HomeMy WebLinkAbout2660003 - Report Received from Internal Staff - EnvironmentENVIRONMENTAL REPORT
To: Donna McEvoy – A/Executive Scientist.
From: Martina McPhillips (Environment Section – Waste Team)
Re: 26/60003 Monaghan Harps GAA Club, Roosky, Monaghan Town, Co. Monaghan.
Consultants: Coyle Civil & Structural Ltd.
Permission: … permission will consist of construction of a new astro turf playing pitch with 2.40m
high metal perimeter fencing and associated netting (combined height 6.40m), 4 no.
12m high columns with 2 floodlights per column, changes to front elevation of existing
club house to include the removal of existing front door, to be replaced with a new
curtain panel system new storage/maintenance shed with a new car parking area,
connection to existing foul rising main and all associated site works.
Planner: Liam Ward
Date: 15/09/2026
__________________________________________________________________________________
Background
The following additional information was requested
I therefore request the following information.
A) Submit a revised site layout plan (Scale 1:500). This plan shall clearly mark
I. The existing and proposed storm water drainage system (blue) and the location
of any manholes and the outfall points and direction of flows.
II. The existing and proposed foul wastewater drainage system (red).
III. Submit details on the proposed car parking area to include
• How surface water arising from the proposed carpark will be
managed.
• Submit design specification details for petrol Interceptor to
demonstrate adequate capacity.
• Submit proposed finished i.e. Concrete/Tarmac for car parking
spaces.
• Include existing and proposed oil/petrol interceptors and the
location of outfall and drainage area.
The applicant has submitted a revised site layout plan as part of FI. Site layout plan
identifies the existing and proposed stormwater and foul drainage networks, associated
manholes, attenuation, separators, discharge point and drainage infrastructure. Details have
also been provided regarding the management of surface water from the proposed car
parking areas, including attenuation systems, swales and Class 1 bypass separators. Car park
finish is identified as tarmac.
B) Submit a Construction & Environmental Management Plan (CEMP) to Monaghan
County Council for consideration.
I. A Construction and Demolition Plan and By-Products Management Plan for the
proposed development works shall be provided using “Best Practice Guidelines
for the preparation of resource & waste management plans for construction and
demolition projects” – EPA, 2021.
II. An Asbestos survey and removal plan for the proposed development works.
I spoke with the agent with regards to 2(b) and 2(c) outlined in the request for further information.
The Agent confirmed there will be no significant structural upgrades apart from the removal of the
existing door and side windows. An asbestos survey and CDWMP will not be required.
C) Submit a site-specific Flood Risk Assessment.
Site-Specific Flood Risk Assessment prepared by Coyle Civil & Structural has been received as part of
FI. The report identifies potential sources of flooding including fluvial and pluvial flooding and rules
out coastal and groundwater flooding. Majority of the site lies within Flood Zone C and that the
proposed astro pitch does not interact with mapped flood extents.
The submitted Flood Risk Assessment acknowledges that sections of the proposed roadway and car
parking area may be subject to flooding during extreme flood events. The only mitigation measure
proposed is the installation of warning signage to alert users to the potential flood risk.
Report concludes that the proposed development is not expected to create an unacceptable flood risk
or worsen flooding in the surrounding area.
D) Submit a Confirmation of Feasibility from Uisce Éireann to assess feasibility and identify
necessary infrastructure upgrades to the development.
Applicant has not submitted a Confirmation of Feasibility letter from Uisce Éireann. However, a Pre-
Connection Enquiry for the proposed development has been received as part of FI.
Recommendations
I have no objection to planning subject to the following conditions:
a) Prior to commencement of development submit a fully completed water protection plan checklist.
b) The applicant shall submit evidence of confirmation of feasibility from Uisce Eireann to the
planning authority for new water & wastewater connections and continue to engage with Uisce
Eireann to obtain a connection agreement prior to commencement of development.
Or
The applicant shall sign a connection agreement with Irish Water prior to the commencement of
the development and adhere to the standards and conditions set out in that agreement.
c) Any construction and demolition waste or excess soil generated during the construction phase
which cannot be reused on site in accordance with Section 3 (1)(c) and Section 39 (1) of the Waste
Management Act 1996 as amended, shall be disposed/recovered at an appropriately permitted
facility in accordance with the requirements of the Waste Management Act 1996 as amended using
authorised waste collectors authorised to collect the type of material for disposal/recovery at
authorised treatment facilities.
d) If infilling material is required to be imported onsite the applicant or economic operator shall:
(i) Utilise EPA By-Product Regulation 27 in moving soil infill material from one site to another.
Official correspondence demonstrating Article 27 Registration with the EPA shall be
submitted to the Planning Authority prior to commencement of development.
Or
(ii) If using waste material as infill and prior to acceptance of material a valid permit must be
issued by Monaghan County Council in accordance with the Waste Management (Facility
Permit and Registration) Regulations 2007 as amended.
Or
(iii) Buy topsoil material as a product for final landscaping purposes only. Documentation
demonstrating purchase shall be submitted to Planning Authority.
e) The site shall be managed in a manner which prevents the discharge of polluting matter to any
ground or surface waters.
f) The applicant shall ensure that adequate measures and precautions are in place for the
construction phase to ensure there is no discharge of polluting matter/sediment laden waters
discharging from the site to any watercourse. These measures shall take account of the
Guidance produced by Inland Fisheries Ireland titled “Requirements for the Protection of
Fisheries Habitat during Construction and Development Works at River Sites”, available to
download at https://www.fisheriesireland.ie/documents/624-guidelines-on-protection-of-
fisheries-during-construction-works-in-and-adjacent-to-waters/file.html
g) Any accidental discharge, spillage or deposit of any polluting matter from the premises which
enters or is likely to enter any waters shall be reported to Monaghan County Council
Environment Section immediately.
h) All waste oils and any other hazardous waste materials shall be stored appropriately and
collected, recovered or disposed of in accordance with the Waste Management Act 1996 as
amended, and records of such shall be kept on site.
i) All hazardous liquid waste or oil/fuel storage containers, temporary or otherwise, shall be
bunded. All bunds will be designed to contain 110 % of the capacity of the largest storage
container located within the bund.
j) The applicant shall ensure completely separate foul and surface water drainage systems are
in place.
k) Facilities shall be provided for the collection and segregation of recyclable waste. Wastes shall
be collected for recycling/reuse whenever feasible or otherwise disposed of in accordance
with the Waste Management Act, 1996 as amended.
Prepared By:
Date: 15/09/2026
Environment Technician
Approved
Date: 15/09/2026
A/Executive Scientist