HomeMy WebLinkAbout2660219 - Notification of Decision07/08/2026
Ref No: 26/60219
TO: Luke Keenan & Shannon McGee
C/O Patrick Ruxton
Corgreagh
Shercock
County Monaghan
A81 PW32
Re: Planning and Development Act 2000 (as amended)
NOTIFICATION OF DECISION
Monaghan County Council has by order dated decided to GRANT permission to the above named for
development of land, in accordance with the documents submitted namely for:- permission to erect a
two storey dwelling, detached domestic garage, connection to public sewerage, new entrance and all
associated site works at Emy,, Emyvale, Co. Monaghan., subject to the 7 condition(s) set out in the
Schedule attached.
Signed on behalf of Monaghan County Council
________________________________________
ADMINISTRATIVE OFFICER
___________________________
DATE
Provided there is no appeal against this DECISION a grant of planning permission will issue at the
end of four weeks (see footnote).
NO WORKS CAN COMMENCE ON FOOT OF A ‘NOTIFICATION OF DECISION’ ON AN APPLICATION.
THE DEVELOPMENT IS ONLY AUTHORISED WHEN A ‘NOTIFICATION OF FINAL GRANT’ IS ISSUED.
07/08/2026
pp
Footnote:
An appeal against a decision of a Planning Authority under the Planning and Development Act 2000 (as
amended) may be made to An Coimisiún Pleanála, 64 Marlborough Street, Dublin 1, D01 V902. (Tel.
(1)8588100) during office hours.
1.You have four weeks beginning on the date the planning authority makes its decision which
was 07/08/2026. This is a strict time limit.
2.You must put your appeal in writing (either typed or handwritten).
3.You must clearly state your own name and address. If someone is acting for you, like a
planning agent they must clearly state their own name and address as well as your name and
address.
4.You must give enough details to allow An Coimisiún Pleanála to identify the application you
wish to appeal.
5.You must provide your planning grounds of appeal (reasons and arguments) for your appeal
and any items you wish to support your grounds of appeal.
6.If you are a third party, you must include the written acknowledgement given to you by the
planning authority to confirm it received your submission at planning application stage.
7.You must pay the correct fee.
For more information on how to make an appeal see www.pleanala.ie
26/60219 Luke Keenan & Shannon McGee Emy, Emyvale, Co. Monaghan.
1.
a) The developer shall pay to Monaghan County Council a sum of €2,630.00 in accordance with the
General Development Contribution Scheme 2021 - 2026, made by the Council under Section 48 of
the Planning and Development Act 2000 (as amended), towards expenditure incurred or proposed
to be incurred by the Council in the provision of community, recreation and amenity public
infrastructure and facilities in the area.
b) The sum attached to this condition shall be revised from the date of the grant of planning permission
to the value pertaining at the time of payment in accordance with the Wholesale Price Index for
Building and Construction (Materials and Wages).
c) No works shall commence until payment of the development contribution is made in full, or until
Monaghan County Council has agreed in writing to a schedule of phased payments of the sum.
Reason: It is considered appropriate that the developer should contribute towards the expenditure
incurred or proposed to be incurred by the Council in the provision of community, recreation and
amenity infrastructure and facilities in the area.
2.
a) Prior to any other works commencing, visibility splays of 45 metres, measured to the nearside road
edge in each direction, shall be provided from a point in the centre of the entrance 2.4 metres from
the road edge at a height of 1.05 metre to 2.0 metres above ground level to an object height of 1.05
metres to 2.0 metres above ground level in both directions. The visibility splays shall be retained
and kept clear thereafter.
b) Where it is necessary to remove hedges, fences, embankments or other obstructions in order to
achieve the required visibility splays, they shall be reinstated behind the visibility splays. It is
recommended that any new trees or shrubs are planted back from the visibility splays to allow for
future growth, and some species will require additional set back. All existing planting must be kept
trimmed behind visibility splays.
c) Where the existing roadside hedge/embankment is to be removed, the roadside verge shall be
widened (by grading back or infilling where necessary using appropriate inert material) to include
the entire area within the visibility splays, top soiled, and grassed to the satisfaction of the planning
authority.
d) The new entrance shall form a bellmouth of 4.0 metres radius with edge of new boundary. Recessed
entrance shall be of sufficient dimensions to contain a stationary vehicle off the public road.
Entrance gates shall open inwards only.
e) Entrance/access road shall be surfaced with concrete or bitmac from edge of public road for a
minimum of 5 metres and the surface shall be graded back so that its level at 3.0 metres from the
edge of the carriageway is a minimum of 100 mm below road level. Gradient of access road shall be
not greater than 1:20 (5.0%) for the first 5 metres from boundary and 1:10 (10.0%) thereafter.
f) Cattlegrid/ACO Drain/Gullies shall be installed at proposed entrance to the public road and
constructed in such a manner as to prevent water from the entrance flowing onto the public road.
Similarly, measures shall be taken to prevent road surface water from flowing onto the entrance.
The discharge from the above drainage shall be piped to an appropriate drainage pipeline or
watercourse.
g) Provision shall be made within the site for surface water drainage and no surface water to be
allowed flow onto the public roadway. The discharge of surface water from the public road onto the
site through road surface drainage and road subsoil drainage to remain unimpeded.
h) No development exempt or otherwise shall be erected over the public sewer, drain or water-main,
unless otherwise agreed in writing with the planning authority.
i) Before any work is commenced on this development a security, by way of a cash deposit, in the sum
of €2250, shall be paid to the planning authority by the developer to ensure the satisfactory
completion of all surface water drainage/boundary work within and abutting the site area, to
prevent runoff of surface water onto the public roadway and to ensure that no damage is caused to
public roadway and any such damage is repaired satisfactorily. Failure to carry out all entrance
works to a standard to the satisfaction of the planning authority will result in forfeiture of part or all
of the cash security.
Reason: In the interest of traffic/road safety.
3.
a) Prior to the commencement of development, the developer shall contact Irish Water regarding the
provision of water and sewerage services necessary to enable the proposed development and to
confirm acceptability of the proposed development regarding source/network infrastructure.
b) The development within the site in respect of water and sewerage services shall be to standards as
required by Irish Water.
Reason: In the interests of orderly development, public health and securing a satisfactory standard of
development.
4.
The detached garage hereby approved shall be used solely for purposes ancillary to the residential
dwelling within the site area, and not for any separate purposes.
Reason: In the interest of orderly development.
5.
a) Existing mature trees and hedgerow defining the site boundaries shall be permanently retained in
this development. They shall also be reinforced with additional planting as per the submitted
landscaping plan and protected from damage at all times, particularly during building operations.
b) Notwithstanding the submitted landscaping plan, the new site boundaries shall be planted with
native hedgerow species so as to form naturalised hedgerows similar to existing hedgerows in the
vicinity. Predominant species shall be whitethorn, with blackthorn, hazel and holly also included.
Planting shall be in a double staggered row with 8 (eight) 2–3 year-old plants per metre; 250mm
apart, with 300mm between rows.
c) Hedgerow planting, as required, shall be supplemented as per the submitted landscaping plan with
native tree species at irregular intervals. Species shall include ash, oak, sycamore and beech.
d) Planting as required shall be carried out in the first planting season following commencement of
building operations and shall be permanently retained thereafter. Any plant which fails in the first
planting season shall be replaced. Trees shall be allowed to mature and shall not be topped when
trimming hedgerows.
e) Any boundary fencing shall be of stained wood
Reason: In the interest of visual amenity.
6.
a) Ground levels and finished floor levels shall be as detailed on plans submitted to Planning Authority
on 28/05/2026.
b) Any facilitating cut and/or fill shall be graded to a natural contour to reflect the existing topography
of the area.
Reason: In the interests of visual amenity and securing a satisfactory standard of development.
7.
The development shall be carried out in accordance with plans and documentation submitted to the
Planning Authority on 28/05/2026 as amended by further Information submitted to the Planning
Authority on 16/07/2026 and 30/07/2026, except as may otherwise be required in order to comply with
the above conditions
Reason: To ensure a satisfactory standard of development.