PLANNING AND DEVELOPMENT ACT 2000 (as amended)
Chief Executive's Order No
Reference Number
Name of Applicant
P986-26
26/60003
Monaghan Harps GAA Club
Address: Coyle Civil & Structural Ltd.
3 High St
Mullaghmonaghan
Co. Monaghan
H18 X635
Nature of Application: Permission will consist of construction of a new astro turf playing pitch
with 2.40m high metal perimeter fencing and associated netting
(combined height 6.40m), 4 no. 12m high columns with 2 floodlights
per column, changes to front elevation of existing club house to
include the removal of existing front door, to be replaced with a new
curtain panel system new storage/maintenance shed with a new car
parking area, connection to existing foul rising main and all associated
site works. Significant further information received includes a flood
risk assessment, landscaping details, additional drainage, and revised
maps.
Location of Development: Roosky
Monaghan Town,
Co. Monaghan
nRnFR•
I hereby decide, pursuant to the provisions of the Planning and Development Act 2000 (as amended)
and the Planning and Development Regulations 2001 (as amended) to grant permission for the above
development in accordance with documents submitted, subject to the 8 condition(s) set out in the
Schedule attached hereto.
I further decide that PERMISSION be granted subject to the same conditions on the expiration of the
period for the taking of an appeal to An Coimisiun Pleanala against this decision if there is then no
appeal before An Coimisiun Pleanala.
Adrian Hughes
SENIOR PLANNER
2J —k 2_
Date
26/60003 . Monaghan Harps GAA Club, Roosky, Monaghan Town, Co. Monaghan
a) Prior to commencement of development submit a fully completed water protection
plan checklist.
b) The applicant shall submit evidence of confirmation of feasibility from Uisce Eireann
to the planning authority for new water & wastewater connections and continue to
engage with Uisce Eireann to obtain a connection agreement prior to
commencement of development
or
The applicant shall sign a connection agreement with Irish Water prior to the
commencement of the development and adhere to the standards and conditions set
out in that agreement.
c) Any construction and demolition waste or excess soil generated during the
construction phase which cannot be reused on site in accordance with Section 3
(1)(c) and Section 39 (1) of the Waste Management Act 1996 as amended, shall be
disposed/recovered at an appropriately permitted facility in accordance with the
requirements of the Waste Management Act 1996 as amended using authorised
waste collectors authorised to collect the type of material for disposal/recovery at
authorised treatment facilities.
d)) If infilling material is required to be imported onsite the applicant shall conform to
one of the following;
(i) If utilising EPA Article 27 notification to move soil infill material from one site
to another, official correspondence from the EPA granting approval shall be
submitted to the Planning Authority prior to commencement of
development.
or
(ii) If using waste material as infill, a valid permit must be obtained from
Monaghan County Council under the Waste Management (Facility Permit
and Registration) Regulations 2007 as amended prior to acceptance of
material.
or
(iii) If buying topsoil material as a product for final landscaping purposes only,
documentation demonstrating purchase shall be submitted to Planning
Authority.
e) The site shall be managed in a manner which prevents the discharge of polluting
matter to any ground or surface waters.
f) The applicant shall ensure that adequate measures and precautions are in place for
the construction phase to ensure there is no discharge of polluting matter/sediment
laden waters discharging from the site to any watercourse. These measures shall
take account of the Guidance produced by Inland Fisheries Ireland titled
"Requirements for the Protection of Fisheries Habitat during Construction and
Development Works at River Sites".
g) Any accidental discharge, spillage or deposit of any polluting matter from the
premises which enters or is likely to enter any waters shall be reported to Monaghan
County Council Environment Section immediately.
h) All waste oils and any other hazardous waste materials shall be stored appropriately
and collected, recovered or disposed of in accordance with the Waste Management
Act 1996 as amended, and records of such shall be kept on site.
i) All hazardous liquid waste or oil/fuel storage containers, temporary or otherwise,
shall be bunded. All bunds will be designed to contain 110 % of the capacity of the
largest storage container located within the bund.
j) The applicant shall ensure completely separate foul and surface water drainage
systems are in place.
k) Facilities shall be provided for the collection and segregation of recyclable waste.
Wastes shall be collected for recycling/reuse whenever feasible or otherwise
disposed of in accordance with the Waste Management Act, 1996 as amended.
Reason: In the interest of environmental protection.
2. The mitigation measures contained within the site -specific flood risk assessment, as
prepared by Coyle Civil and Structural on, submitted to the Planning Authority on the
10/08/2026, shall be implemented in full.
Reason: In the interest of environmental protection and avoidance of flood risk.
3. Surface water drainage shall ensure that the proposed development will not exacerbate
flooding in the immediate vicinity or wider area and will not obstruct or impede important
flow paths.
Reason: In the interest of orderly development.
4. No other signs, flags, logos or other advertising material (or illumination) shall be erected on
the building, on -site, along the site boundary and/or at the roadside, unless exempt under
the Planning Development Regulations 2001 (as amended), or Full Planning Permission for
same is obtained.
Reason: In the interest of visual amenity.
5. a) Floodlights shall be cowled and directed away from residential properties, the public
road and the adjacent river.
b) Floodlights shall operate only between the hours of 08:00 and 22:30 unless
otherwise agreed in writing with the Planning Authority.
Reason: In the interests of residential amenity and traffic safety.
6. a) Existing mature trees and hedgerow defining the site boundaries shall be
permanently retained in this development, unless otherwise indicated on submitted
plans. They shall also be reinforced with additional planting as per the submitted
landscaping plan and protected from damage at all times, particularly during
building operations.
b) Notwithstanding the submitted landscaping plan, the new site boundaries shall be
planted with native hedgerow species so as to form naturalised hedgerows similar to
existing hedgerows in the vicinity. Predominant species shall be whitethorn, with
blackthorn, hazel and holly also included. Planting shall be in a double staggered row
with 8 (eight) 2-3 year -old plants per metre; 250mm apart, with 300mm between
rows.
c) Hedgerow planting, as required, shall be supplemented as per the submitted
landscaping plan with native tree species at irregular intervals. Species shall include
ash, oak, sycamore and beech.
d) Planting as required shall be carried out in the first planting season following
commencement of building operations and shall be permanently retained
thereafter. Any plant which fails in the first planting season shall be replaced. Trees
shall be allowed to mature and shall not be topped when trimming hedgerows.
e) Any boundary fencing shall be of stained wood
Reason: In the interest of visual amenity.
7. a) Ground levels and finished floor levels shall be as detailed on plans submitted to
Planning Authority on 08/01/2026, as amended by additional information on
04/09/2026.
b) Any facilitating cut and/or fill shall be graded to a natural contour to reflect the
existing topography of the area.
Reason: In the interests of orderly development.
8. The development shall be carried out in accordance with plans and documentation
submitted to the Planning Authority on 08/01/2026, as amended by additional information
on 04/09/2026, except as may otherwise be required in order to comply with the above
conditions.
Reason: To ensure a satisfactory standard of development.
Adrian Hughes Date
Senior Planner