabins, lighting and small tools will be
provided by a low-noise generator. This temporary supply is for construction purposes only and will not alter or
be connected to the permanent electrical arrangement of the Connolly Meats facility.
Electrical works associated with the turbine connection will take approximately 2 weeks and will involve the
installation of switchgear, circuit breakers, transformers and cabling, the commissioning of the electrical
system, and the commissioning of the automated control system. These works will require the excavation of
trenches from the turbine to the existing on-site substation to accommodate underground feeder cables (see
Layout Plan for details). The permanent connection will operate as an embedded sup ply to meet the plant’s
own demand, with no export of electricity to the public grid.
Site Storage
A storage compound will be set up on the crane pad for the storage of all inert materials, including the blades
and tower sections. Additionally, a container will be placed on-site to store nuts, bolts, cables, etc. Oil or other
liquids will not be stored on-site but will be delivered on an ad hoc daily basis from a local supplier. Topsoil and
subsoil will be stored on-site in designated areas shown on the site layout drawing, with surplus subsoil
disposed of off-site. Turbine components will also be stored in specified locations as indicated on the layout
drawing.
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
location of the site and materials compound
WATER MANAGEMENT
Ground Water
During excavation of the foundation, if any ground water is encountered, it will be pumped approximately 30
meters downhill from the excavation. The water will pass through a silt separating bag at the end of the pump
hose to allow any silt particles that were not captured in the bag to settle out before the water enters the
watercourse. This process ensures that any potential silt pollution is minimized.
Surface Water
Any surface water gathered in the excavation will be managed similarly to ground water. It will be pumped to a
field down slope, filtered through a silt bag, and allowed to attenuate and percolate as much as possible before
reaching the watercourse. This approach helps prevent sediment from entering watercourses.
In addition, all stockpiles of soil and subsoil, as well as any storage of fuel, oils or chemicals (if required), will
be located at least 15 metres away from any watercourse or drainage ditch. This setback, combined with the
use of silt bags and controlled pumping, will further reduce the risk of sediment or contaminants entering the
Maghery Stream or other local watercourses. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Seeding of and landscaping disturbed soils to be reinstated will be undertaken as soon as construction is
complete, and soil is levelled. Ideally this will take place during the growing period (early April to late
September), to allow grass cover to establish before the winter season.
The Proposed Development has incorporated a series of mitigation measures as outlined in Inland Fisheries
Ireland (IFI) ‘Guidelines on Protection of Fisheries During Construction Works in and Adjaecent to Waters’ (IFI,
2016) which were deemed relevant.
Foul Water
No foul water will be generated because of the development.
Seeding & Landscaping
Disturbed ground will be reinstated promptly following construction, including regrading and seeding.
SITE POTENTIAL FOR HISTORIC CONTAMINATION OF LAND
Site History
The development site for the proposed project is centred at Grid Reference H 56616 37109, the adjoining lands
currently used as agricultural fields as well as residential houses and a few private businesses. There are no
Annex I habitats recorded onsite or in the immediate vicinity. The main soil type is acid deep well drained
mineral within the acid brown earths, brown Podzolics soil group. These soils are derived mainly from non -
calcareous parent materials. Small occurrences of acid shallow well drained m ineral derived from mainly non-
calcareous parent materials surround the project area. These soils are within the shallow acid brown,
earths/brown Podzolic, Lithosols, Rego sols and some outcropping rock soil group. The site is located over a
poor aquifer – bedrock which is generally unproductive except for local zones. The ground waterbody Water
Framework Directive (WFD) latest status is listed as ‘Good’.
In the unlikely event of any evidence of soil contamination being found during work on site. Appropriate
remediation measures will be employed, in full compliance with all relevant waste legislation. Any work of this
nature would be carried out in consultation with, and with the approval of the Environmental Department of
Monaghan County Council.
6. HEALTH AND SAFETY
All construction works associated with the proposed wind turbine will be carried out in compliance with the
Safety, Health and Welfare at Work Act 2005, the Safety, Health and Welfare at Work (Construction)
Regulations 2013, and all other relevant Irish health and safety legislation and guidance. The appointed
contractor will be responsible for preparing a detailed Health and Safety Plan prior to commencement of site
works.
A site-specific Site Safety Statement, Risk Assessments (RAs) and Method Statements (MSs) will be
prepared and implemented to ensure safe execution of all construction activities.
Key health and safety principles applicable to this project include:
• Ensuring all personnel entering the site receive a full site induction.
• Implementing safe systems of work for high-risk activities, including lifting operations, excavation,
working near machinery, and electrical works.
• Maintaining secure and clearly marked work areas, with restricted access for authorised personnel
only.
• Ensuring that appropriate personal protective equipment (PPE) is used at all times.
• Following emergency response procedures for fire, environmental incidents, medical emergencies, or
severe weather.
• Maintaining good housekeeping to avoid slips, trips, and other hazards.
• Ensuring compliance with all traffic management controls for vehicles and pedestrians.
• Ensuring safe coordination with Connolly Meats operations to prevent interaction with plant activities.
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
The Site Supervisor will be responsible for monitoring compliance with safety procedures, conducting daily
briefings, and ensuring that all staff understand their duties and obligations.
Contractors will be required to immediately report any incidents, near -misses, or hazards to the Project
Manager and to take corrective actions as necessary.
7. EMPLOYMENT AND ACCOMMODATION
Employment for the construction phase will primarily involve specialist contractors experienced in wind turbine
foundation works, crane operations, electrical installation and turbine assembly. Additional general
construction staff will be engaged as required for site preparation, access works and reinstatement.
Construction personnel will generally travel to and from the site daily. No long -term on-site accommodation
will be required. Welfare facilities, including toilets, handwashing stations, rest areas and first -aid provisions,
will be provided within the temporary site compound or in coordination with existing Connolly Meats facilities.
All workers will comply with Connolly Meats site access requirements and must follow health, safety and
environmental procedures at all times. Parking for construction staff will be arranged within the designated
construction compound or another suitable location within the Connolly Meats landholding, in order to avoid
impacts on facility operations or public roads.
Contractors will be expected to provide transport for their personnel to minimise vehicle volumes and ensure
efficient access management.
8. SITE ENVIRONMENTAL AWARENESS
This section outlines the environmental expectations, working hours, and behavioural responsibilities that
apply to all personnel on site. All workers must be aware of and comply with the environmental controls set out
in this CEMP.
WORKING HOURS
Construction activities will take place during standard working hours unless otherwise agreed with Connolly
Meats management and subject to planning conditions:
• Monday to Friday: 08:00 – 18:00
• Saturday: 08:00 – 14:00
• Sunday / Public Holidays: No construction works, except for essential activities or emergency
situations and subject to prior agreement.
High-noise operations (e.g., concrete pouring, turbine component deliveries, crane lifts) will be scheduled
within daytime hours to minimise disturbance.
All deliveries will be coordinated to avoid peak Connolly Meats operational periods where possible.
SITE CONDUCT
All personnel must:
• Follow instructions from the Site Supervisor at all times.
• Stay within designated construction areas.
• Maintain good housekeeping; keep work areas clear of waste and tripping hazards.
• Use personal protective equipment (PPE) as required.
• Avoid unnecessary idling of machinery and vehicles.
• Report any environmental incidents, near misses, or unsafe practices immediately.
• Prevent littering: waste must be placed in designated bins.
• Avoid contamination risks: no refuelling or maintenance outside designated bunded areas. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• Smoking will only be permitted in designated smoking areas.
DO / DON’T
DO:
• Report any sign of pollution or environmental damage, regardless of how small, to the Site Manager.
• Report any spills, incidents, or near misses immediately to the Site Foreman.
• Refuel only in designated, bunded areas.
• Dispose of all waste in the designated skips or bins provided.
• Stick to agreed access routes.
• Follow dust, noise, and sediment control procedures .
DON’T:
• Do not dispose of anything into drains, ditches, or onto land.
• Do not drop litter or allow materials to blow around the site.
• Do not drive plant or machinery outside authorised working boundaries.
IF IN DOUBT, ASK THE SITE SUPERVISOR FOR FURTHER INFORMATION
ENVIRONMENTAL BRIEFINGS
All staff will receive:
• A site environmental induction before starting work.
• Regular toolbox talks, especially before high-risk activities such as excavation, concrete works, or lifting
operations.
• Updates on environmental constraints (e.g., weather -related runoff risks, bat activity periods, fuel
storage controls).
INCIDENT RESPONSE
Any spill, contamination event, dust breach, noise exceedance, or accidental damage to vegetation or
watercourses must be:
• Reported immediately to the Site Supervisor
• Contained using available spill kits or barriers
• Logged and investigated
• Corrective action implemented before resuming works
9. ENVIRONMENTAL RISKS & CONTROL MEASURES
This section identifies the key environmental risks associated with the construction of the proposed wind
turbine and outlines the mitigation measures that will be implemented to ensure protection of the environment,
nearby receptors, and Connolly Meats operations.
Mitigation measures will be applied throughout all phases of construction and will be monitored by the Site
Supervisor and Project Manager.
NOISE
During the construction phase, the potential noise and vibration impacts are associated with site preparation
works, foundation construction activities, construction activities and construction vehicle movements. Similar
to any large construction site, there is potential for noise generation associated with site clearance and
construction activities. Currently, there are no noisy works foreseen outside of normal working hours.
Principal sources of noise will include: RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• Earthworks plant and equipment.
• Construction plant and equipment.
• Construction traffic.
Proposed Noise Control Measures
With regard to construction activities, reference will be made to BS 5228, Noise Control on Construction ad
Open Sites, which offers detailed guidance on the control of noise and vibration from demolition and
construction activities. In particular, it is proposed that various practices be adopted during construction,
including:
• Hours will be limited during which noisy sites activities are permitted.
• Channels of Communication will be established between the Contractor/Developer, Local authority,
and residents.
• A site representative will be appointed responsible for matters relating to the noise.
• Typical levels of noise will be monitored during critical periods and at sensitive locations.
• Plant will be selected with low inherent potential for the generation of noise.
• All site roads will be kept even so as to mitigate the potential for vibration from lorries.
• Barriers will be erected as necessary around items such as generator or high duty compressors.
• Engines, vehicles, and equipment will be switched off when not in use.
• Significant sources of noise will be enclosed.
• Plant will be used and services regularly in accordance with manufacturer’s instructions.
• Machinery having rotating parts will be serviced according to supplier’s recommendations to prevent
friction induced sound.
• Materials should be lowered, not dropped, insofar as practicable and safe.
• All personnel must be made aware that noisy construction activities resulting in significant noise levels
must be minimised and made aware of the above control measures.
DUST
Construction activities have the potential to generate some dust emissions. The potential for dust to be emitted
depends on the type of construction activity being carried out in conjunction with ambient conditions, including
rainfall, wind speed and the distance to potentially sensitive locations. There is potential for dust emissions
from construction activities associates with the construction of the foundations. The contractor shall ensure
dust minimisation plan is prepared and implemented during the construction phase of the project.
Construction activities are likely to generate some dust emissions, particularly during the site clearance and
excavation stages. The following avoidance, remedial or reductive measures will be implemented as part of the
dust minimisation plan:
• During very dry periods when dust generation is likely, construction areas will be sprayed with water.
• Exhaust emissions from vehicles operating within the site, including trucks, excavators, diesel
generators or other plant equipment, will be controlled by the contractor through regular servicing of
machinery.
• Vehicle speeds will be limited in the construction site.
• Surrounding roads used by trucks to access to and egress from the site will be cleaned regularly if
required using an approved mechanical road sweeper. Roads will be cleaned subject to local authority
requirements.
• The technique adopted for all works shall minimise the release of dust into the atmosphere.
LITTER, MUD & HOUSEKEEPING
The following are some of the measures that will be taken to ensure that the site and surroundings are
maintained to a high standard of cleanliness:
• Daily inspections will be undertaken to monitor tidiness.
• A regular program of site housekeeping will be established to ensure a safe an orderly site. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• If necessary, scaffolding will have debris netting attached to prevent materials and equipment being
scattered by the wind.
• Food waste will be strictly controlled on all parts of the site and source separated.
• In the unlikely event that mud is carried over from the project site to the public roads, they will be
cleaned regularly as required and will not be allowed to accumulate.
• Loaded lorries and skips will be covered as required.
• Surrounding roads used by trucks for access to and egress from the site will be inspected regularly and
cleaned, using an approved mechanical road sweeper, when and if required.
• In the event of any waste or materials escaping the site, it will be collected immediately and removed to
storage on site and subsequently disposed of in the normal manner.
SOIL, GROUND WATER & SURFACE WATER PROTECTION
The project site consists of improved agricultural grassland, grazed by cattle. The surrounding area is
predominantly improved agricultural land, with several residential dwellings and agricultural buildings
scattered across the landscape and some areas dominated by scrub. The Maghery stream (EPA code: 36M03)
is the nearest watercourse to the project site, flowing west to east approximately 150m west of the site
boundary. There is various other watercourse within 2km of the proposed site, however they are m inor streams
and are not hydrologically connected to the proposed development site.
The soil profile underpinning the proposed development site and surrounding area is predominantly Surface &
Groundwater Gleys, with some patches of Basin Peats & Blanket Bogs and Alluvium along the watercourses.
The areas of Basin Peats & Blanket Bogs in the surrounding area are mostly covered by scrub consisting of
Gorse (Ulex europaeus) and various grasses and Juncus species.
Proposed control measures
The employment of good construction management practices will minimise the risk of pollution of the soil. The
Construction Industry Research and Information Association (CIRIA) in the UK has issued a guidance noter on
the control and management of water pollution from construction sites. The below mitigation measures
proposes a variety of SuDS measures to prevent sediment or contaminants from entering the waterbody
(Maghery Stream) (See Appendix 2).
The construction management of the site will consider of the recommendations of the CIRIA guidance to
minimise as far as possible the risk of soil contamination. Site activities considered in the guidance note
include the following:
• Excavation
• Earthmoving
• Concreting operations
Measures, as recommended in the guidance above that will be implemented to minimize the risk of spills and
contamination of soils include:
• Where concrete will be poured for the establishment of the foundation, this shall be done by the
contractor under dry conditions and a minimum of 10m away from the drainage ditch.
o It will be prohibited to discharge cement laden water directly into surface waterbodies.
• Silt traps shall be placed along the eastern boundary of the western field of the Proposed Development,
immediately adjacent to the drainage ditch to prevent spillage.
• The level of discharge entering the Maghery Stream shall not exceed 25 mg/l of suspended solids
• During the excavation works, straw bales shall be placed into the drainage ditch which shall be placed
into the drainage ditch adjacent to the excavation works.
• All vehicles and plant will be regularly inspected for fuel, oil, and hydraulic fluid leaks. Suitable
equipment to deal with spills will be maintained on site.
• All vehicles left idle overnight shall have a drip tray placed underneath the vehicle and shall be left a
minimum of 50m away from the southern drainage ditch or waterbody.
• Throughout the duration of the construction phase, silt fencing shall be erected within the width of the
drainage ditch channel shall be placed along the northern section of the drainage ditch adjacent to the
existing access track and one no. at the southern section prior to the drainage ditch running adjacent to RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
the Conolly Meats facility. This shall ensure that no emissions shall run downstream from the proposed
works from the northern fields and ensures that no emissions from the excavation works associated
with the cabling laying will leave the site. An additional silt fence shall be placed 10m from the pipe out
falling into the Maghery Stream.
o All proposed silt fencing shall be inspected on a weekly basis by the main contractor to ensure
they are operating effectively and there are no channels for silt to pass through by the EnvCoW.
o All proposed silt fencing shall be removed once construction activities are completed.
• Where possible, soil excavation will be completed during dry periods and undertaken with excavators
and dump trucks. Topsoil and subsoil will not be mixed.
• All stockpiles of soil and subsoil will, be compacted at the end of the working day and covered during
periods of heavy rain.
• All landscape areas and exposed soil will be reseeded and planted up promptly.
• Construction site runoff from exposed soil or stockpiles will be prevented from running off to the public
road.
• Ensure that all areas where liquids are stored, or cleaning is carried out are in a designated
impermeable area that is isolated from the surrounding area, e.g., by a roll -over bund, raised kerb,
ramps or stepped access.
• Minimise the use of cleaning chemicals.
• Ensure that all staff are trained and follow vehicle cleaning procedures. Post details of the procedures
in the work area for easy reference.
• A Water Sampling Plan shall be implemented and overlooked by the appointed EnvCoW (See
Appendix 1).
• Silt traps shall be fitted into edge of the existing track to the northern end of the drainage ditch. This
shall ensure that phosphorous associated with excavation material will not wash off into the drainage
ditch.
o The main contractor shall be responsible for undertaking daily inspections on the silt trap to
ensure that there is no malfunctioning occurring and overspilling does not occur. The waste
associated with the silt traps shall disposed of by a certified waste collector and disposed of
into a certified waste facility.
o The EnvCoW shall inspect the silt traps and ensure these are operating effectively when they are
completing
The above measures will be implemented, as appropriate along with the following site -specific measures:
• Damaged, leaking, or empty drums will be removed from site immediately and disposed of via a
registered waste disposal contractor.
• Mobile plant will be refuelled in a designated area, on an impermeable base away from drains or
watercourses.
• Any spills during refuelling will be treated with a spill kit.
TRAFFIC MANAGEMENT & CONSTRUCTION TRAFFIC
The construction phase has the potential to impact on the existing traffic regime through the generation of
additional traffic associated with the import/export of building materials, the arrival/departure of operatives,
and various other miscellaneous sources. A traffic Management Plan will be implemented to ensure safe
operation of construction traffic.
Construction Traffic
During the construction phase, vehicular traffic will play a crucial role in facilitating various activities. The
following outline provides insight into the types of vehicles that may be involved:
• Articulated trailer trucks to bring the turbine, electrical/communication cables, steel reinforcement for
the foundation and ancillary equipment.
• Tipper trucks to bring stone to construct access tracks to reach the construction compound and turbine
location.
• Concrete mixers to deliver concrete for the turbine. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• One approximately 80 tonne crane and one 200 tonne crane to erect the wind turbine.
• Miscellaneous vehicles and handling equipment, including vehicles belonging to the construction
workforce.
Potential impacts from construction traffic include temporarily increased local traffic levels and traffic noise
during the construction phase.
Construction traffic on the local road system will be managed in accordance with requirements of the local
planning authority. This may include the installation of road signage and traffic signals as appropriate. Given
the minor levels of construction traffic involved and the short duration of construction activity, traffic impacts
are likely to be negligible.
Transport of large/oversized loads to the wind farm will be executed via the local public roads, as specified in
the site location and transportation plans. Access to the site for wind turbine components will be established
from the Public Road in front of the site, in accordance with the preliminary traffic management plan. The
national and regional road network possesses the necessary specifications to accommodate the wind turbine
components, with the largest dimensions originating from the blades (26m). This size classifies the turbine as
relatively small in the present context.
A comprehensive Traffic Management Plan, will be prepared after permission is obtained and will be prepared
by a specialized company, will be submitted for implementation. This plan will encompass coordination with
pertinent authorities and the formulation of detailed traffic management arrangements. If granted permission,
close collaboration with Monaghan County Council will be established in advance.
For transportation of abnormal loads, a proactive approach will be taken. Agreed timings for such
transportation will be established in coordination with Monaghan County Council, Gardai, and emergency
services. Furthermore, applications for abnormal load permits will be submitted to Monaghan County Council
no less than one week before the intended movement.
10. ECOLOGY: BASELINE & MITIGATION MEASURES
This section outlines the ecological context of the site and the measures that will be implemented to protect
habitats, flora, fauna, and watercourses throughout the construction phase.
The development site consists of improved agricultural grassland located north of the Connolly Meats facility. No
designated ecological sites occur within the development footprint, and no protected habitats will be directly
impacted by the proposed works.
Construction Phase Mitigation
• A project ecologist will be appointed to oversee required works if necessary.
• Measures will be implemented to control dust and prevent silt from entering local watercourses
and drainage channels.
• Stockpiling of loose materials will be kept at least 15 m from watercourses and drainage
channels.
• Silt traps will be put in place near runoff channels to prevent sediment from entering
watercourses.
• Invasive species management plan and biosecurity measures will be implemented.
Protection of Flora and Fauna
There shall be on-going monitoring of wildlife in the vicinity of the construction site, and any unusual species,
dead species or damaged habitats should be reported immediately to the Construction Manager and/or
Environmental Officer. This will be co-ordinated with the appointed Ecologist for the project who will be
responsible for the ecological monitoring on-site. Where unexpected ecological habitats are uncovered the
habitats protection protocol will be adhered to by site contractors. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
This protocol is designed to ensure that ALL persons working on the construction site are fully aware of their
legal obligations under the Wildlife Act 1976, as amended. This Act affords protection to a range of wildlife in
Ireland including wild birds, animals, and plants. Where a project has received permission to proceed, this
does not override certain laws that prevent wilful harm to protected species.
The following is applicable to the proposed development site:
Should the removal of scrub, hedgerow, tree felling or delimbing be required this will be carried out outside of
the bird breeding season (1st March to 31st August inclusive). A pre-works check by a qualified ecologist should
be undertaken to ensure nesting birds are absent.
• All wild birds and their eggs, nests and young, except for certain species, are protected under the
Wildlife Acts. Certain animals including all bat species. Areas of the site found containing nests will be
cordoned off to 20 metres where possible from any nests and all plant and construction will remain
outside of this cordon until the young have fledged (left the nest entirely). The 20 -metre radius will be
centred on the nest site, and each nest would be protected by an equivalent circle. All other areas are
safe for operations. When a 20m buffer zone around active birds’ nests is not possible due to
construction works, alternative mitigation and guidelines will be adopted.
• Surveys of the area have already been carried out to locate where protected species may be living.
• Contractors may discover bat roosts and if any bats are found the works must halt and the NPWS
contacted.
• Sufficient onsite cleaning of vehicles prior to arrival and leaving the site and on nearby roads, will be
carried out as required, particularly during groundworks. Contractor’s vehicles and equipment will be
thoroughly cleaned and then dried using high-pressure steam cleaning, with water >65 °C, in addition to
the removal of all vegetative material as necessary.
• Following cleaning, all equipment and vehicles will be visually inspected to ensure that all adherent
material and debris has been removed manually.
• No removed material or run-off will be allowed to enter a water body of any sort.
• For any material entering the site, the supplier must provide an assurance that it is free of invasive
species.
• Ensure all site users are aware of invasive species management plan, biosecurity, and treatment
methodologies. This can be achieved through “toolbox talks “before works begin on the site.
• Adequate site signage, hoarding and fencing will be erected in relation to the management of non -native
invasive species as required.
• Plant and equipment to be used during works, will be in good working order, fit for purpose, regularly
serviced/maintained, and have no evidence of leaks or drips.
• Weather conditions shall be considered during the construction phase. Works may need to be halted
during or following periods of heavy rain or other conditions likely to lead to large -scale or additional
water flow that would carry soil or silt into the local watercourses.
Procedure for Protection of Potential Bat Roosts
No potential roost sites were identified on -site. Whilst no bat roosts were found, there is a chance that bats
could occupy roosts in the surrounding area prior to the commencement of works. If bat roosts or bats are
found during site clearance, works will cease, and the National Parks and Wildlife Service (NPWS) will be
contacted to avoid an offence being committed by disturbing a bat roost. Works will be suspended if bats are
found to avoid further risk of direct harm to bats.
Procedure for Protection of Avifauna
Where practicable, no clearance of trees on site will occur during the bird breeding season from 1st March to
31st August.
Post construction monitoring measures are recommended regardless of the predicted risk to local bird
population. Standard post construction measures for a development such as this would include fatality
monitoring and possibly flight activity surveys. These measures would be conducted for 2 years post
completion of the development. Fatality monitoring is completed as least once a quarter each year and
consists of walked transects beneath the rotor swept area of the turbine looking for bird carcasses. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Alternatively, the fatality monitoring shall be conducted by carcass detection canines which have been proven
considerably more effective at detecting fatalities. The results of the post construction monitoring shall inform
the likely impacts if the development on the local bird populations. The results will also be relayed to the
appropriate local authorities.
(Further details are provided in the revised Ornithology Report submitted as Appendix C.)
Operational Phase Mitigations
• During the operational period, the wind turbine will operate automatically on a day -to-day basis. The
best means practicable, including proper maintenance of plant, will be employed to minimise the noise
produced by on site operations.
• Yearly bird monitoring to be carried for a minimum of 2 years post construction, but ideally for up to 5
years. This shall be completed by the appointed ECoW.
• Both breeding and winter bird surveys, with particular emphasis placed on Hen Harrier, to be
completed as part of the monitoring. Surveys should include flight activity details (i.e., flight height and
flight paths) of birds observed. This shall be completed by the appointed ECoW.
• Fatality monitoring of the turbine to be conducted at minimum quarterly each year, for a minimum of 3
years post construction. It is recommended that canine fatality monitoring is implemented as canines
have been proven to be significantly more effective a t identifying collision fatalities.
• Monitoring for invasive species should be conducted on a regular basis. Some invasive plant species
may only become establish and appear during the operational phase of the development. Appropriate
measures should be taken to control the invasive species, should they be identified on-site.
• Monitoring of the habitats on-site should be taking a yearly intervals post construction to ensure that
habitats are re-establishing well and without issue.
Decommissioning Process and Site Restoration
Measures will be taken during the decommissioning phase to restore the site to a state like its former condition
or to a condition that is required for the future intended land use. Due to the longevity of the project changes to
habitat and vegetation may occur.
Inspections by an appropriately qualified person will be carried out during decommissioning phase to certify
that the measures detailed in the construction management plan are being implemented effectively and, if
required, removal of materials from the site will be halted and corrective action taken.
Residual Effect
After assessing the impacts of the proposed project all attempts should be made to avoid and mitigate
ecological impacts. The proposed development will not result in the loss or fragmentation of habitats that are
essential to the Conservation Objectives for the Slieve Beagh SPA.
Provided that the recommended mitigation measures set out here and in the NIS (APPENDIX D Figure 1) are
implemented in full, it is not expected that significant impacts will result to the qualifying features identified for
appraisal in this NIS and thus it is not expected that the proposed works will have an adverse impact on the
integrity of the relevant Natura 2000 site(s). Assuming that the mitigations measures are implements accurately
during the construction phase and recommended post-construction monitoring is followed, then it is believed
that there will not be significant residual effects on the receiving environment and the Slieve Beagh SPA
because of the proposed development.
There is no other European site(s) at risk of effects from the proposed development. It has been objectively
concluded, following an examination, analysis and evaluation of the relevant information, including the nature
of the predicted impact from the proposed development, that the proposed development will not adversely
affect (either directly or indirectly) the integrity of the Slieve Beagh SPA or any other European site, either alone
or in combination with other plans or projects, and there is no reason able scientific doubt in relation to this
conclusion.
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
11. OPERATIONAL LIFESPAN OF THE PROPOSED WIND TURBINE
The proposed wind turbine will have an expected operational lifespan of approximately 20–25 years, subject to
ongoing maintenance, technological updates, and manufacturer recommendations. During the operational
phase, the turbine will operate automatically , with periodic inspections to ensure safe and efficient
performance.
ROUTINE MAINTENANCE
Routine maintenance will typically include:
• Scheduled inspections at intervals recommended by the manufacturer (usually bi-annual).
• Servicing of mechanical, electrical and control components.
• Checking tower integrity, access systems, and safety equipment.
• Inspection of cabling, earthing systems, and junction boxes.
• Replacement of consumable parts as needed.
• Lubrication and mechanical adjustments to maintain optimal performance.
Maintenance works will be planned in advance and carried out during daylight hours where possible.
MONITORING DURING OPERATION
Throughout the operational phase, the turbine will be monitored to ensure continued environmental
compliance. This includes:
• Monitoring for any oil leaks, fluid loss or contamination.
• Monitoring of surface water drainage to ensure no operational impacts occur.
• Recording any environmental incidents and ensuring corrective actions are taken.
• Ensuring the turbine continues to meet relevant noise and safety requirements.
SAFETY MEASURES
The turbine will remain fenced or otherwise secured as required to prevent unauthorised access. Warning
signage will be maintained and kept in good condition.
Safety systems incorporated into the turbine include:
• Overspeed protection systems.
• Emergency shutdown mechanisms.
• Lightning protection.
• Automatic fault-response procedures.
OPERATIONAL NOISE MANAGEMENT
Noise produced during turbine operation will be minimised through:
• Proper maintenance of mechanical components.
• Use of manufacturer-specified noise control technologies.
• Prompt repair of any mechanical issue that may increase noise output.
If noise complaints arise, they will be logged, investigated, and addressed as necessary.
ENVIRONMENTAL PROTECTION IN OPERATION
During its operational phase, the turbine will be managed to avoid environmental impacts. Measures include:
• Maintaining setbacks and protection around watercourses.
• Ensuring no operational discharges to land or drainage systems occur. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
• Monitoring the site for invasive species and addressing them promptly if detected.
• Ensuring any vegetation reinstated post-construction continues to establish successfully.
12. DECOMMISSIONING PLAN
An experienced main contractor will be appointed to undertake the decommissioning of the Connolly Meats
wind turbine. All works will comply with the Construction Environmental Management Plan (CEMP) used during
construction and the Operation and Environmental Management Plan (OEMP) applied throughout operation,
including any revisions made during the project lifecycle. The following provides an overview of the expected
decommissioning methodology.
WIND TURBINE REMOVAL
Before any decommissioning works begin, the turbine will be disconnected from the electrical grid by the site
operator in coordination with ESB Networks and EirGrid. The dismantling of a turbine of this scale requires specialist
expertise; wherever possible, this will be carried out by the original turbine supplier.
Large cranes will return to site and operate from the existing hardstand area. As during construction,
dismantling activities will only proceed during suitable weather conditions, particularly avoiding high winds.
Turbine components will be removed from site in a manner similar to the original delivery, using extended
articulated trucks. If early decommissioning occurs, reuse options for turbine components may be explored;
therefore, this decommissioning plan assumes removal of all major components intact.
Transport will follow a dedicated Transport Management Plan, prepared in accordance with the Road Traffic
(Special Permits for Particular Vehicles) Regulations 2007. This plan will include all necessary safety measures
such as convoy arrangements, Garda escort where required, and off-peak turning or reversing movements.
TURBINE FOUNDATIONS
The concrete turbine foundation will not be excavated or removed, as this approach would create unnecessary
environmental disturbance. Instead, the foundation will be covered with locally sourced imported soil, due to the
absence of suitable overburden remaining on-site after construction.
The imported soil will be graded over the foundation using a tracked excavator. The area will be reseeded with an
appropriate seed mix to promote vegetation regrowth and assist the reinstatement of natural drainage patterns.
UNDERGROUND CABLING
Electrical and fibre optic cables connecting the turbine to the substation will be removed from the ducting. A
mechanical winch will extract the cabling, rolling it onto a drum for removal. This process will take place at
each joint bay or pull pit along the cable route.
Localised excavation at each pull pit will be required and will be fully reinstated once works are complete. The
underlying cable ducting will be left in situ, as removing it would cause unnecessary soil disturbance for
infrastructure that is no longer visible or environmentally harmful.
TRAFFIC MANAGEMENT
A dedicated Traffic Management Plan will be prepared for decommissioning, treating it as a standalone project.
A specialist haulier will undertake turbine removal, and all arrangements—including routing, timing, and safety
controls—will be agreed in advance with the competent authority.
While similar to the arrangements for turbine delivery, the plan will reflect the specific requirements of
decommissioning at the time it occurs.
13. PRELIMINARY WASTE MANAGEMENT PLAN
This section of the Decommissioning Plan provides a preliminary waste management plan (WMP) outlining best
practice procedures during the decommissioning of the Wind Turbine. The WMP will detail waste prevention RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
and minimization methods, recycling, recovery, and reuse at each stage of decommissioning. Disposal of
waste will be considered as a last resort.
The Waste Manager on the site will ensure that all contractors hired to remove waste from the site have valid
Waste Collection Permits. Furthermore, waste contractors and receiving facilities must adhere to the
conditions set out in their respective permits and authorizations.
The waste management plan sets out the most efficient way of managing waste in the following order:
Prevention and Minimisation: The primary aim of the WMP will be to prevent and thereby reduce the amount
of waste generated at each stage of the project.
Reuse of Waste: Reusing as much of the waste generated on site as possible will reduce the quantities of
waste that will have to be transported off site to recovery facilities or landfill.
Many construction materials can be reused multiple times before disposal. For example, electrical wiring can
be reused on similar wind energy projects, and elements of the turbine components may be reusable,
depending on their condition and the timing of d ecommissioning.
Recycling of Waste: There are established markets available for the beneficial use of Construction and
Demolition waste, such as utilizing waste concrete as fill for new roads. Throughout the implementation of the
WMP, waste disposal to landfill will only be considered as a last resort. If a certain type of construction material
cannot be reused on-site, recycling becomes the most suitable option. However, the opportunity for recycling
during decommissioning will be limited and restricted primarily to compo nents of the wind turbines. All waste
generated during the decommissioning phase, including dry recyclables, will initially be deposited in on -site
skips, and subsequently sent for segregation at a remote facility. The anticipated volume of waste material to
be generated at the site is low, justifying the adoption of this waste management method.
Waste Arising from Decommissioning: Relevant components will be removed from the site for re-use,
recycling, or proper waste disposal. Structural elements that cannot be recycled will be disposed of
appropriately. All lubrication fluids will be drained and set aside for proper collection, st orage, transport, and
disposal. Materials that cannot be re-used or recycled will be disposed of by an appropriately licensed
contractor. The waste types arising from the decommissioning of the wind farm development incl ude:
• Cables: Electrical wiring
• Metals: Copper, aluminum, lead, and iron
• Fiberglass: Turbine blade components
• Hydrocarbons: Oils and lubricants drained from the turbines.
This Preliminary Waste Management Plan outlines how all waste generated during the construction of the wind
turbine will be managed in accordance with the Waste Management Act 1996 (as amended), the Waste
Management (Collection Permit) Regulations, and all relevant best-practice guidance. The aim is to ensure that
waste is prevented where possible, reused or recycled where feasible, and that all unavoidable waste is
handled, stored, transported and disposed of responsibly.
Only authorised waste contractors will be permitted to remove waste from the site, and all movements will be
recorded and retained for compliance purposes.
14. IMPLEMENTATION OF CEMP
The site supervisor will be responsible for implementing the CEMP on site. The primary means of
implementation will be through contractual obligation – adherence to the construction management controls
will be adopted as a fundamental requirement of all works contracts. To this end, all contractors will be
required to prepare Method Statements (including Risk Assessments and Emergency Response Plans) outlining RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
how they intend to achieve compliance with the CEMP. The Method Statements will require sign off from the
Site Supervisor prior to the commencement of any works. In addition, all relevant personnel will be required to
undergo induction training prior to the commencement of any works to ensure that they fully understand their
obligations. Following commencement weekly meetings will be scheduled to discuss any implementation
issues. Contractual obligation will be supported through the adoption of a culture of environmental
responsibility and all personnel will be expected to always follow good environmental practices.
Monitoring
The Site Manager will be required to implement an Environmental Auditing and Inspection programme which
will include weekly inspection of all construction management controls to ensure their efficacy and proper
working order. Each inspection will be recorded and a log detailing all incidents, the cause of the incidents, and
the associated corrective actions will be maintained.
Non-Compliance
In the event of a non-compliance incident all works will be immediately ceased. The cause of incident will be
investigated and an instruction for corrective action will be issued by the site manager. On completion of the
corrective action the measure will be inspected for effectiveness and, assuming it is in order, will be certified by
the site manager prior to re-commencement of works. The occurrence of a non -compliance incident will
automatically initiate a review of the CEMP.
Review
The CEMP will be subject to on-going review in response to operational activities, variations in the construction
schedule, non-compliance incidents, etc. The results of all reviews will be assessed and, where appropriate,
corrective actions will be undertaken.
Emergency Planning
In accordance with the safety, health and welfare at work act and the safety, health, and welfare at work
(construction) regulation, a site-specific emergency response plan will be prepared and implemented for the
development. In the unlikely event of an emergency the procedures outlined in the CEMP will be followed, and
no action will be undertaken unless it is accordance with the CEMP. All site operatives will be provided with
Appropriate Health and Safety training and personnel protective equipment. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Appendix 1: WATER SAMPLING PLAN
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Section 1: INTRODUCTION
This Water Sampling Plan (WSP) has been prepared to support the Proposed 850kW Turbine project at
Dundrumman (hereinafter referred to as ‘the Proposed Development’) and sets out the procedures for
monitoring surface water before, during, and after constru ction works. The primary objective of the plan is to
ensure that all site activities are undertaken in a manner that prevents deterioration of water quality and
protects downstream receptors.
Wind farm developments have the potential to impact water quality through activities such as earthworks,
track construction, concrete pours, drainage installation, and the use of plant and machinery. This plan
provides a structured framework for identifying potential risks to the water environment, establishing baseline
conditions, and implementing a monitoring regime capable of detecting any changes attributable to the
development.
The Water Sampling Plan outlines the monitoring locations, parameters, sampling frequency, trigger
thresholds, and response actions that will be applied throughout the lifecycle of the Proposed Development.
The WSP is intended to demonstrate compliance with relevant planning conditions, environmental legislation,
and best practice guidance, and to inform adaptive management should exceedances or pollution risks be
identified.
The WSP will be implemented by suitably qualified personnel and integrated with the wider environmental
management and pollution prevention measures for the Proposed Development. The monitoring programme
will remain under review for the duration of the works and shall be updated where site conditions, activities, or
regulatory requirements change.RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Section 2: SURFACE WATER MONITORING
Details of the proposed surface water monitoring during the pre -construction, construction and operational
and decommissioning phases are outlined in the below sections. Due to the low magnitude of impact
anticipated throughout the operational phases of th e Proposed Development as identified in the Water
Framework Directive (WFD) Assessment accompanying this planning application, there is no requirement for a
water monitoring to take place. It shall be the responsibility of appointed contractor to maintain all monitoring
records which shall include water sampling results.
2.1 Appointed Personnel
Prior to undertaking construction activities, the appointed contractor shall appoint a suitably qualified
Environmental Clerk of Works (EnvCoW) of whom shall be appointed prior to construction works and for the
duration of construction works. An EnvCoW sha ll also be appointed for the duration of the decommissioning
phase. The EnvCoW shall be made aware of the monitoring requirements as set out in Section XXX.
The EnvCoW shall:
• Have a suitable environmental qualification - degree in environmental / ecological sciences.
• Have demonstrable experience (minimum of 5 years) in overseeing construction projects; and
• Be a full member of a relevant environmental institute, such as the Chartered Institute of Ecology and
Environmental Management (CIEEM), the Institute of Environmental Management, or equivalent.
The EnvCoW will be delegated sufficient powers under the construction and decommissioning contract so that
they will be provided sufficient powers to halt works and to direct the carrying out of emergency
mitigation/clean-up operations. The EnvCoW is to be notified of any environmental incident and is to sign -off on
any mitigation and remediation measures proposed. The EnvCoW will be responsible for preparing and
producing compliance reports which will be sent to the client and contractor.
2.1.1 Training
All construction workers involved in water sampling will receive appropriate training prior to undertaking any
monitoring activities. Training will be delivered by the EnvCoW and will cover the purpose of the monitoring
programme, the importance of protecting water quality, and the correct sampling methodology. This will
include instruction on selecting safe and representative sampling points, avoiding sample contamination, use
and calibration of field meters, correct sample collection and labelling, completion of field records, and basic
health and safety considerations when working near watercourses. Construction workers must be signed off by
the EnvCoW as being able to effectively take and process water samples prior to undertaking the monitoring
procedure. Refresher training will be provided as required, and toolbox talks shall be used to reinforce good
practice before high‑risk activities or during periods of increased monitoring.
The main contractor shall be involved in taking water samples throughout the construction phase and relevant
data from the water samples shall be sent over to the EnvCoW on a weekly basis. Where the trigger levels as set
out in Table 2 have been exceeded, the EnvCoW shall arrive on site, provide an investigation as where the
breach has occurred. Works will not continue until appropriate mitigation measures have been proposed and
implemented.
2.2 Recording and Reporting
Inspections undertaking by the EnvCoW throughout the inspections shall be recorded by the EnvCoW and shall
be kept on file. These reports shall include a pre-construction report which shall provide details of the current
baseline of the Maghery Stream based on the findings from the samplings RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Where the EnvCoW identifies indicators of pollution, works will halt and a write up will be completed by the
EnvCoW. In this write up, the EnvCoW shall identify the source of pollution and provide suitable mitigation
measures to prevent this. This write-up shall be provided to the client and the contractor. Mitigation measures
must be implemented prior to works commencing. Through monitoring and this open and transparent
reporting, there is a much-reduced likelihood of a small incident becoming a serious po llution occurrence that
may require regulator action.
2.3 Water Sample Monitoring
2.3.1 Water Sample Locations
As there is only on drainage ditch identified as potentially acting as a pathway to a surface water body, two no.
water sampling location is deemed sufficient to identify whether the Proposed Development has potential to
negatively affect surface water bodies. The water sample locations shall be located within the Maghery Stream,
on water sampling location approximately 5m downstream and one no. water sampling location upstream from
where the drainage ditch outfalls into the Maghery Stream (See Figure 1 ). In the event where water levels are too
low, the EnvCoW will be able to take samples further downstream. The EnvCoW can take samples from any
location as long as it is downstream from where the drainage ditch outfalls into the Maghery Stream and must
be close to where the drainage outfalls into the Maghery Stream as practicable. RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Figure 1: Proposed Water Sampling Locations RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
2.3.2 Surface Water Monitoring Schedule
A surface water monitoring schedule for the construction phase of the Proposed Development has been
developed (See Table 1) and outlines the selected parameters with their associated trigger limits (See Table 2),
as well as the frequency of monitoring to be completed prior to, during, and at the decommissioning phase of
the Proposed Development. The discharge is screened primarily against the EPA IPC Licence conditions,
existing baseline conditions as well as the surface water regulations.
Table 1: Surface Water Monitoring Schedule
Parameters Frequency Responsibility
Pre-Construction
Turbidity and visual checks
(examination of surface
drainage/sediment control
measures/watercourses)
One check will be conducted
prior to the commencement of
works.
EnvCoW and the main contractor
pH, Electrical Conductivity,
Turbidity, Temperature (Handheld
Meter)
One check will be conducted
prior to the commencement of
works.
EnvCoW
Conductivity, Chloride, Dissolved
Oxygen, Molybdate Reactive
Phosphorus, Mineral Oil, pH,
Turbidity, Total Ammonia, Total
Phosphorus, Total Suspended
Solids (Grab Samples)
One check will be conducted
prior to the commencement of
works.
EnvCoW
Construction Phase
Turbidity and visual checks
(examination of surface
drainage/sediment control
measures/watercourses)
Daily EnvCoW and the main contractor
pH, Electrical Conductivity,
Turbidity, Temperature (Handheld
Meter)
Monitoring during clearance
phase and construction works at
Turbines
Weekly EnvCoW and the main contractor
Conductivity, Chloride, Dissolved
Oxygen, Molybdate Reactive
Phosphorus, Mineral Oil, pH,
Turbidity, Total Ammonia, Total
Weekly EnvCoW and the main contractor RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Parameters Frequency Responsibility
Phosphorus, Total Suspended
Solids (Grab Samples)
Decomissioning Phase
Turbidity and visual checks
(examination of surface
drainage/sediment control
measures/watercourses)
Daily EnvCoW and the main contractor
pH, Electrical Conductivity,
Turbidity, Temperature (Handheld
Meter)
Monitoring during clearance
phase and construction works at
Turbines
Weekly EnvCoW and the main contractor
Conductivity, Chloride, Dissolved
Oxygen, Molybdate Reactive
Phosphorus, Mineral Oil, pH,
Turbidity, Total Ammonia, Total
Phosphorus, Total Suspended
Solids (Grab Samples)
Weekly EnvCoW and the main contractor
The results of the water sampling conducted during the pre-construction sampling period shall form the
baseline and shall be used to inform the trigger levels as detailed in Table 2
Table 2: Proposed Trigger Values
Parameter Indicative Limits Units Source
pH >4.5 and <9 pH units SI No. 77 of 2019 EU
Surface Water
Environmental
Objective Regulations
Dissolved Inorganic
Nitrogen as N
2.6 mg/l SI No. 77 of 2019 EU
Surface Water
Environmental
Objective Regulations
Chemical Oxygen
Demand
100 mg/l or within
preconstruction values
mg/l EPA Licence limits RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Parameter Indicative Limits Units Source
Total Ammonia 0.14 mg/l or within
preconstruction values
mg/l SI No. 77 of 2019 EU
Surface Water
Environmental
Objective Regulations
Total Phosphorus 0.1 mg/l or within
preconstruction values
mg/l SI No. 77 of 2019 EU
Surface Water
Environmental
Objective Regulations
Total Suspended Solids 35 mg/l or within
preconstruction values
mg/l EPA Licence limits
Total Sulphate 200 mg/l SI No. 77 of 2019 EU
Surface Water
Environmental
Objective Regulations
Conductivity To be informed by pre-
constrcution surveys
µS/cm or within
preconstruction values
µS/cm Based on pre-
construction surface
water quality
BTEX To be informed by pre-
construction sampling
mg/l Based on pre-
construction surface
water quality
Mineral Oil µg/l or within pre
construction values
µg/l Based on pre-
construction surface
water quality RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Section 3: CONCLUSION
Following on from the WSP as outlined above, there will be no risk for the Proposed Development to give rise to
significant negative effects to the water quality of downstream receptors. The measures outlined in the water
sampling plan shall identify at an early stage when a pollution event has occurred. The implantation of the daily
visual check shall provide early warning in the event of any major contamination incidents at an early stage. The
more technical surveys shall identify any slower changes to the water quality that are less serious and not
detectable by eye. This document is a live report which forms the basis of the WSP, however, updates will be
made by the EnvCoW and the main contractor as required and where new findings are identified that req uires
changes to the WSP.RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
Appendix 2: SITE DRAINAGE PLAN
RECEIVED: 26/05/2026
Greenvolt Next
www.next.greenvolt.com
Confederation House, Block C&D, Waterford Business Park, Cork Rd, Waterford, X91T449
RECEIVED: 26/05/2026