Loading...
HomeMy WebLinkAbout2660018 - F.I. Received Doc. - Appropriate assessment screening report Appropriate Assessment Screening Report Proposed Renewable Biogas Plant at Maghernakelly and Drumcall, Drum, Co. Monaghan & Associated Gas Grid Connection Prepared for: Stream BioEnergy Completion Date: August 2026 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment i Table of Contents Table of Figures ............................................................................................................................................................. ii Table of Tables .............................................................................................................................................................. ii Section 1: INTRODUCTION .......................................................................................................................................... 1 1.1 Report Update Following Further Information ........................................................................................................ 1 1.2 Legislative Background ............................................................................................................................................ 2 Section 2: METHODOLOGY ......................................................................................................................................... 3 2.1 Screening Methodology .......................................................................................................................................... 3 2.2 Report Structure ...................................................................................................................................................... 4 2.3 Guidance and Legislation ......................................................................................................................................... 4 2.4 Treatment of Standard Project Design and Environmental Controls at Screening .................................................. 5 Section 3: PROJECT DESCRIPTION ............................................................................................................................... 6 3.1 Site Location ............................................................................................................................................................ 6 3.2 Topography & Drainage ........................................................................................................................................... 8 3.3 The Proposed Development .................................................................................................................................... 9 Operational Phase ..................................................................................................................................................... 9 Construction Phase.................................................................................................................................................. 17 3.4 Planning and Regulatory Context .......................................................................................................................... 18 Section 4: BASELINE CONDITIONS .............................................................................................................................. 19 4.1 Baseline Ecology .................................................................................................................................................... 19 Section 5: STAGE 1. SCREENING FOR APPROPRIATE ASSESSMENT .............................................................................. 22 5.1 Overview of Potential Impacts .............................................................................................................................. 22 5.2 Determining the Likely Zone of Influence .............................................................................................................. 23 5.3 List of Relevant European Sites ............................................................................................................................. 24 5.4 Description of Relevant European Sites ................................................................................................................ 26 5.4.1 Kilroosky Lough Cluster SAC (001786) ............................................................................................................ 26 5.4.2 Lough Oughter and Associated Loughs SAC (000007) .................................................................................... 26 5.5 Screening of Relevant European Sites ................................................................................................................... 28 Section 6: IN-COMBINATION AND CUMULATIVE EFFECTS .......................................................................................... 31 6.1: Assessment Methodology .................................................................................................................................... 31 6.2: Existing and Permitted Plans and Projects ........................................................................................................... 31 6.3: Assessment of Potential In-Combination Effects .................................................................................................. 42 6.4 Conclusion ............................................................................................................................................................. 44 Section 7: SCREENING DETERMINATION .................................................................................................................... 45 7.1 Summary of Screening Findings ............................................................................................................................ 45 Section 8: REFERENCES ............................................................................................................................................. 48 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment ii Table of Figures Figure 1 : Stages of Appropriate Assessment. ................................................................................................................... 3 Figure 2: Regional Site Location ........................................................................................................................................ 6 Figure 3: Site Location ....................................................................................................................................................... 7 Figure 4: Land Drains & Flow Direction ............................................................................................................................ 9 Figure 5: Proposed Development Site Layout ................................................................................................................. 11 Figure 6:Potential Gas Pipeline Route & Grid Connection Point ..................................................................................... 13 Figure 7: European Sites within 15km of the Proposed Development ............................................................................ 25 Table of Tables Table 1: European Sites located within or connected to the ZoI ..................................................................................... 25 Table 2: Screening Assessment of Relevant European Sites ............................................................................................ 28 Table 3: Other projects in the locality (source: eplanning.ie). ......................................................................................... 32 Table 4: Plans associated with the Proposed Development ............................................................................................ 38 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment iii General Details Details of Author(s) Name: Anna Paula Moreira Address: Office 17, Oran Town Centre, Station Road, Oranmore Co. Galway Company name: Veon Ltd. Veon Ecology Tel. no: M: +353 87 607 1539 E-mail: apmoreira@veon.ie Details of relevant qualifications/ affiliations/years of experience B.Sc. (Hons) in Environmental Science University of Galway Over 2 years experience in conducting Phase 1 walkover surveys, mammal surveys, and habitat assessments across a diverse range of projects. Work includes solar farms, wind farms, forestry, and building developments, with a strong emphasis on preserving biodiversity and promoting ecological sustainability in each project. Also proficient in preparing ecological reports and assessments, including Appropriate Assessment (AA) Screening, Natura Impact Statements (NIS), Ecological Impact Assessments (EcIA), and Biodiversity Management Plans (BMP). Describe scope of contribution in preparing this Report • Conducted a Desktop Survey, Phase 1 Habitat Survey, and Ecological Impact Assessment (EcIA) focused on biodiversity. • Undertook Appropriate Assessment (AA) Screening to evaluate potential impacts on Natura 2000 sites. Ensured a robust and comprehensive AA Screening was achieved that adhered to relevant legislation. Veon Ltd. Veon Ecology Revision Description Author: Date Reviewed By: Date Authorised by: Date 1. Draft Report AM 31/03/2024 AH 31/03/2025 PMcK 31/03/2025 2 Author Updates JG 21/11/2025 AH 21/11/2025 PMcK 21/11/2025 3. Final Report JG 28/11/2025 AH 28/11/2025 AH 28/11/2025 4. Final Report JG 26/01/2026 AH 26/01/2026 AH 26/01/2026 5 Final Report – Updated to remove reference to the Soil Relocation Area JG 17/08/2026 AH 17/08/2026 AH 17/08/2026 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 1 Section 1: INTRODUCTION Veon Ltd. (Veon Ecology) were commissioned by Stream BioEnergy Ireland Ltd. to undertake a Screening for Appropriate Assessment (AA) for a proposed renewable biogas plant (‘the proposed development’) and associated infrastructure, at Maghernakelly and Drumcall, Drum, County Monaghan. The proposed project also comprises an associated underground gas grid connection which forms an integral component of the overall project and has therefore been considered throughout this Appropriate Assessment Screening. The proposed development will employ anaerobic digestion (AD) technology to process up to 99,000 tonnes of organic waste feedstocks annually, producing biomethane for injection into the national gas grid, nutrient-rich sustainable fertiliser (as an alternative to synthetic fertilisers), and biogenic carbon dioxide (CO₂) for industrial/commercial applications, thereby supporting Ireland’s decarbonisation objectives. The proposed development constitutes a ‘project’ under the Environmental Impact Assessment (EIA) Directive (2014/52/EU) and is not directly connected with, nor necessary to, the management of any Natura 2000 site. As such, an AA Screening is required under Article 6(3) of the EU Habitats Directive (Council Directive 92/43/EEC) to determine whether the project, individually or in combination with other plans or projects, is likely to have a significant effect on any Natura 2000 (European) site, in view of their conservation objectives. This requirement is transposed into Irish law through Part XAB of the Planning and Development Act 2000 (as amended) and the European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477/2011, as amended). This AA Screening Report has been prepared to assist Monaghan County Council (MCC), the competent authority, in fulfilling its obligations under Article 6(3). It provides objective scientific information to assess whether the proposed development is likely to have a significant effect on European sites, specifically Special Areas of Conservation (SACs) and Special Protection Areas (SPAs). This report presents findings from desk-based studies and field surveys conducted between July 2024 and September 2025, utilising best practice methodologies to evaluate potential effects on European sites within and beyond a 15 km Zone of Influence (ZoI). As such, the European sites of interest to this screening include: • Lough Oughter and Associated Loughs SAC (000007); and • Kilroosky Lough Cluster SAC (001786). The 15 km search radius was used only to identify European Sites for further consideration. The Zone of Influence for individual impact pathways was subsequently refined using the Source–Pathway–Receptor model. 1.1 Report Update Following Further Information This Appropriate Assessment Screening Report has been updated following the Further Information request issued by Monaghan County Council in March 2026 and the subsequent refinement of the Proposed Development. In particular, the Soil Relocation Area previously forming part of the planning application has been removed from the Proposed Development, with surplus excavated soil and stone now proposed to be managed off site at an appropriately authorised receiving facility. The Screening Report has consequently been reviewed and updated to reflect the revised project description and the updated technical assessments prepared as part of the Further Information response, including the Water Framework Directive Assessment, Flood Risk Assessment and the updated Land, Soils and Geology, Water (Hydrology and Hydrogeology), Air Quality and Biodiversity assessments. The assessment of potential source–pathway–receptor linkages and the in-combination assessment have also been reviewed having regard to the revised Proposed Project. The amendments do not alter the conclusion of the Stage 1 Screening that likely significant effects on European Sites can be excluded, either alone or in combination with other plans or projects. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 2 1.2 Legislative Background The Habitats Directive (Council Directive 92/43/EEC) and the Birds Directive (Directive 2009/147/EC, codifying Directive 79/409/EEC) establish the legal framework for the conservation of habitats, species, and birds of European importance. Together, they form the Natura 2000 network, a coherent ecological network of protected sites comprising SACs and SPAs. SACs are designated under the Habitats Directive to conserve natural habitat types listed in Annex I and species listed in Annex II, ensuring they are maintained or restored to a favourable conservation status. SPAs, designated under the Birds Directive, protect bird species listed in Annex I and regularly occurring migratory species, safeguarding their populations and habitats. The features for which these sites are designated are termed Qualifying Interests (QIs) for SACs and Special Conservation Interests (SCIs) for SPAs, collectively referred to in this report as Qualifying Features (QFs). Article 6 of the Habitats Directive outlines the management and protection of European sites. Specifically, Article 6(3) requires: “Any plan or project not directly connected with or necessary to the management of the [Natura 2000] site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subjected to appropriate assessment of its implications for the site in view of the site’s conservation objectives. In light of the conclusions of the assessment of the implications for the site and subject to the provisions of paragraph 4, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appropriate, after having obtained the opinion of the general public.” Article 6(4) provides for derogations in cases where no alternatives exist, adverse effects on site integrity cannot be avoided, and imperative reasons of overriding public interest (IROPI) are demonstrated, subject to compensatory measures. Article 7 of the Habitats Directive extends the requirements of Articles 6(2) to 6(4) to SPAs, ensuring a consistent assessment process for both SACs and SPAs. In Ireland, the Habitats Directive and Birds Directive are transposed, for the purposes of this application, through Part XAB of the Planning and Development Act 2000 (as amended) and the European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477/2011, as amended). The Planning and Development Act 2024 is being commenced on a phased basis. This application and the associated Appropriate Assessment Screening are being progressed under the applicable provisions of the Planning and Development Act 2000 (as amended). Since the proposed development is not directly connected with or necessary to the management of any European site, MCC must determine, using best scientific knowledge and a precautionary approach, whether it is likely to have a significant effect on any European site, individually or in combination with other plans or projects, in view of their conservation objectives. This AA Screening (Stage 1) informs that determination, with the methodology detailed in Section 2. As part of this assessment, Northern Irish Special Areas of Conservation and Special Protection Areas have not been included. This relates to the OPR (2021) which states ‘Transboundary effects relate to the likelihood of significant effects on a site which is part of the Natura 2000 network but lies outside our national boundaries. Since 1 January 2021 nature conservation areas in the UK (including Northern Ireland) are no longer part of the Natura 2000 network.’ These have instead been considered in the Biodiversity chapter as part of the Environmental Impact Assessment Report accompanying this planning application. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 3 Section 2: METHODOLOGY 2.1 Screening Methodology The AA Screening process follows a systematic, evidence-based methodology to identify and evaluate potential impacts on European sites, adhering to Part XAB of the Planning and Development Act 2000 (as amended) and current guidance, including the Office of the Planning Regulator (OPR) Practice Note PN01 (2021) and the Department of Housing, Local Government and Heritage (DHLGH) guidance on Appropriate Assessment (2010, updated 2023). The methodology adopts a precautionary approach, ensuring that potential significant effects are not overlooked, while avoiding premature evaluation of site integrity, which is reserved for a Stage 2 AA (Natura Impact Statement (NIS)) if required, in line with EU case law (e.g., People Over Wind, 2018). The AA process comprises four stages, as outlined in Figure 1: Figure 1 : Stages of Appropriate Assessment. • Stage 1: Screening for AA – Determines whether the project is likely to have a significant effect on a European site, in view of its conservation objectives. • Stage 2: Appropriate Assessment (NIS) – Assesses the implications of the project on the site’s integrity, including mitigation measures to avoid adverse effects. • Stage 3: Assessment of Alternative Solutions – Examines alternatives if adverse effects on site integrity cannot be ruled out. • Stage 4: Imperative Reasons of Overriding Public Interest (IROPI) – Considers compensatory measures if no alternatives exist and adverse impacts remain, subject to IROPI. This screening report focuses on Stage 1, employing the following methodology: 1. Desk-Based Studies: A comprehensive desk study was conducted to identify European sites within a ZoI, initially established as a 15 km radius around the proposed development site, consistent with guidance from OPR Practice Note PN01 (2021). As such, two SACs and no SPAs were identified within this radius: • Kilroosky Lough Cluster SAC (001786): 12.2km northwest; • Lough Oughter and Associated Loughs SAC (000007): 14.8 km southwest; and Data to inform the AA screening were sourced from: • NPWS site synopses, Natura 2000 data forms, and conservation objectives (www.npws.ie); • National Biodiversity Data Centre (NBDC) species records (biodiversityireland.ie); • Environmental Protection Agency (EPA) mapping tools (gis.epa.ie/EPAMaps/AAGeoTool); • Department of Agriculture, Environment and Rural Affairs (DAERA) and Northern Ireland Environment Agency (NIEA) for transboundary sites; and • GIS tools, aerial photography (Google Earth, Bing Maps), and Ordnance Survey Ireland (OSI) mapping. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 4 2. Field Surveys: Ecological surveys were undertaken from July 2024 to September 2025 (including supplementary surveys along the proposed gas pipeline corridor), adhering to best practice guidelines. These surveys assessed the presence of Annex I habitats, Annex II species, and invasive species listed under the European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477/2011) within and in the vicinity of the site. 3. Source-Pathway-Receptor (S-P-R) Model: Potential impacts were evaluated using the Source-Pathway-Receptor (S-P-R) model, identifying sources (e.g., sediment/contaminant run-off, construction/operational emissions), pathways (e.g., hydrological, airborne), and receptors (e.g., QFs of European sites). The assessment covered both construction and operational phases, examining the potential for direct impacts (e.g., habitat loss) and indirect impacts (e.g., water quality changes) on the identified European sites. 4. In-Combination and Cumulative Effects: The screening assessed potential in-combination and cumulative effects with other plans and projects within the ZoI, including permitted developments and proposed plans. Data were obtained from MCC’s planning portal (eplanning.ie) and An Coimisiún Pleanála ensuring a comprehensive evaluation of synergistic impacts. 2.2 Report Structure This report is structured to systematically address the AA Screening requirements: • Section 1: Introduction – Outlines the purpose and legal framework. • Section 2: Methodology – Details the AA screening methodology. • Section 3: Project Description – Details the proposed development, including location, scale, and phases. • Section 4: Baseline Conditions – Presents desk-based and field survey results to establish baseline conditions. • Section 5: Stage 1 Screening for Appropriate Assessment (AA) – Identifies European sites and assesses impacts. • Section 6: In Combination and Cumulative Effects – Assesses the potential for the proposed development to cause significant effects in combination with other projects and plans. • Section 7: Screening Determination– Summarises findings and determines whether there is the need for a Stage 2 AA (or not). • Section 8: References – Lists sources and guidance used to inform this assessment. • Section 9: Appendices – Includes maps, survey data, conservation objectives, and photographs. 2.3 Guidance and Legislation This AA Screening has been prepared in compliance with the following legislation and guidance, ensuring alignment with best practice and legal requirements in Ireland and the European Union: • Legislation: − Council Directive 92/43/EEC on the Conservation of Natural Habitats and of Wild Fauna and Flora (Habitats Directive). − Directive 2009/147/EC on the Conservation of Wild Birds (Birds Directive). − European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477/2011, as amended). − Planning and Development Act 2000 (as amended), Part XAB. − Planning and Development Regulations 2001 (as amended). RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 5 • Guidance: − CIEEM (2024). Guidelines for Ecological Impact Assessment in the UK and Ireland, Version 1.3, September 2024, Chartered Institute of Ecology and Environmental Management. − DHLGH (2010, updated 2023). Appropriate Assessment of Plans and Projects in Ireland – Guidance for Planning Authorities, Department of Housing, Local Government and Heritage. − EC (2013). Interpretation Manual of European Union Habitats, Version EUR 28, European Commission. − EC (2018). Managing Natura 2000 Sites: The Provisions of Article 6 of the ‘Habitats Directive’ 92/43/EEC, Office for Official Publications of the European Communities, Luxembourg, European Commission. − EC (2021). Assessment of Plans and Projects in Relation to Natura 2000 Sites: Methodological Guidance on Article 6(3) and (4) of the Habitats Directive 92/43/EEC, European Commission. − NPWS (2019a). The Status of EU Protected Habitats and Species in Ireland. Volume 2: Habitat Assessments, Unpublished NPWS report. − NPWS (2019b). The Status of EU Protected Habitats and Species in Ireland. Volume 3: Species Assessments, Unpublished NPWS report. − OPR (2021). Practice Note PN01 – Appropriate Assessment Screening for Development Management, Office of the Planning Regulator. 2.4 Treatment of Standard Project Design and Environmental Controls at Screening In undertaking the Stage 1 screening assessment, a distinction has been made between measures intended specifically to avoid or reduce harmful effects on a European Site and standard features or controls which form part of the Proposed Project irrespective of any potential effect on a European Site. In People Over Wind and Sweetman v Coillte Teoranta (Case C-323/17), the Court of Justice held that measures intended to avoid or reduce the harmful effects of a project on a European Site cannot be taken into account at the screening stage. In Eoin Kelly v An Bord Pleanála [2019] IEHC 84, the High Court subsequently considered the application of this principle to Sustainable Urban Drainage Systems and distinguished standard environmental measures which are not intended to avoid or reduce harmful effects on a European Site from mitigation measures introduced for that purpose. This distinction is also reflected in the Office of the Planning Regulator Practice Note PN01, which identifies the objective purpose of the measure as the relevant consideration. The position was further considered by the Court of Justice in Eco Advocacy CLG v An Bord Pleanála (Case C-721/21), which confirmed that Article 6(3) does not preclude account being taken at screening of features incorporated into the project as standard features irrespective of any effect on the European Site concerned. The Renewable Biogas Plant incorporates a range of engineering and environmental control features which are inherent components of the development and would be required irrespective of the presence or absence of any European Site. These include the engineered surface water drainage system, Sustainable Drainage Systems, attenuation and surface water treatment infrastructure, controlled discharge arrangements, impermeable process areas, bunded storage and secondary containment, sealed process drainage and containment of process liquors. These features arise from the functional requirements of the plant and from generally applicable engineering, drainage, pollution-control and regulatory requirements. They have not been introduced for the purpose of avoiding or reducing an effect on any European Site. Similarly, construction of the Proposed Project will be undertaken in accordance with generally applicable statutory requirements and established construction-industry good practice. Relevant guidance includes CIRIA C532, C648, C649 and C811 and the applicable guidance for the protection of waters during construction. The environmental controls arising from such guidance comprise standard construction practices which would apply to the works irrespective of the presence of any European Site and have not been introduced in response to the identified downstream hydrological connection. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 6 No additional or site-specific mitigation measure introduced for the purpose of avoiding or reducing a harmful effect on a European Site has been relied upon in reaching the Stage 1 screening determination. Section 3: PROJECT DESCRIPTION 3.1 Site Location As shown on Figure 2, the proposed development is located at Maghernakelly, Drum, County Monaghan. Figure 2: Regional Site Location The site lies approximately 4.2 km northwest of Cootehill, 11.2 km southeast of Clones, and 17.5 km south of Monaghan Town. It is accessible via the R189 regional road, which connects to the N54 at Monaghan Town to the north and the R188 at Dawson Grove Demesne near Cootehill to the south. As shown on Figure 3, the proposed development site spans approximately 6.2 hectares (ha) and is located across two separate fields, which are predominantly covered by improved grassland (GA1) and bordered by maintained hedgerows (WL1) with gorse (Ulex europaeus), hawthorn (Crataegus monogyna), blackthorn (Prunus spinosa), holly (Ilex aquifolium), and bramble (Rubus fructicosus agg.). The actively grazed and cut for silage grassland features perennial ryegrass (Lolium perenne), Yorkshire fog (Holcus lanatus), and weeds such as nettle (Urtica dioica), dock (Rumex obtusifolius), and creeping buttercup (Ranunculus repens). The fields are separated by an overgrown hedgerow, interspersed with a mix of tree species (WL2), such as hawthorn (Crataegus monogyna), holly (Ilex aquifolium), goat willow (Salix caprea), gorse (Ulex europaeus) and beech (Fagus sylvatica). The site is bordered on three sides by maintained hedgerow, with gated access from the adjacent public roads, which create disturbance in terms of severance, noise, threat, etc, potentially limiting ecological value. These roads are: • R189 which contains the eastern boundary of the proposed development site; • L2280 Drumcall Road which contains the northern boundary of the proposed development site; and RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 7 • L22802 (McKeever’s Road) which contains the western boundary of the proposed development site. Moreover, the hedgerow is cut back and gappy which further reduces the ecological value of the existing hedgerow and limits its value as a movement corridor for small mammals, bats and birds. Moreover, as the hawthorn is cut back it will limit the hawthorns ‘ability to produce fruit and flowers. Immediately south of the proposed development site is an adjacent farmyard/farmhouse and residential property (classified as built land (Fossitts Habitats Code: BL3)) separated by ditches (FW4) and hedgerow (WL1), interspersed with a number of mature trees (WL2). The site forms part of an agri-business unit associated with this farm and residential property, all forming part of the same overall land holding. Figure 3: Site Location Given the topography of the proposed development site (as detailed further below), an excess of fill material will be generated during construction works. Whilst a large portion of excess soil will be repurposed as fill material for landscaping within the proposed development site, an estimated 18,600 m³ of surplus excavated material that cannot be reused on-site will be removed by suitably authorised contractors to an appropriately licensed soil recovery facility or other authorised receiving facility, in accordance with the Waste Management Acts and all applicable waste legislation. The wider area is generally characterised by farmland consisting of improved agricultural grassland separated by hedgerows and interspersed with lakes, drumlin terrain, low-lying areas of poor drainage, individual residences and farm properties and small woodland copses. Larger forestry plantation can be found further to the east. A wetland RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 8 habitat consisting of fens, wet grasslands, reed swamp and scrub located approximately 195 m to the east of the proposed development site1. 3.2 Topography & Drainage The topography of the proposed development site slopes gradually from the adjacent local roads to the northeast and west, then rises steeply towards a high point to the south (close to the adjacent farm property). The highest elevation is in the south-west at 111.75 m Above Ordnance Datum (mAOD) and lowest elevation in the north-east at 90.00 mAOD. The topographical data indicates natural drainage towards the north-east. As shown on Figure 4, a land drain along the northern field boundary of the proposed development site conveys surface water runoff via a culvert under the R189 into another land drain. These drains are hydrologically connected to the Coolkill Lough Stream, which rises to the northeast of the L2320. The culvert is a 450 mm diameter pipe with the invert level raised above the level of the receiving downstream ditch, creating impassability issues for local wildlife (due to its height above ground and diameter). A number of land drains (FW4) are also aligned along the eastern and western field boundary of the proposed development site, separating it from the adjacent local road network. A ditch also runs through the central hedgerow on the proposed development site, connecting with the land drain aligned along the eastern field boundary. As such, all land drains convey field drainage / surface run-off to the land drain running to the north the proposed development site and draining to the east. No natural watercourses occur within or immediately adjacent to the proposed development site, with surface water drainage currently provided by a network of agricultural land drains. As part of the proposed development, existing drainage arrangements within the site will be replaced by an engineered surface water management system incorporating attenuation and treatment measures, as described in the accompanying EIAR and drainage strategy, as detailed within the Engineering Services Report. The floodmaps.ie web portal indicates that the proposed development site or the surrounding area is not at risk of flooding in any of the available modelled scenarios. This is the conclusion of the Flood Risk Assessment which accompanies this application and can be located in Volume III of this EIAR. The accompanying Flood Risk Assessment concludes that the proposed development site is not at risk of flooding under any of the modelled scenarios, and there is no evidence of significant historical flooding affecting the site. 1 Available at: https://wetland.maps.arcgis.com/apps/View/index.html?appid=e13b75c3bcab4932b992aa0169aa4a32&extent=- 12.6266,51.3236,-3.2168,55.4102 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 9 Figure 4: Land Drains & Flow Direction 3.3 The Proposed Development The proposed development comprises a renewable biogas plant and associated underground gas pipeline connecting the facility to the national gas network. The project also includes all associated infrastructure including access roads, drainage infrastructure, attenuation systems, utilities, landscaping, lighting, process buildings, tanks, storage infrastructure and ancillary works necessary for construction, operation and maintenance. Operational Phase The proposed development will utilise AD technology to generate renewable energy in the form of biomethane from up to 99,000 tonnes of feedstock per annum consisting of poultry manure, cattle manure, and agri-food organic waste feedstock, sourced from the surrounding area. This will be achieved through a state-of-the-art, highly regulated facility incorporating advanced technologies and abatement systems to mitigate the potential for adverse impacts on the environment and human health. Key features in this regard will include enclosed handling of all materials within sealed buildings / tanks, multi-stage odour treatment, noise containment, and engineered site drainage. The process is illustrated and described below RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 10 The AD process can be broadly divided into the following four main stages: • Feedstock Reception and Pre-Treatment: Organic waste feedstocks are delivered to the site, stored in enclosed reception areas, and pre-treated to optimise digestion. • AD Treatment: Pre-treated feedstocks are fed into anaerobic digesters, where micro-organisms break down the material over several weeks, producing biogas (primarily methane and CO₂). • Post-Treatment (following Digestion): The resulting digestate is separated into solid and liquid fractions, with solids processed into fertiliser pellets and liquids recirculated. • Energy Generation and Use: Biogas is upgraded on-site to biomethane and injected into the national gas grid via a nearby connection, replacing fossil fuel-derived natural gas and contributing to Ireland’s renewable energy targets under the Climate Action Plan 2025. Combined Heat and Power (CHP) units utilise a portion of the biogas to generate electricity and heat for on-site use. The AD process primarily produces: • Nutrient-Rich Digestate: A biofertiliser suitable for use in agriculture and horticulture as a sustainable alternative to synthetic fertilisers, reducing reliance on chemical inputs. • Biogenic Carbon Dioxide (CO₂): Captured during biogas upgrading for industrial applications, such as food processing or greenhouse cultivation, replacing CO₂ derived from fossil fuel-intensive processes and supporting decarbonisation efforts. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 11 Figure 5: Proposed Development Site Layout The site layout of the proposed development is provided on Figure 5, comprises a number of integrated elements including: • 1 - Administration Building (with associated surface level car parking); • 2 - Main Process Building (with associated vehicle service areas); • 3 - Odour Control System (with associated emission stack); • 4 - Bunded Tank Farm (accommodating the vast majority of tanks that require containment and other plant); • 5 - Digestate Treatment Plant (Evaporator); • 6 - Digestate Drying Plant; • 7 - Pellet Hall (for fertiliser storage); • 8 - Combined Heat and Power (CHP) Building (accommodating two CHP engines); • 9 - Boiler Unit; • 10 - Shared Emission Stack (for exhaust connection to the Digestate Drying Plant, CHP engines and Boiler); • 11 - CO2 Liquefaction Plant; • 12 - Biogas Upgrade Plant (BUP); • 13 - Biogas Treatment Plant (Biological De-sulphurisation Units); • 14 - Gas (Holder) Buffer Dome; RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 12 • 15 - Weighbridges and Wheel Washes; • 16 - Liquid Feedstock Storage Tanks (silos); • 17 - Backup Gas Flare; • 18 - Fuel Storage Tank; • 19 - Gas Grid Entry Unit; • 20 - Fire Water Storage Tank; • 21 - Liquefied Petroleum Gas (LPG) Storage Tanks (Propane); • 22 - Freshwater Storage Tank (Underground); • 23 - Staff and Visitor Parking; • 24 - Control Building; • 25 - Plant Room; and • 26 - Back-Up generator. Other integrated elements, though not numbered on Figure 5 include: • Internal road and footway provision; • Engineered stormwater drainage system; • Landscaping and Earthworks; • Lighting; • Fencing and security gates; and • Site entrance/exit off the L2280 Drumcall Road with gated frontage. This shall include localised widening and realignment of this road and reconfiguration of the junction with the R189. In general, the operational phase will involve regular vehicle movements (e.g., HGVs for feedstock delivery and by - product distribution), air emissions from the CHP units / boiler / dryer, noise from plant operations, minimal surface water discharge due to rainwater harvesting, no release of wastewater (being recirculated to the process) and appropriate site wide containment measures, including a bunded area designed in accordance with CIRIA requirements. The plant will operate under an Industrial Emissions Licence (IEL) issued by the EPA under the Environmental Protection Agency Act 1992 (as amended). The IEL will impose stringent regulatory controls, including emission limits, environmental performance reporting requirements, and regular EPA inspections, ensuring compliance with national and EU environmental standards (e.g., Industrial Emissions Directive 2010/75/EU). Stream BioEnergy is committed to proactive monitoring and collaboration with regulatory authorities to maintain the highest operational and environmental standards. The proposed development incorporates a number of permanent engineering and environmental protection measures that form integral components of the project design. These include: • enclosed feedstock reception; • sealed digestion process; • enclosed digestate handling; • impermeable process yards; • engineered surface water drainage; • attenuation and treatment systems; • spill containment; • bunded storage; • odour treatment including biofilter; • sealed process drainage; and • contained process liquors. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 13 These features form part of the proposed development as designed and have therefore been considered throughout this Appropriate Assessment Screening. As detailed above, biogas generated by the proposed development will be upgraded on site to biomethane and injected to the gas grid (approximately 3.5 km south of the site) to replace fossil fuel derived natural gas (see Figure 6). Figure 6:Potential Gas Pipeline Route & Grid Connection Point The Proposed Project requires an approximately 3.5 km Linear Gas Grid Connection to facilitate the injection of biomethane into the national gas network. The Linear Gas Grid Connection does not form part of the planning application for the Renewable Biogas Plant and will be delivered separately by Gas Networks Ireland under the RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 14 applicable statutory consenting process. However, it forms part of the overall Proposed Project and has therefore been considered throughout this Appropriate Assessment Screening. Its features include: • installed within existing road corridor; • localised temporary works; • HDD beneath sensitive crossings where required; • no instream works; • reinstatement of disturbed areas; • no direct interaction with European Sites; • no new operational emissions. Digestate Management The proposed development does not include the land spreading of digestate. Digestate is a product of the anaerobic digestion process. It is intended that digestate generated from the proposed development will be made available for supply to third party landowners and occupiers for use as a biofertiliser. Land spreading of digestate produced at the proposed development is, therefore, considered a reasonably foreseeable indirect activity associated with the future operation of the facility, and has been considered accordingly within this assessment. Digestate produced will be pumped to the pasteurisation tanks for treatment in a batch manner to the appropriate Transformation Standard. Compliance with the Animal Byproduct Regulations (ABP) requires pasteurisation at 70ºC for one hour, with a particle size of <12mm (similar to the PAS110 Certification Scheme in operation in the UK). The plant will include temperature monitoring equipment and a reporting package for proof of batch time and temperature to demonstrate achievement of the ABP sanitisation requirements. The quality of digestate leaving the site will be controlled in accordance with the standards specified in the EPA IE licence and the requirements of a permit issued by DAFM under ABP Regulations and will be certified as a non-waste where it complies with these quality standards. These standards are established to ensure no direct or indirect adverse impacts on human, animal or plant health and to prevent environmental pollution. In this way the environment will be afforded full protection and the application of digestate will not give rise to nutrient imbalances. The application of digestate to land as a fertiliser is not part of the proposed development, but rather is considered an indirect activity regulated by an entirely separate and evolving regulatory framework that provides for the effective management of land spreading of fertilisers to avoid and minimise any associated environmental risks to land and soils, to water quality and aquatic habitats, and to air quality, including the following: • The Nitrates Directive (91/676/EEC), as transposed into Irish law by the Good Agricultural Practice for Protection of Waters Regulations (S.I. No. 113 of 2022, as amended by S.I. No. 393 of 2022, S.I. No. 716 of 2022, S.I. 62 of 2023, S.I. 42 of 2025, and as may be further amendment from time to time); • The 2025 Nitrates Derogation Terms and Conditions (where applicable); • The DAFM Code of Good Agricultural Practice for Reducing Ammonia Emissions from Agriculture; and • Inland Fisheries Ireland’s Code of Practice for the Protection of Waters. Collectively and together with other programmes and measures implemented by DAFM, the EPA and Inland Fisheries, among others, landowners and occupiers are subject to stringent regulatory controls on nutrient management including timing, application rates, buffer zones, and prohibited spreading periods, designed to protect inter alia water and air quality, and aquatic and coastal habitats (referred to in this EIAR as ‘Good Agricultural Practice’). Furthermore, relevant local authorities have water quality testing and reporting obligations. These regulatory controls require that any fertilisers (including digestate) must be applied to land in a manner that will not cause environmental impact. Protective measures include: • Maximum nutrient application rates; • Prohibited spreading periods (e.g. during winter months); RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 15 • Minimum buffer distances from watercourses, wells, and karst features; • The use of low emission spreading techniques; • Requirements for soil condition and weather suitability; • Record-keeping and nutrient management planning; and • Additional environmental protection for aquatic ecosystems, particularly in proximity to sensitive surface water bodies. Local nutrient imbalances will not occur when this product is applied to land as landspreading of digestate must be undertaken by farmers in accordance with nutrient management planning in order to comply with the requirements of the Nitrates Directive. Compliance by landowners and occupiers is achieved through systematic planning, reporting, inspection, testing, and regular compliance review requirements prescribed by the Good Agricultural Practice framework. A long term digestate offtake agreement is in place with a local specialist agricultural contractor and agronomist who will be responsible for the transfer and spreading of digestate in accordance with all relevant regulations and guidance. Landowners are required to demonstrate annually through nutrient management planning that proposed landbanks for landspreading have a requirement for the nutrients contained in the materials applied to the land. Stream will ensure that digestate meets relevant quality standards when it leaves the biogas plant and will provide digestate quality reports detailing nutrient content to the agronomist and farmers to allow nutrient management plans to be prepared at the appropriate time. This will ensure proper and compliant management and controls in accordance with applicable regulations and good practice guidance for digestate spreading. As part of the digestate offtake agreement, arrangements will be put in place with local farmers to provide sufficient storage capacity for digestate during the prohibited spreading period, as per established successful practice at other biogas plants operated by Stream. Digestate will only be supplied to farms with sufficient storage capacity to satisfy relevant agricultural good practice. The application of digestate to land is not part of the proposed development and is a separate and distinct activity subject to its own set of independent rules and regulations which are the responsibility of the landowner2,3 As the Court of Appeal held in an AA context in Sweetman v ABP [2025] IECA 49, the relevant competent authority (in that case, the EPA) was obliged to conduct an AA for the proposed activity for which consent was required (in that case, an EPA licence for the on-site activity) and found no likely significant effects on European sites. The competent authority was not required to undertake a further assessment of off-site land spreading of by-product from the proposed activity (fertiliser), as the application of fertiliser to third party lands did not form part of the project for which the consent was sought. In reaching this decision, the High Court and Court of Appeal had regard to the Supreme Court’s reasoning in An Taisce v An Bord Pleanála [2022] IESC 8 (‘Kilkenny Cheese’). “Fundamentally, what was required to be assessed in the Kilkenny Cheese Factory case was the “project”; in this case the “activity” being licensed. This is the notice party’s installation lands and not any other lands on which poultry litter and wash water might be spread. It would seem to me that this principle must hold good, regardless of whether one is concerned with upstream or downstream activities, and regardless of the number of potential upstream or downstream premises engaged in such activities. Even though the number of farms or spread lands might be more limited or defined than in the Kilkenny Cheese Factory case, as a matter of principle, the obligation exists, or it does not. What is of relevance in each case is the activity being licensed or authorised.” By analogy with the EIA requirements under the Planning and Development Act 2000, as amended, in Kemper v An Bord Pleanála [2020] IEHC 601, the High Court considered that the land spreading of biosolids was a foreseeable and integral part of the proposed waste water treatment system, but that any assessment of the environmental effects of 2 Kemper v An Bord Pleanála [2020] IEHC 601 3 An Taisce v An Bord Pleanála [2022] IESC 8 RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 16 such land spreading was not reasonably practicable the specific lands where the biosolids would be spread would only be known after the project was operational and customers came forward, and because land spreading is separately regulated under the Good Agricultural Practice framework (see below). Digestate is a product of the anaerobic digestion process. Digestate generated from the proposed development will be made available for supply to third party landowners and occupiers for use as a biofertiliser. Land spreading of digestate produced at the proposed development is, therefore, considered a reasonably foreseeable indirect activity associated with the future operation of the facility. However, it is not the activity for which consent is sought, nor does it fall within the scope of the proposed development for which an AA Screening is required to be undertaken. Stream will ensure that digestate meets relevant quality standards when it leaves the biogas plant and will provide digestate quality reports detailing nutrient content to allow nutrient management plans to be prepared at the appropriate time. This will ensure proper and compliant management and controls in accordance with applicable regulations and good practice guidance for digestate spreading. The future operator of the proposed development will not have operational, contractual, regulatory or financial control over any individual third party landowner or operator that proposes to use biofertiliser from the proposed development on their landholding. Furthermore, use of fertilisers by third party landowners or occupiers on agricultural land is regulated under several existing, generally applicable and binding environmental frameworks, including the following: • The Nitrates Directive (91/676/EEC), as transposed into Irish law by the Good Agricultural Practice for Protection of Waters Regulations (S.I. No. 113 of 2022, as amended by S.I. No. 393 of 2022, S.I. No. 716 of 2022, S.I. 62 of 2023, S.I. 42 of 2025, and as may be further amendment from time to time). • The 2025 Nitrates Derogation Terms and Conditions (where applicable). • The DAFM Code of Good Agricultural Practice for Reducing Ammonia Emissions from Agriculture • Inland Fisheries Ireland’s Code of Practice for the Protection of Waters. Collectively and together with other programmes and measures implemented by DAFM, the EPA and Inland Fisheries, among others, landowners and occupiers are subject to stringent regulatory controls on nutrient management, including timing, application rates, buffer zones, and prohibited spreading periods, designed to protect inter alia water and air quality, and aquatic and coastal habitats (referred to in this EIAR as ‘Good Agricultural Practice’). Furthermore, certain plans, projects and activities are subject to regulatory requirements and controls under the European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. 477 of 2011, as amended) (‘Habitats Regulations’) and the Wildlife Act 1976, as amended (‘Wildlife Acts’). The relevant competent authorities under the Good Agricultural Practice framework include DAFM and the EPA, while relevant local authorities have water quality testing and reporting obligations. Compliance by landowners and occupiers is intended to be achieved through systematic planning, reporting, inspection, testing, and regular compliance review requirements prescribed by the Good Agricultural Practice framework. The relevant competent authority for the purposes of activities requiring consent under the Habitats Regulations and the Wildlife Acts is either the relevant decision-maker under the applicable consent regime for the proposed plan or project, or Minister for Housing, Planning and Local Government (‘NPWS’) for activities requiring consent (‘ARC’) under the Habitats Regulations. The appropriate management of land in accordance with Good Agricultural Practice, the Habitats Regulations and the Wildlife Acts is the responsibility of each individual third party landowner and occupier, under the regulatory supervision of DAFM and the EPA, primarily. Accordingly, the use of digestate on land is subject to an entirely separate and evolving regulatory framework that provides for the effective management of land spreading of fertilisers to avoid and minimise any associated environmental risks to terrestrial and aquatic habitats, species and animals. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 17 Consequently, it falls outside of the scope of the AA Screening of the proposed development. Notwithstanding the above, for the sake of completeness the land spreading of digestate is considered in this AA Screening as an activity that could theoretically result in indirect effects on European sites, such as: • Nutrient enrichment of sensitive habitats due to surface water run-off or groundwater contamination; • Disturbance of qualifying species (e.g. bird species in SPAs, or aquatic species in SACs) if spreading occurs in or near sensitive foraging areas. It is noted, however, that all landowners and occupiers proposing to use fertiliser on agriculture land, irrespective any potential interaction with a European site, are required to comply with the Good Agricultural Practice framework, including their site-specific nutrient management plan. All such landowners and occupiers are further required to comply with the Habitats Regulations and the Wildlife Acts, insofar as applicable. Provided all such landowners and occupiers comply with these binding requirements, which may be revised or updated from time to time to ensure compliance with European law, the use of digestate from the proposed activity is unlikely to have a significant effect on a European site. Furthermore, no significant indirect or cumulative impacts on European sites are anticipated, provided that digestate application adheres to these established and legally binding generally applicable environmental protection measures, including: • Maximum limits on nitrogen and phosphorus application rates; • Prohibited spreading periods (e.g. during winter months); • Minimum buffer (set-back) distances from watercourses, wells, and karst features; • Exclusion of areas (including European sites) that could result in run-off to sensitive aquatic habitats; • The use of low emission spreading techniques, • Requirements for soil condition and weather suitability (e.g. avoiding wet and frozen conditions); • Record-keeping and nutrient management planning; • Prohibition of activities that could cause or permit the spread of specified invasive plants or animals, per the Habitats Regulations and Wildlife Acts. The NPWS further regulates any ‘activities requiring consent’ of the Minister under the Habitats Regulations, where such activities are not otherwise subject to a development consent process under the Planning and Development Act 2000, as amended, or any other statutory provision listed in Schedule 2 of the Habitats Regulations. All other plans or projects likely to have a significant effect on a European site are subject to a separate consent process, either under the Planning Acts (if applicable) or under one of the other Acts listed in Schedule 2 of the Regulations. In all of the circumstances, the AA Screening of the proposed development may exclude beyond a reasonable scientific doubt the likelihood of significant effects on any European site arising from the indirect off-site activity of land spreading of biofertiliser that will be produced by the proposed development when operational, on the basis that any such effect is too remote, is not known or ascertainable, and is the subject of a separate and independent regulatory framework. Construction Phase The Proposed Development will require earthworks (cut and fill) to establish suitable levels for the integrated elements necessary for the plant's operation. A temporary construction compound will also be established during this stage, including welfare facilities, material storage and site offices. These facilities will be contained within the proposed development site. It is anticipated that not all surplus excavated material can be reused on-site and any excess material will be removed by suitably authorised contractors to an appropriately licensed soil recovery facility or other authorised receiving facility in accordance with the Waste Management Acts and all applicable waste legislation. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 18 Vegetation clearance, where required, will comprise: • topsoil stripping of grassland; • removal of the tree-lined hedgerow located through the centre of the proposed development site; • removal of the hedgerow along the L2280 to accommodate the partial realignment of this road and visibility splays from the proposed development junction; and • removal of a section of hedgerow along the R189 to accommodate the modified junction visibility splay. Construction will include earthworks, reinforced concrete works, tank installation, structural steel erection, building construction, installation of mechanical and electrical equipment, road and hardstanding construction, landscaping and commissioning. Landscaping will be implemented at the earliest practicable stage, with priority given to the site boundaries and the proposed landscape berms along the south-eastern and north-western portions of the site. Construction activities will be undertaken in accordance with best practice environmental management measures and the Construction Environmental Management Plan, including appropriate controls for surface water management, sediment control, dust suppression, noise management and pollution prevention, as described in the accompanying EIAR. 3.4 Planning and Regulatory Context The proposed development requires planning permission from MCC under the Planning and Development Act 2000 (as amended). This AA Screening Report accompanies the planning application and has been prepared to assist the competent authority in determining whether the proposed development, either alone or in combination with other plans or projects, is likely to have a significant effect on any European Site in accordance with Article 6(3) of the Habitats Directive and the European Communities (Birds and Natural Habitats) Regulations 2011 (as amended). The operational facility will also require an Industrial Emissions Licence (IEL) issued by the Environmental Protection Agency under the Environmental Protection Agency Act 1992 (as amended). The IEL will regulate emissions, environmental monitoring, reporting and operational performance through legally enforceable licence conditions. The proposed development will therefore be subject to statutory planning and environmental regulation throughout its construction and operational phases. The potential for likely significant effects on European Sites is assessed in Section 5 of this report. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 19 Section 4: BASELINE CONDITIONS This section describes the existing environmental conditions at the proposed development site, focusing on ecological, geological, hydrological, and hydrogeological characteristics. This baseline informs the screening of potential impacts on European sites in Section 5.3, using the Source-Pathway-Receptor (S-P-R) model outlined in Section 2. 4.1 Baseline Ecology The ecological baseline for the proposed development site was established through a desk study and field surveys undertaken in July 2024 and September 2025. A separate walkover survey of the proposed gas pipeline corridor between the proposed development site and Cootehill was also undertaken in June 2025 to inform the wider project assessment. The proposed gas pipeline does not form part of the planning application that is the subject of this AA Screening Report. The ecological surveys were undertaken in accordance with the Chartered Institute of Ecology and Environmental Management (CIEEM, 2024) Guidelines for Ecological Impact Assessment in the UK and Ireland (Version 1.3) and were designed to: • classify habitats in accordance with Fossitt (2000) A Guide to Habitats in Ireland; • identify the presence of Annex I habitats and Annex II species listed under the Habitats Directive (92/43/EEC), applying the precautionary principle; • identify invasive alien species listed under the European Communities (Birds and Natural Habitats) Regulations 2011 (as amended); • record protected and notable fauna and other ecological features; and • supplement field observations with records obtained from the National Biodiversity Data Centre (NBDC). The proposed development site extends to approximately 6.2 ha and comprises two agricultural fields dominated by improved agricultural grassland (GA1), bounded by managed hedgerows (WL1) with occasional mature trees (WL2). Agricultural drainage ditches (FW4) occur along sections of the site boundaries and a central drainage ditch follows the existing internal hedgerow. These habitats are characteristic of the surrounding agricultural landscape and provide local ecological connectivity, particularly for common farmland species. Immediately south of the proposed development site is an existing farmyard, farmhouse and associated residential property separated from the site by hedgerows and drainage ditches with scattered mature trees. The surrounding landscape is characterised by improved agricultural grassland, hedgerows, scattered woodland, small watercourses and drumlin topography typical of the locality. Surface water drainage from the site is currently provided by a network of agricultural land drains which discharge northwards before draining east towards the Coolkill Lough Stream. No natural watercourses occur within or immediately adjacent to the proposed development site. No Annex I habitats or Annex II species were recorded within the proposed development site during the ecological surveys. Similarly, no invasive alien plant species listed under the European Communities (Birds and Natural Habitats) Regulations 2011 (as amended) were identified within the proposed development site. The bird assemblage recorded during the surveys comprised common farmland and hedgerow species. No bird species that are Qualifying Interests or Special Conservation Interests of any European Site were recorded within the proposed development site. No badger (Meles meles) setts were recorded during the surveys, although the surrounding agricultural landscape may provide occasional foraging habitat. The proposed development site provides limited suitability for otter (Lutra lutra) owing to the absence of permanent watercourses and associated riparian habitat. No evidence of otter activity, RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 20 including holts, couches or spraints, was recorded during the surveys or within the vicinity of the site. Camera traps deployed on-site during August recorded fox (Vulpes vulpes) but did not record otter or badger activity during the survey period. The nearest EPA WFD-mapped reach of the Coolkill Lough Stream is located approximately 350 m east/north-east of the point of discharge from Proposed Development site. Detailed ecological survey findings and species-specific assessments are presented in the Biodiversity Chapter of the accompanying EIAR. Overall, the proposed development site comprises habitats that are typical of the surrounding agricultural landscape and are generally of low ecological value. The principal ecological features of relevance to this Appropriate Assessment Screening are the existing agricultural drainage network, which provides the only potential hydrological pathway to downstream European Sites, and the boundary hedgerows, which provide local ecological connectivity for common terrestrial fauna. The site is physically separated from all European Sites by substantial intervening distances. There is no direct ecological connectivity between the proposed development site and any European Site. The principal credible pathway identified between the Renewable Biogas Plant site and a European Site is the indirect downstream hydrological connection to Lough Oughter and Associated Loughs SAC via the Coolkill Lough Stream catchment. The indicative gas pipeline corridor follows the existing public road network and is largely confined to the carriageway and roadside verges. Habitats within the corridor are generally of low ecological value and comprise road verge grassland, managed hedgerows and existing highway infrastructure. No Annex I habitats or Annex II species were recorded along the indicative corridor. 4.2 Geology, Hydrology, and Hydrogeology This subsection outlines the geological, hydrological, and hydrogeological characteristics of the site, focusing on potential pathways to European sites identified in Section 5.3, using the S-P-R model. Data were sourced from the Geological Survey of Ireland (GSI) and the Environmental Protection Agency (EPA). 4.2.1 Geology The proposed development site is underlain by bedrock of the Red Island Formation, comprising predominantly greywacke, microconglomerate and argillite, as mapped by the Geological Survey Ireland (GSI). According to GSI mapping (2025), the site is overlain by glacial till derived from Palaeozoic sandstones and shales. These deposits are generally characterised by low permeability. No geological features of conservation importance occur within the proposed development site and there are no recorded karst features, geological faults or other preferential geological pathways that could provide a direct connection between the site and any European Site. The proposed development will not involve the extraction of geological resources or any activities that would directly affect geological features within a European Site. Consequently, the geology of the site does not provide a viable source–pathway–receptor linkage to any European Site. The nearest European Site is Kilroosky Lough Cluster SAC (Site Code: 001786), located approximately 12.2 km north - west of the proposed development site. 4.2.2 Hydrology Surface water drainage at the proposed development site currently comprises a network of agricultural land drains (FW4) located along the northern, eastern and western field boundaries, together with a drainage ditch located within the central hedgerow. These features collect and convey surface water runoff from the surrounding agricultural land. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 21 A land drain located along the northern boundary of the proposed development site conveys surface water eastwards via a culvert beneath the R189 before discharging to a downstream agricultural drain. This drainage network is hydrologically connected to the Coolkill Lough Stream (Waterbody Code: IE_NW_36D020700). The Coolkill Lough Stream subsequently flows through Coolkill Lough before joining the Rockcorry Stream. No natural watercourses occur within or immediately adjacent to the proposed development site, with surface water drainage currently provided by this network of agricultural land drains. As part of the proposed development, the existing drainage regime will be replaced by an engineered surface water management system incorporating attenuation, treatment and controlled discharge measures, as described within the accompanying Engineering Services Report and EIAR. These measures are designed to maintain the existing hydrological regime and manage surface water runoff from the developed site. The proposed development site is located within the Erne WFD Catchment (Catchment 36), the Dromore_sc_20 Sub - catchment, and the Dromore_070 River Sub-basin (EPA, 2025). The receiving waterbody is the Coolkill Lough Stream (IE_NW_36D020700), which is currently assigned Poor Ecological Status under the Water Framework Directive and is classified as At Risk of failing to achieve Good Ecological Status. According to the EPA, the principal pressure affecting the waterbody relates to its poor benthic invertebrate status, indicating existing ecological stress within the catchment. The nearest European Sites are: • Kilroosky Lough Cluster SAC (Site Code: 001786), located approximately 12.2 km north-west of the proposed development site; and • Lough Oughter and Associated Loughs SAC (Site Code: 000007), located approximately 14.8 km south-west of the proposed development site (approximately 38 km downstream by hydrological pathway). The potential hydrological pathways between the proposed development site and these European Sites are considered further within the Stage 1 Appropriate Assessment screening presented in Section 5. 4.2.3 Hydrogeology The proposed development site is underlain by the Red Island Formation bedrock aquifer, which is classified by the GSI) as a Poor Aquifer, generally unproductive except in localised zones. Groundwater vulnerability at the site is classified as Moderate, reflecting the nature and thickness of the overlying glacial till deposits. No significant karst features, regionally important aquifers or other hydrogeological features capable of facilitating rapid groundwater flow are recorded within or immediately adjacent to the proposed development site. Furthermore, the site is not located within a mapped Groundwater Dependent Terrestrial Ecosystem (GWDTE). The nearest European Sites are Kilroosky Lough Cluster SAC (Site Code: 001786), located approximately 12.2 km north - west, and Lough Oughter and Associated Loughs SAC (Site Code: 000007), located approximately 14.8 km south-west of the proposed development site. The Qualifying Interests of these SACs include natural eutrophic lakes, bog woodland and otter. None of these European Sites is hydraulically connected to the proposed development site via a significant groundwater pathway. Having regard to the hydrogeological setting, including the presence of a poorly productive bedrock aquifer, moderate groundwater vulnerability, the absence of karstic features and the substantial separation distances involved, there is limited potential for groundwater connectivity between the proposed development site and any European Site. The significance of any potential hydrogeological pathways is considered further within the Stage 1 Appropriate Assessment screening presented in Section 5. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 22 Section 5: STAGE 1. SCREENING FOR APPROPRIATE ASSESSMENT This section provides the Stage 1 Screening for AA to determine whether the proposed development either alone or in combination with other plans or projects, is likely to have significant effects on European sites. The screening follows the methodology outlined in Section 2, using the S-P-R model and adopts a precautionary approach in line with EU guidance (EC, 2021). This Stage 1 Appropriate Assessment Screening has been undertaken having regard to the Proposed Project as designed, including the standard engineering and operational characteristics which define the nature of the development and the potential sources and emissions arising from it. These inherent project characteristics include enclosed feedstock reception and processing, sealed anaerobic digestion and digestate storage systems, impermeable process areas, bunded storage and secondary containment, engineered surface water drainage, Sustainable Drainage Systems, attenuation and surface water treatment infrastructure, sealed process drainage and containment of process liquors. These features are standard functional, engineering, pollution-control and regulatory components of the Renewable Biogas Plant and would be incorporated into the design irrespective of the presence or absence of any European Site. They have therefore been taken into account in characterising the Proposed Project and identifying potential source- pathway-receptor linkages. No measure introduced specifically to avoid or reduce a harmful effect on a European Site has been relied upon in reaching the Stage 1 screening conclusion. Accordingly, this Stage 1 Appropriate Assessment Screening has been undertaken having regard to the proposed development as designed, including its embedded engineering and environmental protection measures. These include, but are not limited to: • enclosed feedstock reception, handling and processing areas • sealed anaerobic digestion and digestate storage systems; • impermeable process yards and bunded storage areas; • the permanent surface water management system incorporating attenuation and treatment; • permanent odour treatment infrastructure, including the biofilter and associated odour control systems; • combustion plant designed and assessed in accordance with the proposed emission characteristics; • containment and management of process liquors and drainage infrastructure; and • all other permanent engineering features forming part of the proposed development as described in Section 3 and assessed within the accompanying EIAR. These features have been considered as intrinsic components of the proposed development in characterising potential emissions and identifying source–pathway–receptor linkages. They are not mitigation measures introduced following the identification of likely significant effects but rather form part of the project being assessed. 5.1 Overview of Potential Impacts The proposed development has been reviewed to identify all potential source–pathway–receptor linkages that could give rise to likely significant effects on European Sites during both the construction and operational phases. The assessment has been undertaken on a precautionary basis and considers both direct and indirect pathways. The principal potential impact pathways identified are as follows: • Surface Water Pollution: During construction, earthworks, excavation, concrete works and the use of fuels, oils and other hazardous substances have the potential to result in sediment or contaminant runoff entering the existing agricultural drainage network and ultimately the Coolkill Lough Stream. During operation, accidental spillages associated with feedstock handling, digestate storage or vehicle movements could similarly affect surface water quality. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 23 • Groundwater Pollution: Construction activities involving excavation, accidental spillages or the handling of hazardous substances have the potential to affect groundwater locally. Operational activities have also been considered in the context of the site's hydrogeological setting. • Atmospheric Emissions: Operational emissions associated with the CHP units, boiler, digestate drying plant, odour control system and emergency flare have been considered as potential pathways for effects arising from air pollutants or nitrogen deposition on European Sites. • Noise, Vibration and Human Disturbance: Construction activities and operational plant, including vehicle movements and mechanical equipment, have the potential to generate noise and disturbance. The potential for such effects to extend to qualifying species associated with European Sites has been assessed. • Habitat Loss and Fragmentation: Vegetation clearance associated with the proposed development has been considered in relation to ecological connectivity and any potential indirect effects on European Sites. • Lighting: Operational lighting has been considered in terms of potential disturbance to nocturnal fauna and ecological corridors. • Traffic and Vehicle Movements: Construction traffic and operational HGV movements have been assessed in relation to accidental pollution, disturbance and any potential indirect effects on European Sites. • Digestate Management: Although the land spreading of digestate does not form part of the proposed development and is regulated under separate statutory controls, it has been considered as a reasonably foreseeable indirect activity associated with the operation of the facility. Each of these potential pathways is considered further within the screening assessment using the Source–Pathway– Receptor model to determine whether a credible pathway exists between the proposed development and the Qualifying Features of any European Site. 5.2 Determining the Likely Zone of Influence The ZoI for the proposed development has been established having regard to the nature, scale and location of the proposed development, the characteristics of the receiving environment, the ecological sensitivities of nearby European Sites, and the presence of any credible source–pathway–receptor linkages. In accordance with OPR Practice Note PN01 (2021), an initial search radius of 15 km was used to identify European Sites. However, the final ZoI has been refined based on the existence of viable impact pathways rather than distance alone. Hydrological Pathways Potential hydrological effects during both the construction and operational phases relate principally to the accidental release of sediment or other contaminants to the existing agricultural drainage network. Surface water runoff from the proposed development site currently drains via agricultural land drains to the Coolkill Lough Stream (Waterbody Code: IE_NW_36D020700), which subsequently flows to the Rockcorry Stream, the Dromore River and ultimately the Lough Oughter and Associated Loughs SAC (Site Code: 000007). Accordingly, Lough Oughter and Associated Loughs SAC has been included within the ZoI for assessment owing to the presence of a downstream hydrological connection. The potential significance of this pathway is assessed in the following sections having regard to the separation distance, intervening watercourses, dilution, settlement processes and the nature of the proposed development. No hydrological pathway exists between the proposed development site and Kilroosky Lough Cluster SAC (Site Code: 001786). Disturbance Pathways Potential disturbance effects during construction and operation include noise, vibration, lighting and increased human activity. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 24 Having regard to the nature of the proposed development, the surrounding agricultural landscape and the distances to the nearest European Sites, disturbance effects are only considered potentially relevant within the immediate vicinity of the proposed development site. A precautionary ZoI of 300 m has therefore been adopted for disturbance pathways, consistent with accepted ecological guidance for similar developments. No Qualifying Interest or Special Conservation Interest species associated with any European Site were recorded within this area during the ecological surveys. Air Quality Pathways Potential air quality effects include construction dust and operational emissions associated with the CHP units, boiler, digestate drying plant, emergency flare and odour control system. Construction dust effects are generally limited to the immediate vicinity of construction activities. Accordingly, a precautionary ZoI of 50 m has been adopted for construction dust, consistent with IAQM guidance. Operational emissions have been assessed separately within the Air Quality Chapter of the EIAR, including consideration of nitrogen oxides (NOx), ammonia (NH₃), particulate matter and nitrogen deposition. The findings of that assessment have been taken into account in the Stage 1 Appropriate Assessment screening. Groundwater Pathways The proposed development site is underlain by a poorly productive bedrock aquifer with moderate groundwater vulnerability. No significant groundwater pathways or hydrogeological connections to European Sites have been identified. Nevertheless, groundwater has been considered as a potential pathway within the screening assessment in accordance with the precautionary principle. Summary of the Zone of Influence Based on the characteristics of the proposed development and the receiving environment, the principal potential pathways requiring consideration within this Appropriate Assessment Screening comprise: • surface water pathways to downstream receiving waters; • groundwater pathways; • atmospheric emissions; • construction dust; • noise, vibration and lighting; and • accidental pollution events. The subsequent screening assessment considers whether any of these pathways could give rise to likely significant effects on the Qualifying Features of the identified European Sites, either alone or in combination with other plans or projects. 5.3 List of Relevant European Sites An initial search identified all European Sites within a 15 km radius of the proposed development site, in accordance with OPR Practice Note PN01 (2021). The list of sites was subsequently refined using the Source–Pathway–Receptor (S-P-R) model to identify those European Sites for which a credible impact pathway exists. Following this assessment, two Special Areas of Conservation (SACs) were identified for consideration within this Stage 1 Appropriate Assessment Screening (Table 1 and Figure 7). No Special Protection Areas (SPAs) occur within the 15 km search radius. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 25 • Kilroosky Lough Cluster SAC (Site Code: 001786) is located approximately 12.2 km north-west of the proposed development site. No direct or indirect hydrological connectivity exists between the proposed development site and this SAC. • Lough Oughter and Associated Loughs SAC (Site Code: 000007) is located approximately 14.8 km south-west of the proposed development site. A downstream hydrological connection exists via the agricultural drainage network, the Coolkill Lough Stream, the Rockcorry Stream and the Dromore River. Accordingly, this SAC has been taken forward for further assessment within this AA Screening. The Qualifying Interests and Specific Conservation Objectives for these European Sites are summarised in the following sections and considered in the Source–Pathway–Receptor assessment. Table 1: European Sites located within or connected to the ZoI Designated Site Site Code Straight-Line Distance from Proposed Development (km) Hydrological Connectivity Taken Forward for Assessment Kilroosky Lough Cluster SAC (001786) 12.2 km No Yes Lough Oughter and Associated Loughs SAC (000007) 14.8 km Yes (via Coolkill Lough Stream) Yes The Qualifying Interests and Specific Conservation Objectives of these European Sites are reviewed below before assessing each potential source–pathway–receptor linkage. Figure 7: European Sites within 15km of the Proposed Development RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 26 5.4 Description of Relevant European Sites A description of the relevant European sites, as identified in Section 5.3, is provided below. The descriptions are collated using site synopses, conservation objectives, and other documents available on the NPWS (https://www.npws.ie/protected-sites) and EPA (https://gis.epa.ie/EPAMaps/AAGeoTool) websites. 5.4.1 Kilroosky Lough Cluster SAC (001786) Kilroosky Lough Cluster SAC is located approximately 12.2 km north-west of the proposed development site. The SAC comprises a cluster of calcium-rich, oligo-mesotrophic lakes together with associated fen habitats. The site is of particular ecological importance for its extensive hard water lakes, Cladium fen (a priority habitat) and alkaline fen, all of which are listed on Annex I of the Habitats Directive. The SAC also supports white-clawed crayfish (Austropotamobius pallipes), an Annex II species whose conservation is closely linked to maintaining high water quality and low sediment inputs. The Specific Conservation Objectives (NPWS, 2016) seek to maintain or restore the favourable conservation condition of the following Qualifying Interests: Habitats • [3140] Hard oligo-mesotrophic waters with benthic vegetation of Chara spp.; • [7210] Calcareous fens with Cladium mariscus and species of the Caricion davallianae (priority habitat); and • [7230] Alkaline fens. Species • [1092] White-clawed crayfish (Austropotamobius pallipes) 5.4.2 Lough Oughter and Associated Loughs SAC (000007) Lough Oughter and Associated Loughs SAC is located approximately 14.8 km south-west of the proposed development site and is hydrologically connected via the Coolkill Lough Stream catchment. The SAC comprises an extensive network of lakes, waterways and wetlands within the Erne catchment. It supports important examples of Natural Eutrophic Lakes and Bog Woodland (a priority habitat) together with a population of Otter (Lutra lutra), all of which are Qualifying Interests of the SAC. The principal ecological sensitivities of the SAC relate to the maintenance of water quality, hydrological conditions and suitable habitat for otter. Existing pressures include nutrient enrichment from agricultural runoff, wastewater discharges and other catchment-scale land use activities. The Specific Conservation Objectives (NPWS, 2016) seek to maintain or restore the favourable conservation condition of the following Qualifying Interests: Habitats • [3150] Natural eutrophic lakes with Magnopotamion or Hydrocharition-type vegetation; and • [91D0] Bog woodland (priority habitat). Species RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 27 • [1355] Otter (Lutra lutra). The principal ecological sensitivities of the identified European Sites relate to the maintenance of high water quality, natural hydrological conditions and suitable habitat for the Qualifying Interests identified above. Consequently, the subsequent screening assessment focuses primarily on potential pathways associated with surface water, groundwater, atmospheric emissions, disturbance and accidental pollution. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 28 5.5 Screening of Relevant European Sites This subsection evaluates potential impacts on the European sites identified in Section 5.3, using the S-P-R model to determine if there are likely significant effects on their QFs. The assessment considers the potential impacts outlined in Section 5.1, the ZoI defined in Section 5.2, and the conservation objectives detailed in Section 5.4. The results are summarised in Table 2 below, which assesses impacts across multiple criteria, including direct, indirect, and in- combination effects, adopting a precautionary approach (EC, 2021). As set out in Section 5 above, this screening assessment has been undertaken having regard to the Proposed Project as designed, including the standard engineering and operational characteristics which would form part of the Proposed Project irrespective of the presence or absence of any European Site. These inherent project characteristics have been taken into account in identifying the nature and magnitude of potential emissions and source–pathway– receptor linkages. No additional or site-specific measure introduced for the purpose of avoiding or reducing a harmful effect on a European Site has been relied upon in reaching the Stage 1 screening conclusions.. Table 2: Screening Assessment of Relevant European Sites European site(s) and Approximate Distance Potential for Likely Significant Effects Screening Rationale Kilroosky Lough Cluster SAC (001786) Approx. 12.2 km north-west No Qualifying Interests: Hard oligo-mesotrophic waters with benthic vegetation of Chara spp. (3140), Calcareous fens with Cladium mariscus (7210*), Alkaline fens (7230) and White-clawed Crayfish (Austropotamobius pallipes) (1092). Direct Effects: The Renewable Biogas Plant and associated Linear Gas Grid Connection are located entirely outside the SAC. No land take, habitat loss, fragmentation or direct disturbance of the SAC or its Qualifying Interests will occur. Construction Phase: Construction of the Renewable Biogas Plant will comprise temporary earthworks, concrete works, building construction and installation of plant. Construction of the Linear Gas Grid Connection will comprise short-term trench excavation, predominantly within the existing public road corridor. Temporary construction activities have the potential to generate dust, noise, vibration and accidental pollution. However, no surface water or groundwater connection exists between the project and the SAC, and the SAC lies well beyond recognised screening distances for construction dust, noise and vibration. Consequently, no credible construction-phase source–pathway–receptor linkage exists. Operational Phase: The proposed development incorporates embedded engineering and environmental protection measures as integral components of the project design, including enclosed feedstock reception, sealed digestion and digestate storage systems, impermeable process areas, bunded storage, engineered drainage infrastructure, attenuation and treatment systems, and permanent odour treatment infrastructure comprising a biofilter and associated odour control systems. These embedded design measures have been incorporated into the Air Quality, Water Quality and Noise Assessments forming part of the accompanying EIAR. Chapter 13 Air Quality of the EIAR considers the potential for operational emissions to affect designated ecological receptors and identifies no SAC or SPA within a 10 km operational air- quality Zone of Influence. On that basis, no credible atmospheric pathway RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 29 capable of giving rise to a likely significant effect this European Sites has been identified. There is no hydrological or hydrogeological connectivity between the project and the SAC and the operational buried gas pipeline will not generate emissions or disturbance capable of affecting the SAC. Conclusion: Having regard to the absence of direct, hydrological and hydrogeological pathways, the separation distance, the findings of the accompanying technical assessments and the inherent characteristics of the proposed development, it can be excluded, on the basis of objective scientific information, that the proposed development, either alone or in combination with other plans or projects, will have a likely significant effect on Kilroosky Lough Cluster SAC. Lough Oughter and Associated Loughs SAC (000007) Approx. 14.8 km south-west (approximately 38 km downstream by hydrological pathway) No Qualifying Interests: Natural eutrophic lakes (3150), Bog woodland (91D0*) and Otter (Lutra lutra) (1355). Direct Effects: The Renewable Biogas Plant and associated Linear Gas Grid Connection are located entirely outside the SAC and no direct habitat loss or direct effects on the Qualifying Interests of the SAC will occur. Construction Phase: A downstream hydrological pathway exists between the Renewable Biogas Plant site and Lough Oughter and Associated Loughs SAC via the agricultural drainage network, Coolkill Lough Stream, Rockcorry Stream and Dromore River, over an approximate hydrological distance of 38 km. Construction of the Renewable Biogas Plant has the potential to generate conventional construction-related sources including sediment-laden runoff, excavation water and accidental releases. Construction of the Linear Gas Grid Connection will comprise temporary and progressive works, predominantly within the existing public road corridor. The manner in which the Proposed Project will be constructed is subject to generally applicable statutory requirements and established construction-industry good practice, including CIRIA guidance for the control of water pollution from construction sites and linear construction projects. These construction practices would apply to the works irrespective of the presence or absence of a European Site and have not been introduced in response to the downstream hydrological connection to Lough Oughter and Associated Loughs SAC. Having regard to the nature and scale of the construction activities, the standard manner in which such works will be undertaken, the approximately 38 km downstream hydrological separation, the extensive intervening watercourse network and the findings of the accompanying Water Framework Directive and Water assessments, there is no credible potential for construction of the Proposed Project to give rise to a likely significant effect on the Qualifying Interests of Lough Oughter and Associated Loughs SAC. Operational Phase: The Renewable Biogas Plant incorporates engineered surface water drainage, surface water treatment, attenuation, controlled discharge, impermeable process areas, bunded storage and secondary containment, sealed process drainage and containment of process liquors as inherent characteristics of the facility. These systems arise from the functional, engineering, drainage, pollution-control and regulatory RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 30 requirements of the facility and would form part of the Proposed Development irrespective of the presence or absence of any European Site. No untreated process wastewater will discharge to the receiving surface water network. Having regard to these inherent characteristics of the Proposed Development, the nature and magnitude of the resulting operational emissions, the approximately 38 km downstream hydrological pathway and the findings of the accompanying Water Framework Direc tive and Water assessments, no likely significant effect on the Qualifying Interests of Lough Oughter and Associated Loughs SAC is predicted. Once commissioned, the buried Linear Gas Grid Connection will comprise passive underground infrastructure and will not generate routine operational emissions, runoff, noise or disturbance capable of affecting the SAC. Conclusion: Although a downstream hydrological pathway exists, having regard to the nature and scale of the potential sources, the approximately 38 km hydrological separation, the intervening receiving-water network, the inherent characteristics of the Proposed Project and th e findings of the accompanying Water Framework Directive, Water, Air Quality, Noise and Biodiversity assessments, it can be excluded, on the basis of objective scientific information, that the Proposed Project will have a likely significant effect on Lough Oughter and Associated Loughs SAC.. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 31 Section 6: IN-COMBINATION AND CUMULATIVE EFFECTS Article 6(3) of the Habitats Directive requires consideration of whether the proposed development, either alone or in combination with other plans or projects, is likely to have a significant effect on any European Site in view of its conservation objectives. The purpose of the in-combination assessment is to determine whether the environmental effects of the proposed Renewable Biogas Plant and associated Linear Gas Grid Connection, when considered alongside existing, permitted and proposed developments, or relevant plans and programmes, could combine to give rise to likely significant effects on the European Sites identified in Section 5. 6.1: Assessment Methodology The in-combination assessment has been undertaken in accordance with the Department of Housing, Local Government and Heritage Appropriate Assessment of Plans and Projects in Ireland – Guidance for Planning Authorities (2010, updated 2023), OPR Practice Note PN01 (2021) and European Commission guidance (2021). To inform the assessment, the following information sources were reviewed: • Monaghan County Council Planning Register; • Cavan County Council Planning Register; • An Coimisiún Pleanála planning database; • Monaghan County Development Plan 2025–2031; • Cavan County Development Plan (where relevant to downstream hydrological pathways); • River Basin Management Plan for Ireland; • Inland Fisheries Ireland Corporate Plan 2021–2025 and Inland Fisheries Ireland Statement of Strategy 2026– 2030; • EPA licensed facilities and associated environmental information; and • Other existing, permitted and proposed developments located within the Coolkill Lough Stream catchment and the wider receiving catchment where overlapping impact pathways could reasonably occur. The assessment has focused on developments capable of sharing one or more of the following impact pathways with the proposed development: • surface water quality; • groundwater; • atmospheric emissions; • noise and disturbance; • habitat loss or fragmentation; and • traffic and construction activity. Projects which clearly do not share a source–pathway–receptor linkage with the identified European Sites have not been considered further. 6.2: Existing and Permitted Plans and Projects A review of planning applications and permitted developments within the vicinity of the proposed development identified a range of developments including: • one-off rural dwellings and domestic extensions; • agricultural buildings and livestock facilities; RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 32 • poultry developments; • commercial and industrial developments; • renewable energy developments; and • public infrastructure projects. These developments are summarised in Table 3. The majority comprise small-scale developments with localised environmental effects and do not share hydrological, atmospheric or ecological pathways with the European Sites identified during this assessment. The principal developments considered relevant to the in-combination assessment comprise: • agricultural developments within the Coolkill Lough Stream catchment; • existing and permitted poultry developments; • EPA licensed industrial developments; and • renewable energy infrastructure; Table 3: Other projects in the locality (source: eplanning.ie). Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect Monaghan County Council 2460274 Permission to construct a calf rearing livestock unit complete with concrete apron and drains. Significant Further Information received relates to a revised Site Layout Plan, a Nutrient Management Plan, Nitrogen Loading Details and other documents. 0.6 Although, this planning application is 0.6 km away from the redline boundary, the planning application is approximately 0.2 km away from the proposed gas pipeline. Potential for an in combination noise effect between the proposed gas pipeline and the planning application. Given the scale of the proposed gas pipeline and the planning application, this shall not result in any significant noise effects. Monaghan County Council 22229 Permission to erect a two storey dwelling house, insert a filter unit and percolation area and exit on to public road by way of existing entrance 1.3 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 22312 Permission consisting of erection of 1,300m2 or 250.24kWP of photovoltaic panels on the roofs of our existing manufacturing buildings, in the factory; with all associated site works 1.4 Although, this planning application is 1.4 km away from the redline boundary, it is adjacent to the proposed gas pipeline. This planning application shall not result in any habitat loss. Moreover, the planning application is approximately 950 m south of the Crosslea (IE_NW_36D020600) waterbody. Given the nature of the planning application, this is deemed a sufficient setback zone as to not result in any cumulative impact between the proposed development and the proposed gas pipeline. Monaghan County Council 21178 Permission for a development consisting of the decommissioning of existing septic tank and provision of a new wastewater treatment system and percolation area together with all associated site development works 2 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 21189 Permission to construct a two storey style dwelling house & detached domestic garage, install new mechanical effluent treatment system, 2 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 33 Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect raised/mounded soil based percolation area, new domestic entrance onto existing public road together with all ancillary site works Monaghan County Council 21177 Permission for a development consisting of a new two-storey dwelling, associated detached external store, opening of a new vehicular entrance to site and wastewater treatment system and percolation area together with all associated site development works. Significant further information relates to revised drawings. 2 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 2491 Permission to construct a new poultry unit together with new agricultural entrance, hardened areas, vertical meal bins, underground washings tanks and all ancillary site works 2.2 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 21506 Permission that consists of construction of a slatted cubicle house with underground slurry storage tank together with all ancillary site development works 2.3 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 21272 Permission for a development consisting of a new single storey extension to front and side of existing school, alterations to elevations, toilet facilities, multipurpose room, signage, connection to on site services and associated works 2.5 This planning application is greater than 200 m from any watercourse and the scale of the planning application is not large enough to contribute to the effects of the proposed development. Monaghan County Council 2560449 Permission for the proposed works will comprise of alterations to existing Potting Sheds and change of use to Artist's Studios (previously approved PL 19/574). Works will include an increase in floor area, alterations to the floor plan and elevations, development of a ramp access, canopy and alterations to the external staircase to the tower. Also pergola/ramp link between Potting Sheds and Dance Studio and internal alterations to Dance Studio. All to include external works and connections/alterations to site services and all associated site works. All within the curtilage of a Recorded Protected Structure, ref No. 41401716. 2.5 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 239013 Permission to revise the proposed development granted permission Planning Ref: 18/57, by providing for: a) extensions to the 2 No. Proposed poultry 2.6 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 34 Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect houses, and, b) a supplementary extension to the existing poultry house (in addition to the extension previously approved) together with all ancillary structures and ancillary site works on, and or, adjacent to an existing poultry farm. This application relates to a development, which is for the purposes of an activity (Licensing) Regulation 1994 to 2013. An Environmental Impact Assessment Report (EIAR) will be submitted with this planning application Monaghan County Council 22479 Permission to construct a new single storey art studio and use existing site entrance together with all ancillary site works 2.8 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 2460027 Permission for development consisting of the extension and renovation of existing terrace of 5 houses comprising of: 04 No. 02 storey, 03-bedroom houses and 01 No. 03 storey 04-bedroom house, upgrade existing foul and surface water connections to public sewers, together with all associated site works. 2.8 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Cavan County Council 2560192 To carry out the following alterations & works to an existing dwelling house. (1) To construct a new single storey extension to side of existing dwelling house building, and (2) To upgrade existing septic tank system to a new approved proprietary wastewater treatment system & percolation area, together with all associated site development works 2.8 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 2560015 Permission for the extension and renovation of the existing house, shop and the adjoining Gospel Hall comprising of: Provision of a new conference room and WC facilities on the ground floor with 1 no 3 bedroom apartment over, an additional detached Pastoral Hub to the rear, improved access and toilet facilities to the Gospel Hall and permanent retention of a storage shed and a car parking area, Significant Further Information relates to submitted, revised drawings 2.8 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 21223 Permission for development at this site at the building known as Anderson's Pub, Drum, Co. Monaghan. The building is as a 2.9 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 35 Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect protected structure of local importance in the Monaghan County Development Plan 2019- 2025 under the title 'Anderson's Pub' (ref. no.: Local 80). The development will consist of works including (i) alterations to the internal layouts of the previously approved planning application ref. 19/575 (ii) conversion of existing stores at ground floor level to guest accommodation with annex and the addition of new external steps to provide access, (iii) conversion of an alterations to 2 no. stables at lower ground floor to create guest accommodation, (iv) repair and thermal upgrade of the external fabric of the property including repair works to the existing windows, (v) refurbishment of glazing and shop front to front façade and (vi) all associated site works Monaghan County Council 22497; 20433 Permission for development consisting of: Expansion to existing facility to provide additional warehouse capacity of 443.50sqm, laboratory area of 327.2sqm, ancillary office & staff facilities of 951.10sqm over 4 storeys, with an overall height of 15.8m from ground level. The change of use of existing warehouse area to accommodate a tower which will facilitate ingredient storage & blending with a floor area of 2134.2sqm with an overall height 22.7m from ground level. Expansion to rear of existing facility to accommodate 4no.powder silos with floor area of 776.1sqm over 5 storeys. Overall height 20.8 metres from ground level. Additional first floor office of 42.8sq.m within existing warehouse. First floor 4.2 metres above ground floor, overall height 7m from ground level. Demolition and removal of existing prefabricated office building. Overall height 3m from ground level, floor area of 274.7sqm. New standalone water treatment plant, floor area of 463.6sqm and associated equipment, plant, yard & the height of highest tank is 15.4m from ground level. 3no. existing water tanks to be relocated from 2.9 This planning application had been appealed to An Coimisiún Pleanála whereby the latest appeal had a decision of ‘Application for leave refused.’ Thus, there is no potential for a cumulative effect between the proposed development and this planning application. An AA screening was undertaken for this development, which concluded that even in the absence of any mitigation measures there will be no significant effect, either individually or in combination with other plans or projects, on European site(s) in view of the site’s conservation objectives RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 36 Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect within existing facility & incorporated within new water treatment plant. 3no. existing water tanks and existing water treatment equipment to be removed off site. Installation of new 250mm diameter water ring main around the north and east of the existing facility building. Provision of a temporary construction compound to the north of existing car parks comprising a total of 1750sqm. Ancillary works will also include for; relocation of staff shelter, removal of existing bicycle shelter & provision of new bicycle shelter, realigning existing kerbing, relocation of underground surface water sampling points, associated car parking spaces which incorporates 10no. electric vehicle charge spaces along with associated ducting and services within the proposed car parks. All associated site development / construction works required to facilitate the proposal along with connection to existing foul water, storm water & service networks. The Abbott Ireland Cootehill site operates in compliance with a licence issued under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act,2003) An Coimisiún Pleanála (ACP) ACP 309119-21 110kV loop-in/loop-out substation including substation compound, associated electrical plant and apparatus 3.1 This Planning Application is not adjacent to any water body thus there is no hydrological connection between the planning application and the Proposed Development. Moreover, due to the distance between the planning application with the proposed development, there is no potential for the Proposed Development and this planning application to give rise to cumulative effects to habitat loss, noise disturbance and air quality effects that may negatively affect any European Sites. There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 19486 A ten year permission for the development of 8 no. wind turbines, each with a maximum tip height of up to 180 metres; and all associated site development, reinstatement, temporary and ancillary works including turbine foundations, crane hardstands 5 This Planning Application is not adjacent to any water body thus there is no hydrological connection between the planning application and the Proposed Development. Moreover, due to the distance between the planning application with the proposed development, there is no potential for the Proposed Development and this planning application to give rise to cumulative effects to habitat loss, noise RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 37 Planning Authority App Ref Number Development Description Distance from Red Line (km) Potential for Significant Cumulative Effect disturbance and air quality effects that may negatively affect any European site. There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 21510 To amend the approved development (Planning Reference: 16/507) of a temporary (25 years) solar farm to include photovoltaic panels with mounting frames on screw pile foundations, inverters, transformers, substation, DNO building, communications build 5.2 This Planning Application is adjacent to a river water body, however, there is no hydrological connection between the planning application and the Proposed Development. Moreover, due to the distance between the planning application and the proposed development, there is no potential for cumulative effects to arise to habitat loss, noise disturbance and air quality effects t5hat may negatively affect any European Sites. Monaghan County Council 21136 Permission to consist of a minor amendment to the development permitted under Monaghan County Council Planning Register Reference 19/486 to revise the alignment of the permitted access track between wind turbines T2 and T3. 5.5 This Planning Application is adjacent to a river water body, however, there is no hydrological connection between the planning application and the Proposed Development. Moreover, due to the distance between the Planning Application, there is no potential for the Proposed Development and this planning application to give rise to cumulative effects to habitat loss, noise disturbance and air quality effects. There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. Monaghan County Council 2660140 Retention of the existing single storey sports hall and associated site works at Tonnagh Rd., Rockcorry, Co. Monaghan 1.4 There is no pathway for a significant negative cumulative effect to occur to any ecological receptor between the Proposed Development and this planning application. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 38 Table 4: Plans associated with the Proposed Development Programmes, Plans and Projects High Level Overview of the Plan Key Policies/Issues/Objectives Directly Related to the Conservation of the Natura 2000 Network Potential for In-combination Effects Inland Fisheries Ireland Corporate Plan 2021 -2025 Inland Fisheries Ireland Statement of Strategy 2026–2030 This plan outlines the vision, mission , values and strategic objectives of IFI for the period of the plan (2021-2025). The IFI Corporate Plan outlines seven strategic objectives for 2021–2025, focusing on sustainable management of inland fisheries and ecosystems. Actions and outcomes aim to enhance biodiversity. Key objectives include habitat protection and fishery sustainability. Compliance with IFI objectives supports positive in-combination effects on European sites by enhancing aquatic biodiversity. The proposed development’s mitigation (e.g., silt control) complements IFI goals, ensuring no adverse cumulative impacts on fisheries or connected European sites. There was no identified actions or outcomes that will have a negative cumulative impact with the Proposed Development. Inland Fisheries Ireland Statement of Strategy 2026–2030 The Inland Fisheries Ireland Statement of Strategy 2026–2030 sets out IFI’s strategic direction for the five- year period 2026 to 2030. It reflects IFI’s statutory role in the protection, management and conservation of Ireland’s inland fisheries and sea angling resources and seeks to ensure that these resources are managed sustainably for current and future generations. The Strategy places emphasis on the protection and resilience of aquatic ecosystems, sustainable fisheries management, evidence-based decision-making, climate resilience and stakeholder engagement.. The Strategy includes objectives and actions directed towards protecting aquatic habitats and species, improving the resilience and ecological condition of inland waters, supporting sustainable fisheries management, responding to pressures arising from climate change and pollution, and working with public authorities and other stakeholders to protect and restore aquatic ecosystems. These objectives are consistent with the protection of water-dependent habitats and species which may form Qualifying Interests or Special Conservation Interests of European Sites. Implementation of the Strategy is directed towards the protection, conservation and sustainable management of inland fisheries and aquatic ecosystems. No objectives or actions have been identified which would be expected to combine with the Proposed Project to give rise to likely significant effects on a European Site. Accordingly, no likely significant in- combination effects are identified. Monaghan County Development Plan 2025 – 2031 This Plan was adopted on the 26th May 2025. This Plan provides an overarching strategy for the sustainable planning and development for County Monaghan for the period of the Plan. The following policies are considered relevant to the Proposed Development in conjunction with biodiversity: • EDP 4: The Best Available Technology (BAT) principle will be required to ensure the protection of the environment with regard to pollution mitigation in respect of proposed developments. The proposed development must comply with the Monaghan County Development Plan. This shall support a positive in-combination effect on European sites by enhancing and safeguarding biodiversity. The Monaghan County Development Plan’s policies and objectives , ensures there shall not RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 39 Programmes, Plans and Projects High Level Overview of the Plan Key Policies/Issues/Objectives Directly Related to the Conservation of the Natura 2000 Network Potential for In-combination Effects • HCLSO 1: To promote and encourage the conservation and preservation of the County’s natural environment, cultural heritage and amenities in accordance with legislation, plans and policies developed to specifically address these areas and to ensure a rich cultural landscape, healthy environment and the full provision of ecosystems services in the County. • HCLP 1: No projects giving rise to significant cumulative, direct, indirect or secondary impacts on European sites arising from their size or scale, land take, proximity, resource requirements, emissions (disposal to land, water or air), transportation requirements, duration of construction, operation, decommissioning or from any other effects shall be permitted on the basis of this plan (either individually or in combination with other plans or projects). • HCLP 2: To protect the landscapes and natural environments of the County by ensuring that any new developments in designated sensitive rural landscapes do not detrimentally impact on the character, integrity, distinctiveness or scenic value of the area. Any development which could unduly impact upon such landscapes shall be resisted. • HCLP 6: Protect, conserve and enhance natural heritage, insofar as practicable having regard to the remit of the Council; including European sites (SPAs and SACs), proposed Natura Heritage Areas (pNHAs), other designated sites, and non- designated areas of high nature conservation value known as locally important areas which also serve as ‘Stepping Stones’ for the purposes of Article 10 of the Habitats Directive, improving the ecological coherence of European sites • HLCP 7: Prevent the carrying out of development that would destroy or significantly alter, damage or interfere with the integrity of a pNHA/NHA, or any of its species, communities, habitats; landforms or geological or geomorphological features; or on its diversity of natural attributes • HLCP 8: Any plan or project which is likely to impact on the conservation objectives of a European site shall be screened for Appropriate Assessment (AA) and where pertinent, a Stage 2 Appropriate Assessment (Natura Impact Statement) shall be undertaken in order to make a determination. European sites outside the County and located within 15km of the be no adverse effects on European sites. There were no identified actions or outcomes that will have a negative cumulative impact with the Proposed Development. Any development associated with the Monaghan County Development Plan that may have the potential to give rise to negative effects to any European site shall be subject to EU Habitats Directive (Council Directive 92/43/EEC), specifically Article 6(3) ensuring that there will be no adverse effects to any European site individually or in combination with other projects. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 40 Programmes, Plans and Projects High Level Overview of the Plan Key Policies/Issues/Objectives Directly Related to the Conservation of the Natura 2000 Network Potential for In-combination Effects proposed development site should also be screened for Appropriate Assessment. A Natura Impact Statement shall incorporate a written statement which sets out mitigation measures to prevent the risk of invasive species on to a European site. • HCLP 9: Development within the vicinity of groundwater or surface water dependent European sites (Kilroosky Lough Cluster SAC) will not be permitted where there is potential for a likely significant impact upon the groundwater or surface water supply to the European site. Where appropriate, the applicant shall demonstrate with hydro-geological evidence, that the proposed development will not adversely affect the quality or quantity of groundwater or surface water supply to the European sites. • HCLP 10: The effects of agriculture related air pollution on habitats and species shall be considered by the Planning Authority when deciding on planning applications for significantly scaled agriculture development proposals. Where necessary, Applicants shall be asked to provide appropriate supporting air dispersion modelling and ecological assessment - completed in accordance with relevant guidelines -confirming proposals will not generate adverse effects on protected species or designated sites in Ireland or Northern Ireland. • ISO 1: To support, as appropriate, the National Parks and Wildlife Service’s efforts to seek to control and manage the spread of non-native invasive species on land and water. Where the presence of non-native invasive species is identified at the site of any proposed development or where the proposed activity has an elevated risk of resulting in the presence of these species, details of how these species will be managed and controlled will be required. • ISP 1: To ensure that development proposals do not lead to the spread of invasive species and to ensure that landscaping proposals do not include invasive species. The following objectives are considered relevant to the Proposed Development in conjunction with biodiversity: • AGFO 3 : To protect natural waters, wildlife habitats, conservation areas, heritage areas, prominent landscape features, archaeological sites, nature RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 41 Programmes, Plans and Projects High Level Overview of the Plan Key Policies/Issues/Objectives Directly Related to the Conservation of the Natura 2000 Network Potential for In-combination Effects designations and scenic routes within forest sites from pollution or injury. • HCLO 2: To contribute as appropriate towards the protection of designated sites in compliance with relevant EU Directives and applicable National Legislation. • HCLO 4: To support the implementation of any relevant recommendations contained in the National Biodiversity Action Plan 2020 - 2030, Heritage Ireland 2030, the All – Ireland Pollination Plan 2021 - 2025 and the National Peatlands Strategy and any new or updated/subsequent versions. • HCLO 12: To cumulatively contribute towards, in combination with other users and bodies, the achievement of the objectives of the regulatory framework for environmental protection and management, including compliance with EU Directives – such as the Habitats Directive (92/43/EEC, as amended), the Birds Directive (2009/147/EC), the Environmental Impact Assessment Directive (2011/92/EU, as amended by 2014/52/EC) and the Strategic Environmental Assessment Directive (2001/42/EC), and relevant transposing Regulations. • HCLO 18: A Construction Environmental Management Plan shall be prepared and implemented for all development projects, were appropriate, that may give rise to significant, adverse construction related environmental effects. • GIO 4: To contribute towards the protection and enhancement of biodiversity and ecological connectivity, including woodlands, trees, hedgerows, wetlands, rivers, streams, other landscape features and associated wildlife where these form part of the ecological network and/or may be considered as ecological corridors or stepping stones in the context of Article 10 of the Habitats Directive. • ISO 1: To support, as appropriate, the National Parks and Wildlife Service’s efforts to seek to control and manage the spread of non-native invasive species on land and water. Where the presence of non-native invasive species is identified at the site of any proposed development or where the proposed activity has an elevated risk of resulting in the presence of these species, details of how these species will be managed and controlled will be required. • REO 3: To facilitate the sustainable development, renewal and maintenance of energy generation infrastructure in order to maintain a secure energy supply RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 42 6.3: Assessment of Potential In-Combination Effects Surface Water Programmes, Plans and Projects High Level Overview of the Plan Key Policies/Issues/Objectives Directly Related to the Conservation of the Natura 2000 Network Potential for In-combination Effects while protecting the landscape, archaeological and built heritage and having regard to the provisions of the Habitats Directive and other environmental and ecological considerations. • REO 4: To support the production of sustainable energy from renewable sources such as wind, solar, bio-energy and the development of waste to energy/combined heat and power schemes at suitable locations and subject to compliance with the relevant planning policy, the Habitats Directive, and other environmental considerations. • REO 6: To support and promote the use of renewable energy technologies in the conversion and re-use of existing built developments • REO 10: To support the sustainable development, upgrading and maintenance of energy, generation, transmission, storage and distribution infrastructure, to ensure the security of energy supply and provide for future needs, whilst also ensuring the protection of the landscape, natural, archaeological and built heritage, and residential amenity. REO 12: Support and facilitate proposals for hybrid energy systems and/or co-location of renewable energy where applicable where such development has satisfactorily demonstrated that it will not have adverse impacts on the surrounding environment. The Water Action Plan 2024: A River Basin Management Plan This Plan outlines the measures necessary for the protection and restoration of water quality within the Republic of Ireland. The overarching aim of this plan is to ensure that all natural water resources are sustainably managed. This Plan comprises of a list of actions that must be achieved up until 2027. The following actions are considered relevant to the Proposed Development: • Hymo2: DHLGH will lead the development of a new enhanced and consolidated legislative regime to address pressures on the physical condition of waters. • Land-Use 1: Finalise guidelines for the incorporation of the Water Framework Directive into the planning system and rollout of training on the new water and planning guidelines to practitioners. • Land-Use 2: Legislative provision to give effect to the new Water and Planning Guidance to be progressed. Action 6.3: DHLGH will establish a Programme Delivery Office to oversee and co-ordinate the many relevant bodies that manage, implement and enforce legislation and policies relevant to the Water Framework Directive. Implementation ensures compliance with environmental objectives for water bodies, benefiting water-dependent habitats and species in European sites. No adverse in-combination effects with the proposed development are anticipated. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 43 The principal pathway through which potential in-combination effects could arise is via surface water. A downstream hydrological pathway exists from the Renewable Biogas Plant site through the Coolkill Lough Stream, Rockcorry Stream and Dromore River to Lough Oughter and Associated Loughs SAC. Construction of the Renewable Biogas Plant and Linear Gas Grid Connection has the potential to generate conventional temporary construction-related sources including sediment-laden runoff, excavation water and accidental releases. As described in Section 5, construction of the Proposed Project will be undertaken in accordance with generally applicable statutory requirements and established construction-industry good practice which apply irrespective of the presence of a European Site. During operation, the Renewable Biogas Plant incorporates standard inherent engineering features including engineered drainage, surface water treatment and attenuation, controlled discharge, impermeable process areas, secondary containment and management of process liquors. These features would form part of the facility irrespective of the presence or absence of a European Site. The accompanying Water Framework Directive and Water assessments conclude that the Proposed Project will not result in deterioration of the relevant receiving waterbodies. The projects and activities considered in Section 6.2 have been reviewed for the potential to give rise to overlapping hydrological pathways. Having regard to the nature and scale of the Proposed Project, the approximately 38 km downstream hydrological separation to Lough Oughter and Associated Loughs SAC, the intervening receiving-water network and the characteristics of the other projects considered, no likely significant in-combination effect on the Qualifying Interests of the SAC is predicted via the surface water pathway. No hydrological pathway exists between the Proposed Project and Kilroosky Lough Cluster SAC. Accordingly, no likely significant in-combination effect is identified in respect of that SAC via surface water. Atmospheric Emissions Potential cumulative atmospheric effects associated with ammonia, nitrogen oxides, particulate matter, acid deposition and nitrogen deposition have been considered. The accompanying Air Quality Assessment demonstrates that emissions associated with the proposed development, assessed on the basis of the embedded design of the facility, remain below the applicable screening thresholds for European Sites. Nearby developments comprise predominantly agricultural, residential and commercial developments which either: • are not significant atmospheric emission sources; or • are subject to separate environmental regulation. No overlapping atmospheric pathway has been identified capable of adversely affecting the Qualifying Interests of either European Site. Accordingly, no likely significant in-combination effects are predicted. Construction Activities Temporary cumulative construction activity may occur where other developments are being constructed concurrently with the proposed development. Construction of the Renewable Biogas Plant and Linear Gas Grid Connection will, however, be temporary in duration, localised in extent and progressively undertaken. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 44 The gas pipeline will be installed in discrete sections, limiting the spatial extent of active construction at any one time. Having regard to the nature, scale, temporary duration and progressive character of the construction activities, together with the substantial separation distances to the identified European Sites, no likely significant in-combination construction effect is predicted.. Noise, Vibration and Disturbance Temporary construction noise and operational noise have been considered together with other nearby developments. The identified European Sites are located well beyond recognised screening distances for construction noise, vibration and lighting. No Qualifying Interest species associated with these European Sites occur within distances where cumulative disturbance effects could arise. Accordingly, no likely significant in-combination effects are identified. Habitat Loss and Ecological Connectivity Habitat loss associated with the proposed development is confined to the application site and the associated pipeline corridor. No other developments reviewed would combine with the proposed development to result in habitat loss, habitat fragmentation or loss of ecological connectivity affecting the Qualifying Interests of the identified European Sites. 6.4 Conclusion The proposed Renewable Biogas Plant and associated Linear Gas Grid Connection have been assessed in combination with relevant statutory plans and programmes together with existing, permitted and proposed developments within the surrounding area and the receiving catchment. The assessment considered all credible overlapping source–pathway–receptor linkages including: • surface water; • groundwater; • atmospheric emissions; • construction activities; • noise and disturbance; • habitat loss and ecological connectivity; and • traffic. Having regard to: • the inherent characteristics of the Proposed Project, including standard engineering features incorporated irrespective of the presence or absence of a European Site; • the nature, scale and duration of the potential construction and operational sources associated with the Proposed Project; • the findings of the accompanying Water Framework Directive, Water, Air Quality, Noise and Biodiversity assessments; RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 45 • the temporary and progressive nature of construction of the Linear Gas Grid Connection; • the separation distances and intervening environmental pathways between the Proposed Project and the identified European Sites; and • the absence of any overlapping source-pathway-receptor linkage capable of giving rise to a likely significant in-combination effect on the Qualifying Interests of the identified European Sites, it can be excluded, on the basis of objective scientific information, that the proposed development, either alone or in combination with other plans or projects, will have a likely significant effect on: • Kilroosky Lough Cluster SAC (001786); or • Lough Oughter and Associated Loughs SAC (000007). Accordingly, the proposed development does not require progression to Stage 2 Appropriate Assessment (Natura Impact Statement). Section 7: SCREENING DETERMINATION This section presents the conclusions of the Stage 1 Appropriate Assessment Screening undertaken for the proposed Renewable Biogas Plant and associated Linear Gas Grid Connection in accordance with Article 6(3) of Council Directive 92/43/EEC (the Habitats Directive). The purpose of the screening has been to determine whether the proposed development, either alone or in combination with other plans or projects, is likely to have a significant effect on any European Site in view of its conservation objectives. 7.1 Summary of Screening Findings The Stage 1 Screening identified two European Sites for consideration in the screening assessment:: • Kilroosky Lough Cluster SAC (001786); and • Lough Oughter and Associated Loughs SAC (000007). The assessment was undertaken using the Source–Pathway–Receptor (S-P-R) model and considered both the Renewable Biogas Plant and the associated Linear Gas Grid Connection during the construction and operational phases of the proposed development. The assessment considered the Proposed Project as designed, including its standard inherent engineering and operational characteristics and the generally applicable manner in which construction works will be undertaken. As set out in Section 5, these features and practices would apply irrespective of the presence or absence of any European Site. No additional or site-specific measure introduced for the purpose of avoiding or reducing a harmful effect on a European Site has been relied upon in reaching the Stage 1 screening determination. The principal findings are summarised below. Kilroosky Lough Cluster SAC (001786) Kilroosky Lough Cluster SAC is located approximately 12.2 km north-west of the proposed development. The assessment identified no direct, hydrological, hydrogeological or atmospheric pathway between the proposed development and the SAC. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 46 The Renewable Biogas Plant and associated Linear Gas Grid Connection are located entirely outside the SAC and there is no potential for direct habitat loss or disturbance of the Qualifying Interests of the site. The accompanying Air Quality Assessment demonstrates that atmospheric emissions associated with the proposed development remain below the applicable screening thresholds for European Sites, while the accompanying Water Framework Directive Assessment and Chapter 10 Water (Hydrology & Hydrogeology) of the EIAR confirms that no hydrological pathway exists between the proposed development and this SAC. Accordingly, it can be excluded, on the basis of objective scientific information, that the proposed development will have a likely significant effect on Kilroosky Lough Cluster SAC. Lough Oughter and Associated Loughs SAC (000007) Lough Oughter and Associated Loughs SAC is located approximately 14.8 km from the proposed development, with an approximate downstream hydrological pathway of 38 km. A downstream hydrological pathway exists between the Renewable Biogas Plant site and Lough Oughter and Associated Loughs SAC via the Coolkill Lough Stream, Rockcorry Stream and Dromore River, over an approximate hydrological distance of 38 km. The assessment has had regard to the nature and scale of potential construction and operational sources, the substantial downstream separation, the intervening receiving-water network and the standard inherent engineering and operational characteristics of the Proposed Development. The accompanying Water Framework Directive and Water assessments conclude that no deterioration of the relevant receiving waterbodies is predicted, while the Air Quality, Noise and Biodiversity assessments do not identify another credible pathway capable of giving rise to a likely significant effect on the Qualifying Interests of the SAC. Accordingly, it can be excluded, on the basis of objective scientific information, that the Proposed Project will have a likely significant effect on Lough Oughter and Associated Loughs SAC. . In-combination Effects The proposed development was assessed in combination with relevant statutory plans and programmes together with existing, permitted and proposed developments within the surrounding area and the receiving catchment. No overlapping source–pathway–receptor linkages capable of affecting the identified European Sites were identified. Accordingly, it can be excluded, on the basis of objective scientific information, that the proposed development, either alone or in combination with other plans or projects, will have a likely significant effect on any European Site. 7.2 Screening Determination The proposed development: • is not directly connected with, or necessary to, the management of any European Site; • has been assessed in accordance with Article 6(3) of the Habitats Directive using the Source–Pathway– Receptor model; • has been assessed as comprising both the proposed Renewable Biogas Plant and the associated Linear Gas Grid Connection; RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 47 • has been assessed having regard to the standard inherent engineering and operational characteristics of the Proposed Project which would form part of the project irrespective of the presence or absence of a European Site; • does not rely upon any additional or site-specific mitigation measure introduced for the purpose of avoiding or reducing a harmful effect on a European Site in reaching the Stage 1 screening determination; • has been considered alongside the findings of the accompanying Water Quality, Air Quality, Noise and Biodiversity Assessments; and • has been assessed both alone and in combination with other plans and projects. On the basis of objective scientific information and applying the precautionary principle, it can be excluded that the proposed development, either alone or in combination with other plans or projects, will have a likely significant effect on: • Kilroosky Lough Cluster SAC (001786); or • Lough Oughter and Associated Loughs SAC (000007), in view of their conservation objectives. Accordingly, it is concluded that the proposed development does not require Stage 2 Appropriate Assessment, and the preparation of a Natura Impact Statement (NIS) is not required. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 48 Section 8: REFERENCES Balmer, D. E., Gillings, S., Caffrey, B. J., Swann, R. I., Downie, I. S., & Fuller, R. J. (2013). Bird Atlas 2007-11: The Breeding and Wintering Birds of Britain and Ireland. BTO Books, Thetford. Bang, P., & Dahlstrom, P. (2004). Animal Tracks and Signs. Oxford University Press, Oxford. Cavan County Council. (2022). Cavan County Development Plan 2022–2028. Cavan County Council, Cavan. Available at: https://www.cavancoco.ie/services/planning/development-plans/ (Accessed 9 October 2024). CIEEM. (2018). Guidelines for Ecological Impact Assessment in the UK and Ireland: Terrestrial, Freshwater, Coastal and Marine (2nd ed.). Chartered Institute of Ecology and Environmental Management, Winchester. Colhoun, K., & Cummins, S. (2013). Birds of conservation concern in Ireland 2014–2019. Irish Birds, 9, 523–544. Crowe, O. (2005). Ireland’s Wetlands and Their Waterbirds: Status and Distribution. BirdWatch Ireland, Newcastle, Co. Monaghan. Curtis, T. G. F., & McGough, H. N. (1988). The Irish Red Data Book 1: Vascular Plants. Stationery Office, Dublin. Department of Housing, Local Government and Heritage. (2024). EIA Portal. Available at: https://www.gov.ie/en/service/eia-portal/ (Accessed 9 October 2024). DoEHLG. (2010). Appropriate Assessment of Plans and Projects in Ireland: Guidance for Planning Authorities (Revised 2009). Department of the Environment, Heritage and Local Government, Dublin. EPA. (2022). EPA Maps. Environmental Protection Agency, Ireland. Available at: https://gis.epa.ie/EPAMaps/ (Accessed August 2022). Escauriaza, C., Paola, C., & Voller, V. R. (2017). Computational models of flow, sediment transport, and morphodynamics in rivers. In D. Tsutsumi & J. B. Laronne (Eds.), Gravel Bed Rivers: Processes and Disasters (pp. 123– 150). Wiley Blackwell. European Commission. (2000). Managing Natura 2000 Sites: The Provisions of Article 6 of the ‘Habitats’ Directive 92/43/EEC. Office for Official Publications of the European Communities, Luxembourg. European Commission. (2001). Assessment of Plans and Projects Significantly Affecting Natura 2000 Sites: Methodological Guidance on the Provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC. Office for Official Publications of the European Communities, Luxembourg. European Union. (1979). Council Directive 79/409/EEC of 2 April 1979 on the conservation of wild birds. Official Journal of the European Communities, L 103, 1–18. European Union. (1992). Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora. Official Journal of the European Communities, L 206, 7–50. Fossitt, J. A. (2000). A Guide to Habitats in Ireland. Heritage Council, Kilkenny. Hundt, L. (Ed.). (2012). Bat Surveys: Good Practice Guidelines (2nd ed.). Bat Conservation Trust, London. JNCC. (2004). Common Standards Monitoring Guidance for Terrestrial Mammals (Version August 2004). Joint Nature Conservation Committee, Peterborough. ISSN 1743-8160. RECEIVED: 28/08/2026 Proposed Renewable Biogas Plant, Drum August 2026 Screening For Appropriate Assessment 49 King, J. L., Marnell, F., Kingston, N., Rosell, R., Boylan, P., Caffrey, J. M., FitzPatrick, Ü., Gargan, P. G., Kelly, F. L., O’Grady, M. F., Poole, R., Roche, W. K., & Cassidy, D. (2011). Ireland Red List No. 5: Amphibians, Reptiles & Freshwater Fish. National Parks and Wildlife Service, Department of Arts, Heritage and the Gaeltacht, Dublin. Lundy, M. G., Aughney, T., Montgomery, W. I., & Roche, N. (2011). Landscape Conservation for Irish Bats & Species- Specific Roosting Characteristics. Bat Conservation Ireland, Cavan. Marnell, F., Kingston, N., & Looney, D. (2009). Ireland Red List No. 3: Terrestrial Mammals. National Parks and Wildlife Service, Department of the Environment, Heritage and Local Government, Dublin. Monaghan County Council. (2024). Planning Applications Search. Available at: https://planning.localgov.ie/en/search/application (Accessed August 2026). Nairn, R., & Fossitt, J. (2004). The ecological impacts of roads, and an approach to their assessment for national road schemes. In J. Davenport & J. L. Davenport (Eds.), The Effects of Human Transport on Ecosystems: Cars and Planes, Boats and Trains (pp. 98–114). Royal Irish Academy, Dublin. Nelson, B., Ronayne, C., & Thompson, R. (2011). Ireland Red List No. 6: Damselflies & Dragonflies (Odonata). National Parks and Wildlife Service, Department of the Environment, Heritage and Local Government, Dublin. NPWS. (2019). The Status of EU Protected Habitats and Species in Ireland: Habitat Assessments Volume 2. National Parks and Wildlife Service, Department of Culture, Heritage and the Gaeltacht, Dublin. NPWS. (2019). The Status of EU Protected Habitats and Species in Ireland: Species Assessments Volume 3. National Parks and Wildlife Service, Department of Culture, Heritage and the Gaeltacht, Dublin. NPWS. (2021a). Conservation Objectives: Kilroosky Lough Cluster SAC 001786 (Version 1). National Parks and Wildlife Service, Department of Housing, Local Government and Heritage, Dublin. NPWS. (2021b). Conservation Objectives: Lough Oughter and Associated Loughs SAC 000007 (Version 1). National Parks and Wildlife Service, Department of Housing, Local Government and Heritage, Dublin. NRA. (2008). Guidelines for the Treatment of Otters Prior to the Construction of National Road Schemes. National Roads Authority, Dublin. OPR. (2021). OPR Practice Note PN01: Appropriate Assessment Screening for Development Management. Office of the Planning Regulator, Dublin. Roche, N., Aughney, T., Marnell, F., & Lundy, M. (2014). Irish Bats in the 21st Century. Bat Conservation Ireland, Cavan Court of Justice of the European Union (2018), People Over Wind and Peter Sweetman v Coillte Teoranta, Case C - 323/17, ECLI:EU:C:2018:244. High Court (2019), Eoin Kelly v An Bord Pleanála [2019] IEHC 84. Court of Justice of the European Union (2023), Eco Advocacy CLG v An Bord Pleanála, Case C -721/21, ECLI:EU:C:2023:477. RECEIVED: 28/08/2026