HomeMy WebLinkAbout2660160 - F.I. Request Letter
15/06/2026
Meegan Builders (Castleblayney) Ltd
C/O Wayne Douglas
The Mill Building
Newtown Link Road,
Greenhills,
Drogheda,
Co. Louth,
A92 CD3D
Re: Planning and Development Act 2000 (as amended).
Planning and Development Regulations 2001 (as amended).
26/60160 - planning permission for proposed construction of a single storey building with 2 No. light
industrial units and associated 2-storey ancillary office and amenities •The erection of a 2.4m high
boundary wall / fence to the perimeter of site. •Access to the site will be via the existing business
park service road and entrance onto R927 carriageway as previously granted permission (ref: 17/585
and 22/144). •Foul drainage connection to existing pumping station and storm drainage connection
to mains sewer as previously granted permission (ref:17/584, 17/585 and 22/144). •Together with
associated landscaping, retaining walls and all ancillary site works at Cloghvally Lower TD,
Carrickmacross Co. Monaghan.
_______________________________________________________
Dear Sir/Madam,
With reference to the above application, I am to inform you that the information submitted is not
adequate to enable a decision to be made.
In accordance with the provisions of Article 33 of the Planning and Development Regulations 2001
(as amended) you are hereby requested to submit further information as set out on the attached
page.
Article 33(3) states that “where a requirement under sub-article (1) or sub-article (2) (Clarification)
is not complied with within the period of 6 months from the date of the requirement for further
information, or such additional period, not exceeding 3 months, as may be agreed by the Planning
Authority, the planning application shall be declared to be withdrawn”.
It should be noted that you will be required to give notice in an approved newspaper under article
35(1)(a) and erect a site notice in accordance with Article 35 (1)(b) of the Planning and Development
Regulations 2001 (as amended) if the further information received is considered to contain
significant additional data.
Please Note: 4 copies of Additional Information to be submitted. In the case of Significantly
Different Information, 6 copies of additional information to be submitted.
Yours faithfully,
__________________________
ADMINISTRATIVE OFFICER
pp
26/60160 Meegan Builders (Castleblayney) Ltd
Cloghvally Lower TD, Carrickmacross, Co. Monaghan.
ADDITIONAL INFORMATION
Note: A pre-application consultation did not take place.
You and/or your assigned agent should liaise with Planning Section prior to the preparation and
submission of this Further Information.
The submission should take a coherent account of issues that overlap/interlink.
1.
In the interest of clarity and to allow for a fully informed decision, the Planning Authority requires
the submission of a Traffic and Transport Assessment (TTA), including a scoping study, to assess
the impact of the proposed development, in conjunction with permitted and constructed
development within the business park, on the capacity and safety of the surrounding road
network. The TTA shall:
a) quantify anticipated trip generation and cumulative traffic volumes;
b) classify the types of vehicles associated with the proposed use; and
c) demonstrate, by way of layout drawings and vehicle tracking analysis, that adequate parking,
servicing and manoeuvring space is provided within the site.
2.
In the interests of clarity and appropriate design, please submit commensurate details of the
proposed external lighting for the application site, including a lighting layout plan demonstrating
the location and type of lighting within the site. The submission shall demonstrate that lighting
levels are appropriate to the scale of development and that light spill onto the adjoining road
network and surrounding properties is minimised.
3.
To determine the availability and feasibility of connection to public water services infrastructure,
you are requested to engage with Uisce Éireann by submitting a Pre‑Connection Enquiry (PCE) to
assess the feasibility of connection to the public water services network. The outcome of the PCE
shall be submitted to the Planning Authority to allow for a fully informed decision.
4.
The information submitted is insufficient with regards to environmental protection.
Accordingly, please submit the following:
a) Details of the existing/proposed interceptor installed on-site and area draining to it.
b) Outline details of measures to be implemented to protect surface water and groundwater
during the construction phase, including the management of surface water runoff, fuels and
construction materials.
The planner dealing with this application is Ben Clerkin