Monaghan County Council has by order dated 26/06/2026 decided to GRANT permission to the above
named for development of land, in accordance with the documents submitted namely for:- permission
for the development will consist of the conversion of existing dry/loose livestock handling shed to a
slatted livestock shed with underground slurry storage tank, provision of R.C. walls to part of the shed
and replacement of the existing roof with a new roof together with all ancillary site development works
at Cabragh (D.E.D. Greagh), Castleblayney subject to the 4 condition(s) set out in the Schedule attached.
Signed on behalf of Monaghan County Council
________________________________________
ADMINISTRATIVE OFFICER
___________________________
DATE
Provided there is no appeal against this DECISION a grant of planning permission will issue at the
end of four weeks (see footnote).
NO WORKS CAN COMMENCE ON FOOT OF A ‘NOTIFICATION OF DECISION’ ON AN APPLICATION.
THE DEVELOPMENT IS ONLY AUTHORISED WHEN A ‘NOTIFICATION OF FINAL GRANT’ IS ISSUED.
p.p.
26/06/2026
Footnote:
An appeal against a decision of a Planning Authority under the Planning and Development Act 2000 (as
amended) may be made to An Coimisiún Pleanála, 64 Marlborough Street, Dublin 1, D01 V902. (Tel.
(01) 8588100) during office hours.
1. You have four weeks beginning on the date the planning authority makes its decision which
was (26/06/2026). This is a strict time limit.
2. You must put your appeal in writing (either typed or handwritten).
3. You must clearly state your own name and address. If someone is acting for you, like a planning
agent they must clearly state their own name and address as well as your name and address.
4. You must give enough details to allow An Coimisiún Pleanála to identify the application you
wish to appeal.
5. You must provide your planning grounds of appeal (reasons and arguments) for your appeal
and any items you wish to support your grounds of appeal.
6. If you are a third party, you must include the written acknowledgement given to you by the
planning authority to confirm it received your submission at planning application stage.
7. You must pay the correct fee.
For more information on how to make an appeal see www.pleanala.ie
26/60097 Seamus Mooney & James Mooney, Cabragh (D.E.D. Greagh), Castleblayney,
Co. Monaghan
1.
a) The developer shall pay to Monaghan County Council a sum of €154.00 in accordance with the
General Development Contribution Scheme 2021-2026, made by the Council under Section 48 of
the Planning and Development Act 2000 (as amended), towards expenditure incurred or proposed
to be incurred by the Council in the provision of community, recreation and amenity public
infrastructure and facilities in the area.
b) The sum attached to this condition shall be revised from the date of the grant of planning permission
to the value pertaining at the time of payment in accordance with the Wholesale Price Index for
Building and Construction (Materials and Wages).
c) No works shall commence until payment of the development contribution is made in full, or until
Monaghan County Council has agreed in writing to a schedule of phased payments of the sum.
Reason: It is considered appropriate that the developer should contribute towards the expenditure
incurred or proposed to be incurred by the Council in the provision of community, recreation and
amenity infrastructure and facilities in the area.
2.
a) The development/facility hereby approved shall be operated in accordance with the European
Union (Good Agricultural Practice for Protection of Waters) Regulations, 2025
b) contaminated surface water run-off shall be collected in a sealed system
c) All soiled waters shall be directed to a leak proof storage tank.
d) no effluent or slurry shall discharge or be allowed to discharge to any stream, river, watercourse,
groundwater body or to the public road.
e) All uncontaminated roof water from buildings and yard water shall be separately collected and
discharged in a sealed system to existing drains, streams or adequate soakpits and shall not
discharge or be allowed to discharge to the foul effluent drains, foul effluent and slurry storage tanks
or to the public road.
f) All organic fertiliser generated by the development hereby approved [and existing development
within the farmyard] shall be conveyed through properly constructed channels to the proposed [and
existing] storage facilities and shall not discharge or be allowed to discharge to any stream, river,
watercourse, groundwater body or public road in accordance with the requirements of the
European Union (Good Agricultural Practice for Protection of Waters) Regulations, 2025.
g) All organic fertiliser generated by the proposed development shall be utilised in accordance with the
details submitted to the Planning Authority and in accordance with the European Union (Good
Agricultural Practice for Protection of Waters) Regulations , 2025
h) There shall be no increase in the number of livestock being accommodated at this site unless
otherwise agreed with in writing by the Planning Authority and in accordance with an approved
Farm Nutrient Management Plan.
i) All slatted units, dairy parlours, silage pits and manure storage areas shall be designed and built in
accordance with Department Of Agriculture, Food & the Marine specifications.
j) Any construction and demolition waste or excess soil generated during the construction phase which
cannot be reused on site in accordance with Section 3 (1)(c) and Section 39 (1) of the Waste
Management Act 1996 as amended, shall be disposed/recovered at an appropriately permitted
facility in accordance with the requirements of the Waste Management Act 1996 as amended using
authorised waste collectors authorised to collect the type of material for disposal/recovery at
authorised treatment facilities
k) If infilling material is required to be imported onsite the applicant shall conform to one of the
following;
I. If utilising EPA Article 27 notification to move soil infill material from one site to another.
Official correspondence from the EPA granting approval shall be submitted to the Planning
Authority prior to commencement of development, or
II. If using waste material as infill a valid permit must be issued by Monaghan County Council
under the Waste Management (Facility Permit and Registration) Regulations 2007 as
amended prior to acceptance of material, or
III. If buying topsoil material as a product for final landscaping purposes only,
documentation demonstrating purchase shall be submitted to Planning Authority
prior to acceptance of material.
l) Prior to the commencement of development, the applicant shall submit a site specific Construction
& Demolition Resource Management plan for approval. Applicant shall consider Best Practice
Guidelines for the preparation of Resource & Waste Management Plans for construction and
demolition projects.
m) All waste oils and any other hazardous waste materials shall be stored appropriately and collected,
recovered or disposed of in accordance with the Waste Management Act 1996 as amended, and
records of such shall be kept on site
n) All hazardous liquid waste or oil/fuel storage containers, temporary or otherwise, shall be bunded.
All bunds will be designed to contain 110 % of the capacity of the largest storage container located
within the bund. There shall be no overflow drain facility from any bunds on site and all filling and
off-take points shall be located within a bund
o) Facilities shall be provided for the collection and segregation of recyclable waste. Wastes shall be
collected for recycling/reuse whenever feasible or otherwise disposed of in accordance with the
Waste Management Act 1996 as amended
p) The applicant shall immediately inform the Planning Authority & Inland Fisheries Board of an
accidental spillage of wastewater, organic fertiliser, fuel, machine oil or any other substance which
may threaten the quality of any watercourse or groundwater body.
q) The applicant shall ensure that adequate measures are in place for the construction phase to ensure
there is no discharge of polluting matter/sediment laden waters to any watercourse. These
measures shall take account of the Guidance produced by Inland Fisheries Ireland titled
“Requirements for the Protection of Fisheries Habitat during Construction and Development Works
at River Sites”.
Reason: In the interest of environmental protection and public health.
3.
a) Roofing material shall be dark green, dark grey, dark blue or black in colour.
b) No unpainted metal sheeting shall be used for roofing or on the external finish of the structure.
Reason: In the interest of visual amenity.
4.
The development shall be carried out in accordance with plans and documentation submitted to the
Planning Authority on 18/03/2026, as amended by additional information on 12/06/2026, except as may
otherwise be required in order to comply with the above conditions.
Reason: To ensure a satisfactory standard of development.