Loading...
HomeMy WebLinkAbout2560508 - F.I. Received Doc. - Infiltration Rate TestARC DESIGN SERVICES PLANNING CONSULTANTS -SITE SUITABILITY ASSESSORS Mountain Pole,Kells,Co.Meath. Mob:087-9520269 arcdesignservices@gmail.com Infiltration Rate Tests at Tyrone Guthrie Centre,Annaghmakerrig House,Newbliss,Co.Monaghan,H18 PP70 Please find details of a soakaway tests carried out in accordance with BRE Digest 365 on 14/04/2026 1no.test hole was dug on the proposed site in the approximate area where the soakaway will be located. The dimensions of the hole =1.31M X 1.45M X 1.0M deep.The hole was filled with water to a depth of 0.35m below ground level and the time was recorded when water level reached 75% effective depth and also at 25%effective depth. This procedure was carried out as per BRE Digest 365 and the results recorded and the infiltration rate was calculated using the formula below. Soil infiltration rate,f =Vp75 –25 =0.6173 =0.00000502 m/sec ap50 X tp75 –25 1.794 x 68,520 Total Impermeable Roof Area =292.45 m2 All this information was entered into the spreadsheet attached and the size of the soakaways were calculated at Soakaway =11.0M wide,7.0M long and 0.7M below invert level of inflow pipe,30% free volume.Half Empty Time of 22.53 hours Minimum separating distances of 5m from the proposed dwelling and 3m from the boundaries must be achieved.All driveways to be permeable paving/gravel. Where possible,SUDS solutions should be used to lessen the hydraulic loading to the soakaway.Samples of various methods are shown at the end of the report.RECEIVED: 19/06/2026 Design in accordance with BRE Digest 365 TABLE 1 Values of Factor Z1 for rainfall duration D and ratio r Duration Z1 (mm) 10 0.5 I =then Inflow from the impermeable area drained to the Soakaway 15 0.61 O =the Outflow infiltrating into the soil during rainfall 30 0.78 S =the required Storage in Soakaway to Balance temporarily Inflow &Outflow R =the Total rainfall in a Design Storm 60 1 A =the Impermeable area drained to the soakaway 120 1.23 f =the soil infiltration rate determined in a trial pit at the sit of the soakaway 240 1.53 D -the Storm Duration 360 1.73 a50 =the internal surface area of the soakaway to 50%effective depth 600 2.04 (this excludes the base area which is assumed to clog with fine particles and become ineffective in the long term) TABLE 2 30 year rainfall with 20%Climate Change increase Duration M100-D min (mm) 10 15.96 15 18.996 30 24.876 60 30.084 120 37.476 240 46.08 360 54.564 720 66.996 Impermeable Area 292.45 (m2)Soil infiltration 0.00000791 (m/sec) soil type = gravelly clay (m/sec)(m3/sec) (R)Inflow (I) 10 min Rainfall 0.01596 4.67 15 min Rainfall 0.018996 5.56 30 min Rainfall 0.024876 7.27 (I)Inflow =(Impermeable Area)x (Total Rainfall in Design Storm) 60 min Rainfall 0.030084 8.80 (O)Outflow =(a50)x(Soil Infiltration)x (Storm Duration) 120 min Rainfall 0.037476 10.96 240 min Rainfall 0.04608 13.48 360 min Rainfall 0.054564 15.96 600 min Rainfall 0.066996 19.59 RECEIVED: 19/06/2026 Length 11.0 (L)(m)=depth of Soakaway Breath 7.0 (B)(m)=breath of Soakaway Effective Depth 0.7 (D)(m)=depth of Soakaway below invert level of inflow pipe A50 12.6 (as50)(m2)=(Length)*(Breadth)*(2)*(0.5)*(Effective Depth) Effective area 16.17 (Aeff)(m3)=(Length)*(Breadth)*(Effective Depth)*(Void Ratio) Void Ratio for Stone Filling 0.30 min m3/sec m3/sec m3 m3 Duration (D) Inflow (I) Outflow (O) Storage Capacity (S) Excess Storage 10 4.67 5.98E-02 16.17 11.56230 0.17 hour /10Min 15 5.56 8.97E-02 16.17 10.70432 0.25 hour /15 min 30 7.27 1.79E-01 16.17 9.07441 0.5 hour /30 min 60 8.80 3.59E-01 16.17 7.73073 1 hour 120 10.96 7.18E-01 16.17 5.92774 2 hour 240 13.48 1.44E+00 16.17 4.12909 4 hour 360 15.96 2.15E+00 16.17 2.36554 6 hour 600 19.59 3.59E+00 16.17 0.16500 10 hourRECEIVED: 19/06/2026 Location of Test Hole Test Hole Before Filling Test Hole Filled 0.35 below G.L.Test Hole after a period of drainageRECEIVED: 19/06/2026 Location of Test Hole shown by Red Arrow RECEIVED: 19/06/2026 ?118.03 m 117.68 m 116.68 m Existing Paving 115.85 m 115.18 m14439 m² UA Kitchen 12 m² Entrance 5 m² UA WC6 m² UA WC & Shower 4 m² Storage 1 m² El Board 73 m² Recording Studio 101 m² Dance Studio 34 m² Universal Accessible Studio 1 1 m² ST Proposed flower bed 116.50 m 4483925 1700 177 130010001366 1646 7647 Proposed Paved Area Proposed Paved Area 1578 510551965201692221406 m² Entrance/Lobby 8 m² Corridor 18173590 20552560 800mm Door Min Clear Width 180037006000 Accessible Ramp Gradient 1:15 Compliant with Part M 8000Accessible Ramp Gradient 1:15 Compliant with Part M Covered by Pergola structure 150015001600Grass area369915003698150050001800115.85 m 116.68 m 118.03 m 118.03 m 118.03 m 12002191200 1500 2305 1200 1800 7000Proposed Paved Area (Level to Match Existing Paving) 1510 1800 2378• • Stepped Access Route to Comply with Part M: Tactile hazard warning surfaces should be incorporated at both the top and bottom landings (in accordance with Diagrams 4a and 4b) All step nosings should incorporate a permanently contrasting continuous material on the tread 889711127306132983373 110007000 101806810 Proposed Soakaway RECEIVED: 19/06/2026 RECEIVED: 19/06/2026 RECEIVED: 19/06/2026 Raised Planter Example Raised Planter Construction RECEIVED: 19/06/2026 Permeable Paving Cross Section Permeable Paving Specification RECEIVED: 19/06/2026 Water Butt Example RECEIVED: 19/06/2026